Category:704 Concrete Masonry Repair

From Engineering_Policy_Guide
Revision as of 09:26, 4 November 2010 by Smithk (talk | contribs) (→‎704.2 Materials Inspection for Sec 704: Per CM, updated the links. Now there are two lists of qualified rapid set concrete patching materials.)
Jump to navigation Jump to search
Approved Products
Qualified Rapid Set Concrete Patching Material

704.1 Construction Inspection for Sec 704

This work consists of removing deteriorated concrete, preparing the repair site, forming where required, placing and finishing new concrete or qualified special mortar and applying epoxy in the required areas.

The types of repair are:

  • Repairing Concrete Deck (Half-Soling)
  • Deck Repair With Void Tube Replacement
  • Full Depth Repair
  • Modified Deck Repair
  • Superstructure Repair (Unformed)
  • Slab Edge Repair
  • Substructure Repair (Formed)
  • Substructure Repair (Unformed)
  • Epoxy Sealing.

Refer to Sec 704.

704.2 Materials Inspection for Sec 704

For more information regarding Rapid Set Concrete Patching Material, refer to MSP 02-01A.

Two lists of qualified rapid set concrete patching materials are maintained by Construction Materials. One list shows approved horizontal patching materials and the other list is for vertical and overhead patching materials.

704.3 Laboratory Testing for Sec 704

704.3.1 Scope

This guidance establishes procedures for Laboratory testing and reporting concrete cylinders representing Class X Concrete.

704.3.2 Procedure

Concrete cylinders shall be tested for compressive strength according to AASHTO T 22. Test results and calculations shall be recorded through SiteManager.

704.3.3 Sample Record

The sample record shall be completed in SiteManager, as described in Automation Section 3510. Appropriate remarks, as described in EPG 106.20 Reporting, are to be included in the remarks to clarify conditions of acceptance or rejection. Test results shall be reported on the appropriate templates under the Tests tab.