Difference between revisions of "147.3 Job Order Contracting (JOC)"

From Engineering_Policy_Guide
Jump to navigation Jump to search
m (Per Bidding and Est, guardrail JOC JSP temporarily removed prior to being updated; the Combined Guardrail and Guard Cable JOC JSP will no longer be utilized)
m (updated JOC links)
Line 9: Line 9:
 
|style="background:#BEBEBE" align="center" width=260px|'''Job Order Contracting JSPs<br/>for 2016'''
 
|style="background:#BEBEBE" align="center" width=260px|'''Job Order Contracting JSPs<br/>for 2016'''
 
|-
 
|-
|style="background:#BEBEBE" align="center" | [[media:147 guard cable 2015.doc|Guard Cable]]
+
|style="background:#BEBEBE" align="center" | [http://epg.modot.org/files/c/c9/147_guard_cable_2015.doc Guard Cable]
 
|-
 
|-
|style="background:#BEBEBE" align="center" | [[media:147 fence 2015.doc|Fence]]
+
|style="background:#BEBEBE" align="center" | [http://spexternalsignin/sites/de/JSP/JOC_FENCE.doc Fence]
 
|-
 
|-
|style="background:#BEBEBE" align="center" | [[media:147 concrete pavement repair 2015.doc|Concrete Pavement Repair]]
+
|style="background:#BEBEBE" align="center" | [http://spexternalsignin/sites/de/JSP/JOC_CONCRETE_PAVEMENT.doc Concrete Pavement Repair]
 
|-
 
|-
|style="background:#BEBEBE" align="center" | [[media:147 bridge 2015.doc|Bridge]]
+
|style="background:#BEBEBE" align="center" | [http://spexternalsignin/sites/de/JSP/JOC_BRIDGE.doc Bridge]
 
|-
 
|-
|style="background:#BEBEBE" align="center" | [[media:147 asphalt pavement repair 2015.doc|Asphalt Pavement Repair]]
+
|style="background:#BEBEBE" align="center" | [http://spexternalsignin/sites/de/JSP/JOC_ASPHALT.doc Asphalt Pavement Repair]
 
|-
 
|-
 
| style="background:#BEBEBE" align="center" width=260px|Contact [http://wwwi/design/BiddingAndContract.htm Danica Stovall-Taylor, Estimate and Review Engineer], for additional guidance.  
 
| style="background:#BEBEBE" align="center" width=260px|Contact [http://wwwi/design/BiddingAndContract.htm Danica Stovall-Taylor, Estimate and Review Engineer], for additional guidance.  

Revision as of 11:51, 11 December 2015

148.jpg

MoDOT uses a procurement process called Job Order Contracting (JOC) for traditional on-call maintenance repair contracts, including asphalt and concrete pavement repair, guardrail and guard cable repair, bridge repair and fence repair. JOC allows MoDOT to award fixed price construction contracts with indefinite delivery and indefinite quantity at individual work locations throughout the project limits. The JOC bid proposals contain a catalog of pre-established fixed unit prices for material, equipment and labor for various items of work to be used for completing each job order. The contractor bids adjustment factors for the expected overhead and profit and any additional business and construction related costs for performing the various types of work identified in the contract. The fixed unit prices in the bid proposal allow the contractor to determine the adjustment factor (profit and overhead) that needs to be bid up front without knowing the quantities, schedules or timing of the work orders. Job Order Contracts are awarded based on the lowest responsive bidder. Overall, Job Order Contracting eliminates the ability for contractors to unbalance the bid.

The JOC bid proposal must specify the maximum program budget to be awarded during a specified contract term. MoDOT is not bound, however, to issue a minimum or maximum number of job orders during the contract term. It is MoDOT’s overall intent though to meet the anticipated budget specified in the contract.

Job Order Contracting JSPs
for 2016
Guard Cable
Fence
Concrete Pavement Repair
Bridge
Asphalt Pavement Repair
Contact Danica Stovall-Taylor, Estimate and Review Engineer, for additional guidance.

147.3.1 Fixed Unit Price List

A fixed unit price list containing unit prices for the various items of work for each job order is included in the JOC bid proposal. Fixed unit prices are for complete and in-place construction, including all labor, equipment and material required to complete the construction task. All labor, material, equipment and work required by a specification shall be considered part of the fixed unit price, unless otherwise stated elsewhere in the contract.

147.3.2 Adjustment Factors

The contractor will bid three different Adjustment Factors:

  • Normal Work Adjustment Factor - work conducted from 6:00 a.m. to 7:30 p.m. Monday through Friday
  • Nighttime Work Adjustment Factor - work conducted from 7:30 p.m. to 6:00 a.m. Monday through Thursday
  • Weekend Work Adjustment Factor - work conducted from 7:30 p.m. on Friday through 6:00 a.m. on Monday, night or day, or a holiday

Adjustment factors include business and construction related costs as defined below. It is the responsibility of the contractor to verify the fixed unit prices provided in the contract and to modify their bid for the adjustment factors accordingly.

