Difference between revisions of "103.1 Bid Opening and Award Process"
m (add "practical design issues" to the text (came from "Interim Guidance")) |
m (Corrected link.) |
||
Line 40: | Line 40: | ||
An appropriate bid opening date should be established with the following considerations: | An appropriate bid opening date should be established with the following considerations: | ||
− | * Contract time needed for project completion, including the time a contractor needs to secure the required materials. [[# | + | * Contract time needed for project completion, including the time a contractor needs to secure the required materials. [[#103.1.3.2 Guidelines for Type of Work|Section 103.1.3.2]] provides guidelines for target award quarters depending on contract time. |
* Date when plans, specifications and estimate are complete, right of way clear, utilities clear, agreements executed. | * Date when plans, specifications and estimate are complete, right of way clear, utilities clear, agreements executed. | ||
* Uniform availability of work around the state (reviewed by the Design Division). | * Uniform availability of work around the state (reviewed by the Design Division). |
Revision as of 08:05, 11 June 2008
Additional Information |
PS&E Due Date Chart |
Reviewers Checklist |
Forms |
Award Letter |
Contents
- 1 103.1.1 Introduction
- 2 103.1.2 Bid Opening Location
- 3 103.1.3 Establishing Project Bid Opening Dates
- 4 103.1.4 Requesting Bid Opening Schedule Changes
- 5 103.1.5 Packaging Projects for Bid Opening
- 6 103.1.6 Assembling Bidding Documents
- 7 103.1.7 Advertising Projects for Bid opening and Purchasing Bidding Documents
- 8 103.1.8 Engineer's Estimate
- 9 103.1.9 Bid Opening
- 10 103.1.10 Bid Analysis Process
- 11 103.1.11 Recommendation for Award or Rejection of Bids
103.1.1 Introduction
The goal of MoDOT’s bid opening and award process is to achieve competitive bids by packaging projects in a manner that makes them as attractive as possible to potential bidders. Methods of achieving this goal include, but are not limited to, establishing appropriate bid opening dates for the type of work, maintaining a stable bid opening schedule, and grouping or dividing projects to make them more appealing to bidders.
103.1.2 Bid Opening Location
Design will conduct bid openings for all projects within the right-of-way of the state highway system, with two exceptions. Districts may conduct bid openings for “maintenance by contract” projects that cost less than $25,000 or in the case of an “emergency”. All other contracted work must be included in the regularly scheduled monthly bid openings held in Jefferson City.
Emergency projects are defined as those situations in which conditions threaten the movement of traffic. These situations include:
- The road or a lane of the road is closed,
- Existing conditions threaten to close the road,
- There is risk to the safety of the motoring public.
In most cases, standard advertising requirements may be shortened for emergency projects. The Design Division will work with the district to determine an appropriate advertising period for emergency projects on a case-by-case basis. It should be noted, bid guaranties (bid bonds) and contract bonds are required on all projects, including emergency projects.
For maintenance funded contract work with an estimated cost of $25,000 or less, most aspects of the bid opening (i.e. advertising, proposal preparation, opening and award) can be performed in the district. However, Design Division staff is available to assist the district with these items or to perform them for the district. Advertising for these projects shall follow the provisions contained in Section 102.1.7. In addition, bid guaranties (bid bonds) and contract bonds are required on all projects, including maintenance by contract projects. In addition, projects should be combined into efficient combinations so contractors can provide cost effective bids.
103.1.3 Establishing Project Bid Opening Dates
103.1.3.1 General
An appropriate bid opening date should be established with the following considerations:
- Contract time needed for project completion, including the time a contractor needs to secure the required materials. Section 103.1.3.2 provides guidelines for target award quarters depending on contract time.
- Date when plans, specifications and estimate are complete, right of way clear, utilities clear, agreements executed.
- Uniform availability of work around the state (reviewed by the Design Division).
- Availability of funding. The district should work with the Transportation Planning Division to insure funding is available and to include projects in the Statewide Transportation Improvement Program.
