- 10:22, 26 April 2017 diff hist 0 N File:134.2.2.2 2017.docx current
- 10:21, 26 April 2017 diff hist -281 m Category:134 Engineering Professional Services Per LPA, updated two forms: Fig. 134.2.2.2 Solicitations and Request Letter, Fig. 134.2.2.5.1 Consultant Rating Form
- 10:16, 26 April 2017 diff hist -91 m Category:101 Standard Forms Per LPA, updated two forms
- 07:21, 26 April 2017 diff hist +1 m 751.35 Concrete Pile Cap Integral End Bents →751.35.5.1 Reinforcing Holes: minor correction, per BR
- 14:33, 25 April 2017 diff hist +127 m Main Page EPG 460.3.13
- 13:59, 25 April 2017 diff hist +1,403 m 460.3 Plant Inspection Per CM, new guidance for handling failing binder samples on projects and when additional testing which may take place. Also, recommendations for penalties for failing binders at the different levels.
- 14:25, 21 April 2017 diff hist -257 m Category:702 Load-Bearing Piles →702.1 Pile Types and Testing: Per BR, removed archaic info
- 10:43, 21 April 2017 diff hist -551 m Category:702 Load-Bearing Piles Per BR, minor editorial revisions.
- 07:10, 21 April 2017 diff hist -16 m Main Page
- 14:17, 20 April 2017 diff hist -4 m Main Page
- 13:56, 20 April 2017 diff hist +1 m Main Page
- 13:42, 20 April 2017 diff hist -3 m Category:101 Standard Forms →Construction and Contractor Related
- 13:31, 20 April 2017 diff hist 0 m Main Page
- 13:28, 20 April 2017 diff hist +89 m Main Page
- 13:23, 20 April 2017 diff hist 0 N File:Main Page April 19, 2017.jpg current
- 13:23, 20 April 2017 diff hist 0 N File:Main Page 2 April 20, 2017.jpg current
- 13:23, 20 April 2017 diff hist 0 N File:Main Page April 20, 2017.jpg current
- 13:22, 20 April 2017 diff hist +1,454 m Main Page
- 11:15, 20 April 2017 diff hist +287 m 751.9 Bridge Seismic Design Per BR, added "Additional Info" box linking to the Bridge Seismic Design Process Flowchart
- 12:47, 19 April 2017 diff hist +58 m Main Page
- 15:02, 18 April 2017 diff hist 0 m Main Page
- 07:08, 18 April 2017 diff hist 0 N File:104.6 Bridge Scoping Checklist.docx current
- 07:08, 18 April 2017 diff hist -12 m 104.6 Project Scoping Checklists Per BR, updated Bridge Scoping Checklist
- 14:24, 17 April 2017 diff hist +157 m Category:101 Standard Forms →Construction and Contractor Related: Per ECR and CM, added form, MoDOT Workforce Pre-Construction Diversity Plan Report.
- 09:10, 14 April 2017 diff hist +101 m 616.5 Flagger Control (MUTCD Chapter 6E) →616.5.4 Automated Flagger Assistance Devices (MUTCD 6E.04): added link
- 09:08, 14 April 2017 diff hist +101 m 616.19 Quality Standards for Temporary Traffic Control Devices added link
- 09:05, 14 April 2017 diff hist +422 m 616.6 Temporary Traffic Control Zone Devices (MUTCD 6F) →616.6.2.2 Flags and Advance Warning Rail System on Signs: inserted links
- 08:58, 14 April 2017 diff hist -6 m 616.7 Type of Temporary Traffic Control Zone Activities (MUTCD 6G) →616.7.2 Work Duration (MUTCD 6G.02)
- 08:49, 14 April 2017 diff hist +1 m 751.50 Standard Detailing Notes →H7. Slab Drains (Notes for Bridge Standard Drawings)
- 08:46, 14 April 2017 diff hist +52 m 616.7 Type of Temporary Traffic Control Zone Activities (MUTCD 6G) →616.7.2 Work Duration (MUTCD 6G.02): inserted link
- 10:59, 13 April 2017 diff hist 0 N File:903.7.49.1 2017.jpg current
- 10:59, 13 April 2017 diff hist +5 m 903.7 Conventional Road Guide Signs →903.7.49 Community Wayfinding Signs (MUTCD Section 2D.50): Per TS, updated Fig. 903.7.49.1 to clarify proper use of signs
- 11:08, 12 April 2017 diff hist -4 m Main Page
- 10:46, 12 April 2017 diff hist +15 m Main Page
- 10:44, 12 April 2017 diff hist 0 N File:Main Page 4 April 12, 2017.jpg current
- 10:44, 12 April 2017 diff hist 0 N File:Main Page 3 April 12, 2017.jpg current
- 10:44, 12 April 2017 diff hist 0 N File:Main Page 2 April 12, 2017.jpg current
- 10:44, 12 April 2017 diff hist 0 N File:Main Page April 12, 2017.jpg current
- 10:43, 12 April 2017 diff hist -618 m Main Page
- 07:13, 12 April 2017 diff hist +50 m 751.50 Standard Detailing Notes →G5. CIP Concrete Piles (Notes for Bridge Standard Drawings): Per BR, minor clarifications
- 14:37, 11 April 2017 diff hist +206 m 236.3 Administration Per RW, updated links
- 14:27, 11 April 2017 diff hist -1 m Main Page
- 14:22, 11 April 2017 diff hist -9 m Category:409 Seal Coat
- 13:56, 11 April 2017 diff hist +239 m Main Page EPG 751
- 13:21, 11 April 2017 diff hist 0 m 751.35 Concrete Pile Cap Integral End Bents →751.35.5.1 Reinforcing Holes
- 13:20, 11 April 2017 diff hist 0 N File:751.35.5.1 end of girder.jpg current
- 13:20, 11 April 2017 diff hist 0 N File:751.35.5.1 end of stringer.jpg current
- 13:19, 11 April 2017 diff hist 0 N File:751.35.3.4 2017.jpg current
- 13:18, 11 April 2017 diff hist 0 N File:751.35.3.3 2017.jpg current
- 13:17, 11 April 2017 diff hist +290 m 751.35 Concrete Pile Cap Integral End Bents Per BR, clarified girder chair detail and end distance from center line of bearing to end of steel and prestressed girders.