Difference between revisions of "Category:237 Contract Plans"
m (article construction) |
m (addition of a PDM-to-EPG box.) |
||
Line 5: | Line 5: | ||
|} | |} | ||
− | [[ | + | {|style="padding: 0.3em; margin-left:1px; border:3px solid #a9a9a9; text-align:left; font-size: 95%; background:#ffff99" width="350px" align="right" |
+ | |- | ||
+ | |colspan="2"|<center>'''Where to Find Project Development Manual (PDM) Information in the EPG'''</center> | ||
+ | |- | ||
+ | |colspan="2"|Because of the historical document's wide application, the PDM’s contents have been applied throughout the EPG. Thus, unlike some divisions’ manuals, there are few places in the EPG where large portions of the PDM’s contents remained contiguous. This table will help the reader locate the main portions of the former PDM. The EPG material may not be as extensive as the PDM information was (perhaps because the PDM information was deemed to be primarily in the domain of another division and that division chose not to provide such extensive text on the topic), but may also be expanded and in more than one EPG article. In some cases, MoDOT has revised its Design philosophy so that the previous PDM information no longer applies. | ||
+ | |||
+ | |- | ||
+ | |width=17%| || [[Where to Find PDM Information in the EPG#Chapter I, General Information|'''Chapter I, General Information''']] | ||
+ | |- | ||
+ | |width=17%| || [[Where to Find PDM Information in the EPG#Chapter II, Preliminary Design|'''Chapter II, Preliminary Design''']] | ||
+ | |- | ||
+ | |width=17%| || [[Where to Find PDM Information in the EPG#Chapter III, Surveys|'''Chapter III, Surveys''']] | ||
+ | |- | ||
+ | |width=17%| ||[[Where to Find PDM Information in the EPG#Chapter IV, Detail Design|'''Chapter IV, Detail Design''']] | ||
+ | |- | ||
+ | |width=17%| || [[Where to Find PDM Information in the EPG#Chapter V, Bridge Report and Layout|'''Chapter V, Bridge Report and Layout''']] | ||
+ | |- | ||
+ | |width=17%| || [[Where to Find PDM Information in the EPG#Chapter VI, Pavement Structure Design|'''Chapter VI, Pavement Structure Design''']] | ||
+ | |- | ||
+ | |width=17%| || [[Where to Find PDM Information in the EPG#Chapter VII, Utilities|'''Chapter VII, Utilities''']] | ||
+ | |- | ||
+ | |width=17%| || [[Where to Find PDM Information in the EPG#Chapter VIII, Traffic Control Devices|'''Chapter VIII, Traffic Control Devices''']] | ||
+ | |- | ||
+ | |width=17%| || [[Where to Find PDM Information in the EPG#Chapter IX, Hydraulics and Drainage|'''Chapter IX, Hydraulics and Drainage''']] | ||
+ | |||
+ | |} | ||
+ | |||
The [[237.1 Plan Details|contract plans]] include a [[237.2 Title Sheet|title sheet]], a [[237.3 Summary and Tabulation of Quantities|summary and tabulation of quantities]], [[237.4 Plan-Profile Sheets|plan-profile sheets]], | The [[237.1 Plan Details|contract plans]] include a [[237.2 Title Sheet|title sheet]], a [[237.3 Summary and Tabulation of Quantities|summary and tabulation of quantities]], [[237.4 Plan-Profile Sheets|plan-profile sheets]], | ||
[[237.5 Special Provisions|special provisions]], [[237.6 Estimates|estimates]] and other specialized information. An [[237.7 Equipment and Materials List|equipment and materials list]] may also be necessary. [[237.8 Contract Time|Contract time]] is set to encourage contractors to diligently prosecute the work in a reasonable fashion while causing the least disruption to traffic. | [[237.5 Special Provisions|special provisions]], [[237.6 Estimates|estimates]] and other specialized information. An [[237.7 Equipment and Materials List|equipment and materials list]] may also be necessary. [[237.8 Contract Time|Contract time]] is set to encourage contractors to diligently prosecute the work in a reasonable fashion while causing the least disruption to traffic. | ||