103.1.3.2 Guidelines for Type of Work
Guidelines that may be used in developing preliminary award quarters for a project are listed below. They are based on MoDOT’s low bid experience, categorized by type of work and approximate cost of major work items. These are general guidelines, not rules, and exceptions do exist. This information is only a starting point and the project manager should draw upon the experience of district operations personnel or Design Division as necessary. Note: the number of days specified below refers to working days and not calendar days:
- 1st Quarter – (July, August & September)
- Major bridges - over $5 Million
- Large multi-year corridor projects – over $10 Million
- Large urban widening projects – over $3 Million and/or more than 120 days
- Small maintenance jobs (July & August) – under $250,000 and/or less than 30 days
- Large asphalt or portland cement concrete paving projects – over $10 Million
- Annual maintenance contracts (“on-call” work)
- 2nd Quarter – (October, November & December)
- Major asphalt paving projects - $4-8 Million and/or contract time 90-120 days
- Major portland cement concrete paving projects – up to $10 Million and/or 90-120 days
- Urban widening & rehabilitation - $2-3 Million and/or less than 120 days
- Leveling course program – October and November
- Mowing projects - October, November and December
- Bridge replacements (steel girders) – under $2 Million
- Large grading projects – 90 – 120 working days
- 3rd Quarter – (January, February & March)
- Leveling course program – January and February
- Asphalt resurfacing projects – less than $4 Million
- Urban widening & rehabilitation – less than $2 Million or less than 90 days
- Bridge replacements (concrete) – under $2 Million or less than 120 days
- Large bridge rehabilitation - $1-3 Million
- Bridge rehabilitation involving low slump, latex modified, or silica fume concrete
- 4th Quarter – (April, May & June)
- Smaller maintenance projects (completion in current season) – less than $500,000
- Bridges replacements - $2-5 Million
- Large multi-year corridor projects – over $10 Million
- Miscellaneous projects – under $1 Million and/or less than 60 days
- Annual maintenance contracts (“on-call” work)
103.1.4 Requesting Bid Opening Schedule Changes
Once a project has been programmed in the Statewide Transportation Improvement Program, it is a MoDOT commitment. Further, contractors plan their work according to the bid opening schedule so maintaining its stability is crucial to receiving competitive bids. Every effort must be made to deliver the project on time and within budget. However, if circumstances require a project not be let at the committed bid opening date, the district shall request a change in the bid opening schedule through Transportation Planning. The District Engineer must approve jobs moving to a new fiscal year.
103.1.5 Packaging Projects for Bid Opening
It is desirable to “package” projects to make them as attractive to bidders as possible, particularly in areas of the state with limited competition. Design is available for consultation in determining prospective bid competition. Similarly the Design Division can assist the district in developing attractively packaged projects.
Small projects may need to be combined, while large projects may need to be split apart. Materials availability is also a concern when scheduling certain work types. The number of different work types should be reduced as much as practical (i.e., a small quantity of asphalt with a small quantity of concrete). For certain particularly complex projects, there is a benefit to having one contractor in charge of the entire project. Permitted combinations are generally used when several similar type projects are to be constructed in an area with a good history of competitive bidding (i.e. both large and small contractors are available to do the work). This combination allows for the greatest competition among all contractors. Bidders may bid on any or all of the combination, and will usually bid "all or none". Required combinations are recommended for several small projects with similar work within a reasonable distance from one another. Packaging them together often makes them “economically attractive” to more bidders. Required combinations are also helpful when combining a medium to large project with a single small project in an area. The small project alone may not attract any bidders. Combining it with a more desirable project will increase its chance of being completed.
103.1.6 Assembling Bidding Documents
When the plans, specifications and estimate are submitted by a district, the Bidding and Contract Services Section of Design is responsible for assembling all of the required information into bidding documents that consist of: Request for Bid, Bid Proposal, and Contract Plans. The Bidding and Contract Services unit of Design uses a checklist while processing the plans, specification and estimate and assembling bidding documents. The checklist identifies the necessary documents that the district must provide with the plan submittal and common errors found in the review of plans. The process begins by making sure all necessary documents have been submitted. This includes the following:
- All district plans, consultant plans, bridge plans, and any utility relocation or other miscellaneous plans, job special provisions, and estimates have been submitted.
