(Per Bidding and Estimates, estimating guidance updated to add optional spreadsheet to assist the districts with their scoping and estimating processes. The Resurfacing Per Mile Scoping Form was made available.) |
||
Line 10: | Line 10: | ||
|- | |- | ||
|[[media:Fig 237.6.docx|Costs for Non-Contractual Items]] | |[[media:Fig 237.6.docx|Costs for Non-Contractual Items]] | ||
+ | |- | ||
+ | |'''Resource''' | ||
+ | |- | ||
+ | |[[media:121.7 Project Scoping Form.xlsx|Project Scoping Form]] | ||
|} | |} | ||
Line 18: | Line 22: | ||
The preliminary plans should provide enough detail to allow a fairly accurate Program Estimate of the major project quantities. Generally, 80% of the cost of a project will be included in the 20% of the [http://www.modot.mo.gov/business/contractor_resources/biditemslisting.htm pay items] that comprise the major items of the project. All other anticipated construction costs should also be included in the Program Estimate. | The preliminary plans should provide enough detail to allow a fairly accurate Program Estimate of the major project quantities. Generally, 80% of the cost of a project will be included in the 20% of the [http://www.modot.mo.gov/business/contractor_resources/biditemslisting.htm pay items] that comprise the major items of the project. All other anticipated construction costs should also be included in the Program Estimate. | ||
+ | The [[media:121.7 Project Scoping Form.xlsx|Project Scoping Form]] is available for detailed documentation of various project design elements of the project in order to assist the project estimator in covering all applicable project elements while establishing the program estimate. While the tool does not yield an estimate itself, it serves to clearly define and document the various project elements which combine to impact the project cost. | ||
+ | |||
As details of the project become finalized, the Program Estimate is refined and updated in the STIP, as part of the annual STIP update, until the fiscal year it is scheduled to be awarded. | As details of the project become finalized, the Program Estimate is refined and updated in the STIP, as part of the annual STIP update, until the fiscal year it is scheduled to be awarded. | ||
Revision as of 11:31, 21 October 2019
Related Information |
MoDOT's STIP website |
Figures |
Engineering Factors Report |
Costs for Non-Contractual Items |
Resource |
Project Scoping Form |
The Program Estimate shall not use the cost per mile pricing. The Program Estimate shall be developed at the preliminary plan stage after 30% of the plans are completed.
The best type of Program Estimate that can be produced at this stage of project development is a historic-based estimate. Based on the quantities calculated from the preliminary plans and historical data from previous bid openings, a fairly accurate Program Estimate can be produced.
The preliminary plans should provide enough detail to allow a fairly accurate Program Estimate of the major project quantities. Generally, 80% of the cost of a project will be included in the 20% of the pay items that comprise the major items of the project. All other anticipated construction costs should also be included in the Program Estimate.
The Project Scoping Form is available for detailed documentation of various project design elements of the project in order to assist the project estimator in covering all applicable project elements while establishing the program estimate. While the tool does not yield an estimate itself, it serves to clearly define and document the various project elements which combine to impact the project cost.
As details of the project become finalized, the Program Estimate is refined and updated in the STIP, as part of the annual STIP update, until the fiscal year it is scheduled to be awarded.
In addition, estimates of right of way costs based on generic land values will not be considered to provide the level of confidence that MoDOT requires to make STIP commitments.
Tentative right of way lines included on preliminary plans will provide a reasonable estimate of the easements and right of way required for each project. These can then be combined with an estimated amount for each property to arrive at a fairly accurate right of way estimate.
Historic Engineering Factors Reports |
CY 2006 - 2008 |
CY 2007 - 2009 |
FY 2008 - 2010 |
FY 2010 - 2012 |
FY 2011 - 2013 |
FY 2012 - 2014 |
FY 2013 - 2015 |
FY 2014 - 2016 |
FY 2015 - 2017 |
FY 2016 - 2018 |
All other anticipated right of way and construction costs should also be included in the Program Estimate. These may include Heritage and Homestead Valuation adjustment costs for large utility relocations, right of way easements necesssary for cornstruction activities,non-contractual, incentive/disincentive clauses, contract acceleration clauses, major environmental mitigation costs, etc.
The Engineering Factors Report is a useful document to help calculate a project's future engineering costs such as preliminary and construction engineering and right of way incidentals. The report is updated annually.