Business Costs. Business related costs consist of profit, overhead costs, subcontractor profit and overhead, taxes, finance costs, and other costs including but not limited to;

a. insurance, bonds and indemnification
b. project meetings, training, management and supervision
c. project office staff and equipment
d. employee or subcontractor wage rates that exceed prevailing wages
e. fringe benefits, payroll taxes, worker’s compensation, insurance costs and any other payment mandated by law in connection with labor that exceeds the labor rate allowances.
f. business risks such as the risk of low than expected volumes of work, smaller than anticipated job orders, poor subcontractor performance, and inflation or material cost fluctuations.

Construction Costs. Construction related costs include but are not limited to;

a. personnel safety equipment
b. security requirements
c. excess material waste
d. daily and final clean-up
e. costs resulting from inadequate supply of materials, fuel, electricity, or skilled labor
f. costs resulting from productivity loss
g. working in extreme and adverse weather conditions
h. any other discreet items of work required to complete a particular job order.

General Costs. The above lists are not exhaustive and are intended to provide general examples of cost items to be included in the contractor’s Adjustment Factors as defined in the contract.

147.3.3 JOC Development: Job Special Provisions and Plan Sheets

MoDOT Bidding and Contract Services (BCS) conducts an annual internal MoDOT meeting to discuss lessons learned from previous year’s on-call contracts. Design staff incorporates changes into the next years contracts, and updates the job special provision (JSP) templates for distribution to the districts.

The BCS section also updates the fixed costs to reflect the new market value. In the event the costs change significantly, the BCS section coordinates with industry to ensure the fixed costs are satisfactory. The fixed costs in the draft proposals should not be adjusted by the districts, without prior input from the BCS section. It is important to have agreement on the fixed unit price list with industry to eliminate any outliers that could cause contractors to bid risk in the factors.

In addition, no additional items of work should be added without first coordinating with the BCS section. Our experience to date has shown that adding specialty items of work may discourage contractors from bidding on a typical maintenance contract because the specialty work has to be subcontracted out for additional costs. Many times, specialty items of work or items of work not identified in the list of fixed costs are better managed by negotiating a price with the JOC contractor. Establishment of pricing for any non-fixed cost pay items will be in accordance with Sec 109.4.2 or 109.4.3 of the Missouri Standard Specifications for Highway Construction. If no agreement to pricing can be made then the work will proceed with payment for non-fixed cost items under Sec 109.4.4.

The JOC contracts include contractor-furnished Traffic Control Plans (TCP) as on option, but the district may choose to provide the traffic control with MoDOT forces depending on availability.

Example TCP plans for the Job Order Contracts exist as seed files in ProjectWise. These example plans are based on what has been used on past contracts and are for example purposes only. Some of the traffic control scenarios may not apply to all districts so each district should ensure changes to the Traffic Control Plans are also changed in the JSP template. If there are revisions to the JSP template, the district should identify the revisions to the BCS section at the time of Plans, Specifications & Estimate (PS&E) submittal.

The JOC_TCP files are located at pw:\\ghpwise10:MoDOT\Documents\CADD_Standards\Standard Plans for Highway Construction\Job Order Contracting\.

All district ProjectWise users will have read-only access to the files.

The following is the process for obtaining a clean copy of all the files at one time:

  • Select all of the files, right-click and select Copy.
148.3.jpg
  • Then right-click in the job directory and select Paste.

147.3.4 Issuing Job Orders

The engineer will collaborate with the contractor when developing an individual job order. At any given time the contractor may be performing more than one job order.

The total cost of an individual job order will be determined by multiplying the fixed unit prices of each fixed cost pay item by the appropriate quantity and then multiplying the total cost of all pay items by the appropriate adjustment factor.

Example Job Order

Item Description Fixed Unit Price Quantity Price
SP125C (PG70-22) Per Ton (Over 1000 Tons) $55.75 337.1 tons $18,793.33
SP190C (PG70-22) Per Ton (Over 1000 Tons) $53.75 770.5 tons $41,414.61
Tack Coat $3.40 180 gal $612.00
Mobilization – Coldmilling & Resurfacing (Over 1000 Tons) $3,200.00 1 each $3,200.00
Milling Per SY (4 In. to 6 In. Thick) $2.25 3520 sy $7,920.00
Subtotal: $71,939.94
Nighttime Work Factor 1.200 - -
Subtotal: $86,327.92
Accelerated Repair $2,500.00 1 each $2,500.00
TOTAL: $88,827.92
Note: The adjustment factor is not applied to Accelerated Repair because it is a lump sum cost for accelerated mobilization regardless of it being on a weekend or at night.

147.3.5 Term Extension of Job Order Contracts

All JOC contracts include the option for a mutually agreeable one year term extension. The contract may be extended under the original terms and contract prices for a maximum contract term of two (2) years. The district should contact the BCS section by November 1 to evaluate and discuss whether the JOC should be renewed. Is the district satisfied with performance of the contractor? Are the existing bid prices reasonable? Is it the right business decision to renew the contract? If the option for extending the contract is exercised by MoDOT, a change order will be issued to extend the contract to the new term limits.

