Difference between revisions of "Category:200 GEOMETRICS"

From Engineering_Policy_Guide
Jump to navigation Jump to search
m (add new article)
m (add new articles)
Line 4: Line 4:
 
<categorytree mode=all>202 Removal of Buildings and Structures</categorytree>
 
<categorytree mode=all>202 Removal of Buildings and Structures</categorytree>
 
<categorytree mode=all>203 Roadway and Drainage Excavation, Embankment and Compaction</categorytree>
 
<categorytree mode=all>203 Roadway and Drainage Excavation, Embankment and Compaction</categorytree>
 +
<categorytree mode=all>204 Embankment Monitoring</categorytree>
 +
<categorytree mode=all>205 Modified Subgrade</categorytree>
 
<categorytree mode=all>206 Excavation for Structures</categorytree>
 
<categorytree mode=all>206 Excavation for Structures</categorytree>
 
<categorytree mode=all>207 Linear Grading</categorytree>
 
<categorytree mode=all>207 Linear Grading</categorytree>
 +
<categorytree mode=all>208 Interception Ditch</categorytree>
 +
<categorytree mode=all>209 Subgrade Preparation</categorytree>
 +
<categorytree mode=all>210 Subgrade Compaction</categorytree>
 +
<categorytree mode=all>211 Subgrade Scarifying</categorytree>
 
<categorytree mode=all>212 Subgrading and Shouldering</categorytree>
 
<categorytree mode=all>212 Subgrading and Shouldering</categorytree>
 
<categorytree mode=all>214 Rock Fill</categorytree>
 
<categorytree mode=all>214 Rock Fill</categorytree>

Revision as of 11:34, 25 July 2007

200 Geometrics.jpg


200.1 Construction Inspection Guidance for Grading and Removals

General Preparation and Requirements

This guidance will not only serve to help personnel assigned to grading and removals but, after reviewing the multitude of their duties and responsibilities, will emphasize the importance of their contribution to the quality of the finished product. This information is intended as a guide to uniform administration, inspection, and testing procedures on grading and removal work.

Inspector Preparation

It is essential that the inspector have a thorough knowledge of the standard specifications, special provisions, and plans. The inspector should study all information available to them regarding the various types of soil. The inspector must be able to relate each soil type to the standards as it is being placed in the embankment.

Daily Documentation

The compaction inspector must keep a diary. The inspector should record weather conditions, condition of material being moved, all activities of the contractor forces, an estimate of quantities completed, any special instructions given the contractor, and any other information about the earthwork phase of the work each day. The person making the diary entries must sign them.

Traffic Control Plan

Enforcement of specific safety measures includes requiring all work be properly barricaded and/or signed in accordance with the Traffic Control Plan included in the contract. The plan requires that signs be kept clean, legible, in alignment, and in good repair.