Difference between revisions of "120.3 Bridges"
m (minor clarifications and revising the IRI to 140 from 160) |
m (→120.3.1 Deck and Approach Slab: Link to Innovation Library) |
||
Line 2: | Line 2: | ||
==120.3.1 [[770.6 Bridge Approach Maintenance|Deck and Approach Slab]]== | ==120.3.1 [[770.6 Bridge Approach Maintenance|Deck and Approach Slab]]== | ||
− | + | {|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#ffddcc" width="210px" align="right" | |
+ | |- | ||
+ | |'''Bridge Approach Slabs, Performance and Design''' | ||
+ | |- | ||
+ | |[http://library.modot.mo.gov/RDT/reports/Ri02033/RDT04010.pdf Report 2004] | ||
+ | |- | ||
+ | |[http://library.modot.mo.gov/RDT/reports/Ri02033/brief.pdf Summary 2004] | ||
+ | |- | ||
+ | |'''See also:''' [http://www.modot.gov/services/OR/byDate.htm Innovation Library] | ||
+ | |} | ||
===Performance Expectation=== | ===Performance Expectation=== | ||
Mainline bridge deck and approach slabs shall be maintained to provide a smooth riding transition from one pavement segment to the next. | Mainline bridge deck and approach slabs shall be maintained to provide a smooth riding transition from one pavement segment to the next. | ||
Line 17: | Line 26: | ||
|[[image:120.3.1.1.jpg|350px|thumb|<center>'''Good'''</center>]]||[[image:120.3.1.2.jpg|350px|thumb|<center>'''Poor'''</center>]] | |[[image:120.3.1.1.jpg|350px|thumb|<center>'''Good'''</center>]]||[[image:120.3.1.2.jpg|350px|thumb|<center>'''Poor'''</center>]] | ||
|} | |} | ||
− | |||
==120.3.2 [[770.7 Maintenance of Bridge Superstructure|Superstructure]]== | ==120.3.2 [[770.7 Maintenance of Bridge Superstructure|Superstructure]]== |
Revision as of 12:34, 30 March 2009
Contents
120.3.1 Deck and Approach Slab
Bridge Approach Slabs, Performance and Design |
Report 2004 |
Summary 2004 |
See also: Innovation Library |
Performance Expectation
Mainline bridge deck and approach slabs shall be maintained to provide a smooth riding transition from one pavement segment to the next.
Performance Measures
Randomly selected mainline bridge deck and approach slabs will be annually measured in the fall with the ARAN van to determine the average IRI. Visual inspections will be conducted on the same bridges in the spring to determine the deck rating and percent repaired surface area.
Performance Objectives
Mainline bridge deck and approach slabs shall have an average IRI of less than 140 within 0.1 miles of the bridge, a deck rating of at least 6 and no more than 10% visible patching by surface area.
120.3.2 Superstructure
Performance Expectation
Superstructure elements of overpass bridges shall be in good repair with an acceptable aesthetic appearance and superstructure elements of mainline bridges shall be in good condition.
Performance Measures
Visual inspections will be conducted on randomly selected mainline bridges and overpass bridges located within the roadway segment in the spring to identify exposed reinforcing steel, loose concrete and graffiti visible from the interstate roadway. Visual inspections will be conducted on all mainline and overpass bridges in the fall to determine the superstructure rating and paint condition.
Performance Objectives
Mainline bridges and overpass bridges shall be free of visible exposed reinforcing steel, loose concrete and graffiti. Mainline bridges shall have a superstructure rating of at least 5. Mainline bridges and overpass bridges shall have a paint rating of at least fair. Graffiti shall be removed within 30 days of detection.
120.3.3 Substructure
Performance Expectation
Substructure elements of overpass bridges shall be in good repair with an acceptable aesthetic appearance and substructure elements of mainline bridges shall be in good condition.
Performance Measures
Visual inspections will be conducted on randomly selected mainline bridges and overpass bridges located within the roadway segment in the spring to identify exposed reinforcing steel, loose concrete and graffiti visible from the interstate roadway. Visual inspections will be performed on all mainline and overpass bridges in the fall to determine the substructure rating.
Performance Objectives
Mainline bridges and overpass bridges shall be free of visible exposed reinforcing steel, loose concrete and graffiti. Mainline bridges shall have a substructure rating of at least 5. Graffiti shall be removed within 30 days of detection.
120.3.4 Slope Protection
Performance Expectation
Slope protection shall be maintained in order to prevent the spill fills of the structure from eroding and to provide protection from undermining of the bridge abutments.
Performance Measures
Visual inspections will be conducted on randomly selected mainline bridges and overpass bridges located within the roadway segment in the spring to determine if the slope protection on the bridge looks good and is performing as intended.
Performance Objectives
90% of the concrete slope protection shall be structurally sound without any broken or misaligned slabs. 100% of slope protection visible from mainline shall be free of vegetation.