- 10:04, 1 April 2021 diff hist +334 m 751.1 Preliminary Design Per BR, minor clarifications
- 11:22, 31 March 2021 diff hist 0 N File:903.2a Signpost Selection Guide 2021.xls current
- 11:21, 31 March 2021 diff hist 0 m Category:903 Highway Signing Per TS, minor clarifications and corrections for Signpost Selection Guide
- 11:21, 31 March 2021 diff hist 0 m 903.3 Ground-Mounted Sign Supports Per TS, minor clarifications and corrections for Signpost Selection Guide
- 09:52, 30 March 2021 diff hist -122 m 127.25 Maintenance Environmental Policies Per Maintenance, deleted archaic Deer Death Report Form and Map
- 07:53, 30 March 2021 diff hist +4 m 127.2 Historic Preservation and Cultural Resources
- 07:49, 30 March 2021 diff hist +474 m 127.2 Historic Preservation and Cultural Resources Per Env'l, updated Mo Historic Bridge Inventory links
- 11:21, 29 March 2021 diff hist +120 m 127.2 Historic Preservation and Cultural Resources Per Env'l, archaic link restored until further notice
- 11:12, 29 March 2021 diff hist -120 m 127.2 Historic Preservation and Cultural Resources
- 11:09, 29 March 2021 diff hist 0 m 127.2 Historic Preservation and Cultural Resources Per Env'l, updated Mo Historic Bridge Inventory link
- 13:46, 26 March 2021 diff hist -791 m Recent Policy Changes in the EPG EPG 501.1.3.5
- 13:33, 26 March 2021 diff hist +2,044 m Category:501 Concrete →501.1 Construction Inspection for Sec 501: Per CM, clarification of curing and testing procedures for cores and cylinders in projects with paving and structures.
- 08:14, 25 March 2021 diff hist -89 m Recent Policy Changes in the EPG EPG 751.50
- 08:10, 25 March 2021 diff hist +356 m 751.50 Standard Detailing Notes →H5a. Finger Plate: Per BR, updated note to clarify procedure for making holes for connection.
- 14:50, 24 March 2021 diff hist +201 m Category:108 Prosecution and Progress →108.1.1 Review and Approval of a Subcontract Request: Per CM, clarifed guidance. The MoDOT Contractor report is no longer useful in checking contractor insurance and it is causing some confusion.
- 13:17, 24 March 2021 diff hist 0 N File:129.3 temporary.docx current
- 13:17, 24 March 2021 diff hist -9 m Recent Policy Changes in the EPG EPG 129
- 13:11, 24 March 2021 diff hist -20 m Category:129 Public Involvement →129.6.4 Presentation for Location and Design Approval to the Commission and Commission Actions Needed
- 13:10, 24 March 2021 diff hist -75 m Category:129 Public Involvement →129.6.4 Presentation for Location and Design Approval to the Commission and Commission Actions Needed
- 13:09, 24 March 2021 diff hist +1,485 m Category:129 Public Involvement Per Env'l, FHWA will temporarily allow all public involvement activities previously conducted in person to exclusively use virtual techniques.
- 08:29, 24 March 2021 diff hist -603 m Recent Policy Changes in the EPG EPG 236.15
- 08:25, 24 March 2021 diff hist +241 m 236.16 Outdoor Advertising →236.16.15 Vegetation Removal: Per ODA, updated Vegetation Process in EPG. The current practice has been in place for several years. Unfortunately, it was overlooked on ODA’s part in the EPG.
- 10:53, 23 March 2021 diff hist -26 m Recent Policy Changes in the EPG EPG 108.1.1
- 10:45, 23 March 2021 diff hist +2,690 m Category:108 Prosecution and Progress →108.1.1 Review and Approval of a Subcontract Request: Per CM, new guidance about when subletting requirements can be adjusted
- 15:13, 19 March 2021 diff hist +4 m 642.9 Sidewalk Ramp and Curb Ramp Design Criteria →642.9.1 Slope and Rise of Sidewalk Ramps: Per DE, correction: minimum curb height for sidewalk ramp edge protection is 4 inches, not 2 inches.