- The status of R/W, utilities, and railroad work has been submitted. If the contractor's access to the project is limited due to right of way or utility problems the district should refer to the "Commission Procedure for Liability Acceptance") to determine an appropriate plan of action as early in the process as possible. Once the plans have been submitted, a committee consisting of the appropriate Design Liaison Engineer and the Assistant State Design Engineer review the project for applicability to the "Commission Procedure for Liability Acceptance". If a determination of how to proceed cannot be made by this committee, the matter is referred to the Chief Counsel's Office. In either case, at this point it is often too late to cure restrictions on the contractor's ability to have full and free access to the project, thus creating an acceptance of liability risk if the project remains in the scheduled bid opening. If the job special provisions are not or cannot be drafted to adequately deal with these risks, the Chief Counsel's Office will request a delay in the bid opening.
- Proper Corps of Engineers 404 and Missouri Department of Natural Resources 401 permits have been issued.
- Municipal, county or other funding agreements have been executed, and funds have been deposited as required by the agreement.
103.1.6.1 Assembling Request for Bid
The orange-covered Request for Bid is made up of 3 components: The "boilerplate" contract pages, the itemized bid, and the job special provisions.
103.1.6.1.1 Assembling "Boilerplate" Contract Pages
The Bidding and Contract Services unit performs the following steps to assemble the "boilerplate" contract pages:
- Preliminary review of plans, specifications and estimate, including the workday study to provide the job description and insure adequate contract time.
- Obtain the required DBE percentage and trainee goal for the project from the External Civil Rights Office.
- Insert job number, project description, bid opening date, contract time, liquidated damages, and DBE percentage/Trainee Goal into a standard format for either a federal-aid or state project contract.
- Insure all supporting documents are included with the Request for Bid, including any necessary permits, asbestos survey inspection sheets, electronic geotechnical data, etc.
103.1.6.1.2 Assembling Itemized Bid Pages
The Bidding and Contract Services unit performs the following steps to assemble the itemized bid:
- Check that quantities on 2B sheets match quantities and pay items on the estimate and tabulation of quantities.
- Verify that all pay item numbers are on the current listing of standard pay items.
- Verify all lines on the itemized bid list are consistent with the bidding proposal and include lines for “section total” for roadway items and “section total” for bridge items”, etc.
- Add coding for permitted/required combinations and alternate paving jobs.
- Insure estimate split-outs for financing by others are calculated correctly.
- Create itemized bid sheets for Request for Bid.
103.1.6.1.3 Assembling Job Special Provisions
The Bidding and Contract Services unit performs the following steps to assemble the job special provisions:
- Proofread job special provisions, and format where necessary.
- Insure that the current standardized job special provisions are used.
- Spot check for commonly missed job special provisions.
- Add appropriate "General" special provision indicating current required wage rate provisions and other job special provisions to be inserted by Central Office.
103.1.6.2 Assembling Bid Proposal
The blue-covered Bid Proposal is assembled by the Bidding and Contract Services unit and is used by the contractor to submit their bid. It is identical to the Request for Bid, except that it does not include the job special provisions. In addition, the pages to be filled out by the bidder are printed on colored paper.
103.1.6.3 Assembling Contract Plans
The contract plans are a compilation of roadway plans, bridge plans, and any other miscellaneous plans that may be included in the scope of the project (i.e. utility relocation plans). The Bidding and Contract Services unit performs the following steps to assemble the contract plans:
- Review plans for implementation of practical design. Some practical design issues identified at this time include:
- Superpave on minor routes
- Bridge approach slabs on minor routes
- Full depth shoulders
- Shoulder paving on minor routes
- Pavement thicknesses exceeding existing
- Optional and alternate pavement not used
- Bridge replacement projects with large quantities of pavement replacement
- Excessive bridge widths on minor routes
- Temporary bypasses
- Bridge stage construction instead of road closure
- Bridge design frequencies too high
- Bridge lengths longer that existing
- Safety zones on minor routes
- Unbalanced earthwork
- Verify pavement design and typical sections concur with the pavement group recommendation.
- Check plans against title sheet index to be sure all plans have been included. Combine bridge plans with roadway plans. Insure plans have been signed and sealed.
- Verify that the most current standard plan sheets and other special sheets have been used.
- Review plans for commonly missed items.
- Create 2A sheet from the estimate.
103.1.6.4 Time Requirements for Assembling and Printing Bid Documents
Under ideal circumstances, it should take approximately a week to process a set of plans and a day or two to print the bidding documents, allowing a minimum of two weeks for review of and changes to the preliminary bidding documents prior to advertising the project for bid opening. A chart identifying the bid opening dates, PS&E due dates and print dates is established by the Design Division. It is important that the districts comply with this schedule to insure efficient processing and printing of the projects.