The following are the guidelines for extending the term of a Job Order Contract for an additional year for a maximum two year term.

  • In order for the contract to be extended, the project must contain the language in the Term of Contract JSP that allows for a one year extension.
  • If MoDOT desires to renew the contract, the contractor will be given written notification (e-mail is acceptable) of the extension no later than December 1 of the current contract year.
  • The contractor shall provide written notification (e-mail is acceptable) of acceptance or rejection of the extension of the contract no later than January 1 of the current contract year.
  • If the option for extending the contract is exercised by MoDOT, a time adjustment change order will be issued by the RE to extend the contract to the new term limits. The agreed letters or emails from both parties should be on file as supporting documentation to the time adjustment change order. A final quantity change order will be issued after completion of the second term.
  • The RE must notify the contractor that the performance contract bond shall be increased to an amount equal to the original contract amount plus the extended contract amount (i.e., double the original bond amount). This can be accomplished by issuing a rider to increase the original bond for the original contract amount or by reissuing a new bond for double the original contract amount (i.e., if the original contract is $2 million, an increase rider should be issued for $2 million or a completely new bond for $4 million). A change order to increase the contract amount is not necessary because the new performance bond becomes part of the executed contract. The RE should submit the new bond to Chief Counsel Office (CCO) for review along with the change order for extension and the original contract bond. Include a memorandum that states the reason for the bond review, contract identification, and your contact information. After review, CCO will forward the bond to the Division of Construction and Materials for storage with the original contract.
  • The district should notify the BCS section and Central Office (CO) Planning Programming staff by January 15 of the intent to extend the contracts and request CO Transportation Planning to delete the projects from the future STIP. The following information should be provided:
a. Current project numbers being extended.
b. Future project numbers in the STIP that will not be let because of extension.
c. The source and funding split-out of each project. Indicate if SWIMB (Statewide Interstate and Major Bridge), district-funded or other FFOS.
d. See below example.
148.6 email.jpg
  • JOCs that will not be extended should be closed out in Site Manager at the end of the first year contract term.
  • JOCs that are extended will be closed out in Site Manager at the end of the second year contract term. The district shall close out the contract following the Closing JOC Contracts guidelines below.

District Planning Managers should do the following in SIMS:

  • For contract extensions, add the following message to the SIMS, Detail Screen - Internal District Comment field: “Extending Contract through SFY XXXX for a two-year term.”
147.6.jpg

147.3.6 Closing JOC Contracts

  • Any JOCs that will not be extended should be closed out in Site Manager at the end of the first year contract term. Renewed contracts are closed out in Site Manager at the end of the second year contract term.
  • Check the actual cost charges to make sure they are correct and request journal vouchers from Financial Services for corrections.
  • Proceed with final close out in Site Manager.
  • After close out of extended JOC contracts, enter the following standard reason for cost differences greater or less than 10% into SIMS, Project Accountability Reasons - Completed Projects section: “The cost estimate deviated from the actual cost due to this being a Job Order Contract that was extended for a maximum two-year term.”

147.3.7 Budget Adjustments for JOC Contracts

The contract budget adjustment will occur after the contract is complete.

  • Interstate JOCs: If the contract is extended and an interstate project, Planning will credit the district with 2 years worth of Statewide Interstate and Major Bridge (SWIMB) funds rather than one year.
  • Non-interstate JOCs: Contact Central Office Planning Programming managers because there may be specific issues regarding funding.

147.3.8 Deleted JOC Projects

If a JOC project is deleted, enter the following standard reason into SIMS, Project Accountability Reasons – Reprioritized Projects section: “The project was deleted because an existing project was extended for a second year.”

148.9.jpg

147.3.9 Change Order Approval Levels for Job Order Contracts

SiteManager usually sets a higher approval level for change orders on Job Order Contracts than what is necessary. The Resident Engineer should use the guidance below to manually set the approval level for JOC change orders.

1. Use the amount set up in the district budget as the theoretical original contract amount.
2. If the change order proposes to exceed the budgeted amount by more than (see note below), approval should be elevated to Level 2 (district level).
3. If the change order proposes to exceed the budgeted amount by more than $100,000, approval should be elevated to Level 3 (division level).
4. If the change order proposes to exceed the budgeted amount by more than $1,000,000, approval should be elevated to Level 4 (Chief Engineer level).
5. Time adjustment change orders are normally always division level approval, but routine JOC one-year time extensions can be approved at the district level. Attach the agreed letters (or emails) from both parties to the change order.
6. For any unusual situations, please contact your DCE and/or CLE to determine the appropriate approval level.
Note: This is normally $50,000, but the District Construction Engineer will determine the amount that requires district level approval (some districts have tighter budgets than others).