- 14:56, 19 March 2021 diff hist -320 m Recent Policy Changes in the EPG EPG 109.12.3.2
- 14:50, 19 March 2021 diff hist +2,569 m Category:109 Measurement and Payment →109.12.3 Time Adjustment Change Orders: Per CM, new useful guidance for addressing time adjustment change orders as well as the supporting documentation
- 12:13, 19 March 2021 diff hist -134 m Category:108 Prosecution and Progress →108.7 Contract Time for Completion of the Work: Per CM, deleted sentence that is contrary to specifications
- 07:12, 18 March 2021 diff hist 0 File:235.2.3 Exhibit A.pdf Smithk reverted File:235.2.3 Exhibit A.pdf to an old version current
- 07:10, 18 March 2021 diff hist -24 m Category:235 Preliminary Plans →235.2.3 Municipal Agreements (DE11) and County Agreements (DE10): updated link
- 12:25, 17 March 2021 diff hist -44 m Recent Policy Changes in the EPG EPG 903.15.1
- 12:22, 17 March 2021 diff hist +1,550 m 903.14 Memorial Signs →903.14.1 Memorial Designation Programs: Per TS, new Memorial Designation Programs guidance for statewide uniformity.
- 08:55, 17 March 2021 diff hist +2 m 751.31 Open Concrete Intermediate Bents →751.31.3.2 Column
- 08:48, 17 March 2021 diff hist +4 m 751.31 Open Concrete Intermediate Bents →751.31.3.2 Column
- 14:41, 15 March 2021 diff hist 0 N File:606.1.3.1 Guardrail Length of Need Calculator 2021.xlsx
- 14:40, 15 March 2021 diff hist +10 m 606.1 Guardrail Per Charles Schumann, updated Guardrail Length of Need Calculator to allow selection of a barrier w/ an extended curb so the add'l 12.5’ of guardrail is included if there is not sufficient LON to cover it. Also informational notes and warnings were updated and added
- 13:36, 15 March 2021 diff hist +171 m Recent Policy Changes in the EPG EPG 751.2 and EPG 751.31
- 13:02, 15 March 2021 diff hist +935 m 751.2 Loads →751.2.2.6 Other Loads: Per BR, updated pier protectin guidance to reflect latest AASHTO collision requirements with MoDOT policy exceptions.
- 11:15, 15 March 2021 diff hist +262 m 751.1 Preliminary Design →751.1.2.6.1 Grade Separations: Per BR, updated pier protectin guidance to reflect latest AASHTO collision requirements with MoDOT policy exceptions.
- 08:33, 15 March 2021 diff hist +1,568 m 751.31 Open Concrete Intermediate Bents Per BR, updated pier protectin guidance to reflect latest AASHTO collision requirements with MoDOT policy exceptions.
- 14:42, 12 March 2021 diff hist +85 m Recent Policy Changes in the EPG EPG 751.10.1.3
- 14:26, 12 March 2021 diff hist +4,349 m 751.10 General Superstructure Per BR, provided deck cantilever design guidance for the MASH Type D and H barriers.
- 09:44, 12 March 2021 diff hist +49 m Recent Policy Changes in the EPG EPG 751.1.3.4
- 09:22, 12 March 2021 diff hist 0 N File:751.1.3.4 vertical section.jpg current
- 09:21, 12 March 2021 diff hist 0 N File:751.1.3.4 vertical.jpg current
- 09:19, 12 March 2021 diff hist +1,611 m 751.1 Preliminary Design →751.1.3.4 Barrier or Railing Type, Height and Guidelines for Curb Blockouts: Per BR, refined guidance for use of MASH and NCHRP 350 barrier and rail.
- 09:23, 11 March 2021 diff hist +24 m 903.1 Highway Signing General Information Per EPS, added "(for internal use only)" to a link current
- 13:20, 9 March 2021 diff hist +328 m Recent Policy Changes in the EPG EPG 101
- 13:12, 9 March 2021 diff hist +94 m Category:101 Standard Forms →AASHTOWare Project Quick Reference Guides (QRGs): Per CM, added AWP QRG Revision Dates information
- 16:29, 8 March 2021 diff hist +4 m Category:107 Legal Relations and Responsibility to the Public →107.12 Contractor's Responsibility for Work