103.1.6.5 Electronic Posting of Bid Documents
Once the bid documents are complete, the Design Division posts an electronic version of the itemized proposal for each project on MoDOT’s website. These files may be downloaded and completed by contractors using ExpediteTM software. A contractor may print a copy of his completed itemized proposal and return it as part of his submitted bid. Advantages to using the electronic itemized proposal include: less data entry time for the contractor, less chance for mathematical errors and omissions in the bidding process and more legible bids.
The contractor may submit bids electronically via the internet. Bids submitted electronically shall use the latest version of Trns Port Expedite Bid, and be submitted using the BidExpress® website. Guidelines for How To Submit Bids Electronically are available on MoDOT’s website.
The Design Division also provides electronic files of bidding documents to approved external groups that post them in private electronic plans rooms. These electronic plans rooms allow subscribing members to view electronic versions of bidding documents and order printed versions of the documents. Advantages to sharing the documents in these electronic plan rooms include: quick access to bidding documents by potential bidders, communications with a broader competition base and better opportunities for connections between prime contractors and subcontractors.
103.1.6.6 Changes to Bid Documents
The method of correcting errors in bidding documents is dependent on both the magnitude of the error, and when the error is discovered. The Bidding and Contract Services unit will evaluate whether a change to the bidding documents is necessary and what impacts the addendum may have on the bid. If the error is discovered before the bidding documents are printed, the correction is fairly simple unless it requires redesign and re-submittal of signed and sealed plans, specifications and estimate. This will require from a few days to several weeks.
If the error is discovered after the project is advertised, then the change has to be made manually to the bidding documents as described above, plus it must be sent as an addendum by express mail or “return-receipt” fax to all plan holders and an electronic copy of the addendum are posted to the MoDOT web site, which is a complicated and costly process. If the express mail receipt or fax form is not returned, the plan holders must be contacted by telephone to verify whether or not the addendum was received, and if not, the addendum must be re-faxed to that bidder. Bids that do not include all addenda issued may be declared non-responsive, and again, the result may be unfair competition.
If the error is undetected by MoDOT, but is recognized by a few of the bidders, the result is unfair competition. The bidders that are aware of the error may unbalance their bids, again resulting in unfair competition.
Errors in the bidding documents have caused the Commission to reject all bids on projects. This decision delays the construction of the project, and results in additional costs in re-advertising and re-bidding the project. If the project is awarded, then the Commission
- is likely to pay for change orders in addition to the original contract amount which affects the district's budget,
- is exposed to a claim/law suit from the successful bidder for either more money or more contract time or both,
- is exposed to a law suit from the unsuccessful bidders that had they known the true nature of the project, they could have provided lower bids,
- is at risk of criticism from FHWA and the State Auditor that MoDOT added work to a contract that did not go through the required competitive bidding process.
103.1.7 Advertising Projects for Bid opening and Purchasing Bidding Documents
Under state law, projects must be advertised for bid opening in a newspaper published in the county in which the project will be constructed. Further, FHWA requires a project be advertised at least three weeks before bids are to be received. In addition to newspaper advertisements, MoDOT also issues a Notice of Bid Opening, which is available on the MoDOT web site. MoDOT, at the request of the AGC, has chosen to use a minimum five-week advertising period to allow contractors adequate time to properly prepare their bids. Once the project has been advertised for bid opening, contractors and suppliers may purchase the Contract Plans or Requests for Bid. All purchases of Requests for Bid or Contract Plans are recorded. When ordering the plans, the contractor has the option to be identified as a plan holder. This "Plan Holders List" is presently available to the public and is located on MoDOT’s website.
103.1.8 Engineer's Estimate
As an independent assessment of a projects cost, the “final engineers’ estimate” is completed by the Bidding and Contract Services unit of the Design Division. This estimate is not publicly released and is the basis for the award or rejection of bids for a project. The final engineers estimate is derived with careful consideration of project specific conditions and industry trends. This is accomplished by:
- Utilizing cost base analysis and past history of project specific items.
- Conducting field checks of potentially complex projects.
- Continuous communication with contractors and suppliers concerning construction techniques and availability of materials.