Guidance for the [[237.9 Submission of Plans and Supporting Documents|submission of plans and supporting documents]], the [[237.10 Distribution of Plans|distribution]] and [[237.11 Signing and Sealing|signing and sealing]] of the plans is also provided in this article. The [[237.14 Electronic Design Data Delivery|design electronic data used in the development of the contract plans must be submitted]] along with all other project documents to Design via the ProjectWise document management system. | Guidance for the [[237.9 Submission of Plans and Supporting Documents|submission of plans and supporting documents]], the [[237.10 Distribution of Plans|distribution]] and [[237.11 Signing and Sealing|signing and sealing]] of the plans is also provided in this article. The [[237.14 Electronic Design Data Delivery|design electronic data used in the development of the contract plans must be submitted]] along with all other project documents to Design via the ProjectWise document management system. | ||
− | + | [[image:237.jpg|left|325px]] | |
In order to preserve the integrity of the bidding process, it is imperative to strictly limit project information [[237.12 Communication with the Public|communicated to the public]]. MoDOT requires all bidders have the same information from which to prepare a bid. | In order to preserve the integrity of the bidding process, it is imperative to strictly limit project information [[237.12 Communication with the Public|communicated to the public]]. MoDOT requires all bidders have the same information from which to prepare a bid. |
Revision as of 08:19, 24 March 2008
Electronic Plans Room
The electronic plans room allows anyone to view, print or download highway plans for free. Even the general public has access to project plans by visiting http://modot.indoxservices.com/. |
Because of the historical document's wide application, the PDM’s contents have been applied throughout the EPG. Thus, unlike some divisions’ manuals, there are few places in the EPG where large portions of the PDM’s contents remained contiguous. This table will help the reader locate the main portions of the former PDM. The EPG material may not be as extensive as the PDM information was (perhaps because the PDM information was deemed to be primarily in the domain of another division and that division chose not to provide such extensive text on the topic), but may also be expanded and in more than one EPG article. In some cases, MoDOT has revised its Design philosophy so that the previous PDM information no longer applies. | |
Chapter I, General Information | |
Chapter II, Preliminary Design | |
Chapter III, Surveys | |
Chapter IV, Detail Design | |
Chapter V, Bridge Report and Layout | |
Chapter VI, Pavement Structure Design | |
Chapter VII, Utilities | |
Chapter VIII, Traffic Control Devices | |
Chapter IX, Hydraulics and Drainage |
The contract plans include a title sheet, a summary and tabulation of quantities, plan-profile sheets, special provisions, estimates and other specialized information. An equipment and materials list may also be necessary. Contract time is set to encourage contractors to diligently prosecute the work in a reasonable fashion while causing the least disruption to traffic.
Guidance for the submission of plans and supporting documents, the distribution and signing and sealing of the plans is also provided in this article. The design electronic data used in the development of the contract plans must be submitted along with all other project documents to Design via the ProjectWise document management system.
In order to preserve the integrity of the bidding process, it is imperative to strictly limit project information communicated to the public. MoDOT requires all bidders have the same information from which to prepare a bid.
Articles in "237 Contract Plans"
The following 15 pages are in this category, out of 15 total.
2
- 237.1 Plan Details
- 237.2 Title Sheet
- 237.3 Summary and Tabulation of Quantities
- 237.4 Plan-Profile Sheets
- 237.5 Special Provisions
- 237.6 Project Estimates
- 237.7 Equipment and Materials List
- 237.8 Contract Time
- 237.9 Submission of Plans and Supporting Documents
- 237.10 Distribution of Contract Plans
- 237.11 Signing and Sealing
- 237.12 Communication with the Public
- 237.13 Contract Plan File Name Convention
- 237.14 Electronic Design Data Delivery (BIM Deliverables)