103.1.9 Bid Opening
Bidders may submit paper bids or bids electronically using the BidExpress® website. Only bidders who have a Contractor Questionnaire on file seven days before bid opening are permitted to submit bids for a project. The list of qualified bidders is kept by the Central Office Construction Division and provided to the Secretary to the Commission. Bidders that choose to submit bids via the internet shall have on file with the Commission an “Internet Bidding Agreement”, a copy of which can be found on MoDOT’s website. This agreement shall be initiated by the prospective bidder and submitted to the Commission. A bid will not be opened and read unless a fully executed agreement is on file with the Commission at least seven days prior to the time set for the opening of the bids.
Paper bids are delivered to the Commission Secretary's Office by 11:00 a.m. on bid opening day, and qualified bids are logged in as they arrive. At 11:00 a.m. the paper bids are opened and the electronic bids are uploaded from the BidExpress® website. All bids are given a cursory check to insure all required documents are submitted by the bidder. The bids are then marked for public reading by the State Design Engineer. Bids are read in the Commission Hearing Room to an audience of mostly contractors. The "Bids As Read" report is available on the Internet and as a printed document during the bid opening process. The Bids as Read on the BidExpress® website are called Apparent Bid Results and are generated immediately after all bids are uploaded during the letting. MoDOT also generates the Bids as Read report and posts it to the MoDOT website, generally no later than 12:00 noon. MoDOT’s Bids as Read report provides additional information that is not provided on the BidExpress® website, including maximum monetary, the pavement type for alternate bid projects and how the contractor bid on permitted combination projects. Guidelines for viewing the two versions of Bids As Read are posted on MoDOT’s website.
Each individual item of the paper bids is then entered into the computer. Any discrepancy between bids as read, and bids as tabulated through the computer, are investigated and resolved by the Bidding and Contract Services unit. The bids as tabulated through the computer are the official bids. "Bid Tabulations" which show itemized bids are then printed, along with the "Summary of Bid Opening" which shows the totals for the low and second low bidder for each job. The total bids shown on the Summary of Bid Opening are public information. However, the individual item bids shown on the Bid Tabulations are not made public until the Commission awards a project. These items are not made public when the Commission rejects all bids for a project. A confidential report showing an itemized comparison of the low bid to the final engineer's estimate is produced for bid analysis purposes. Once the Commission awards or rejects the projects at the Commission meeting, the Bid Awards and Bid Tabulations for awarded projects are distributed. Letters are prepared to contractors who have been awarded jobs informing them of their notice to proceed date, and the bid opening information is posted to the MODOT web site by the Design Division.
103.1.10 Bid Analysis Process
Bids deviate from the final engineers estimate, sometimes significantly, for many reasons. Consideration of the number and quality of bidders, and the disparity among the bidders is the first step of the overall analysis. After this step, the low bidder's price for each individual item is compared to the final engineer's estimate for these items. The Bidding and Contract Services unit notes major deviations and irregularities, such as unbalanced bidding, and investigates, as necessary. Information concerning these situations, when detected, is discussed with the appropriate Central Office personnel and can be grounds for rejection of the bid on a project.
103.1.11 Recommendation for Award or Rejection of Bids
Contract Services staff meets with the State Design Engineer after a thorough review of the bids, to discuss the bids received and make their recommendations for project awards. The State Design Engineer discusses the bid information with senior managers where the final recommendation to the Commission for award or rejection of the project is drafted. Prior concurrence of the Division Administrator of FHWA is required for there to be a recommendation to award a federal participation project. The final recommendation is presented to the Commission at its monthly meeting, generally one to two weeks following the bid opening.
Commissioners are provided with all pertinent information from the bid opening including the final engineer's estimate. After the recommendations are presented, the Commission decides whether to award a contract for construction or reject bids on individual projects. The Commission reserves the right to award or reject any or all bids on any project.
A meeting with the low bidder may be held following the Commission’s action on projects that are rejected. The meeting involves Central Office staff, district staff, and the contractor. They discuss any items that were bid excessively high or ways to improve the constructability of the project. These ideas may then be incorporated into a future request for bids on the project.
Sec. 103 of the Missouri Standard Specifications for Highway Construction outlines procedures and obligations involved in the award of a contract to the successful bidder. The resident engineer will be advised of award of a contract upon receiving offical notice that the contractor may proceed with the work.