Created page with "===136.8.1.6 Local Public Agency - ROW and Easement Acquisition=== '''General Summary of the ROW Process''' The Local Public Agency (LPA) has been awarded a federal-aid project on the Transportation Implementation Program (TIP). The Reasonable Progress Policy and the schedule set by the LPA fixes timelines to be met. With ROW acquisition involved in your project, you must plan to continue the design and acquire ROW simultaneously. Coordination and planning are key to th..."
 
No edit summary
 
(5 intermediate revisions by the same user not shown)
Line 1: Line 1:
=1=
<big>'''Copy 136.8.1.6 Local Public Agency - ROW and Easement Acquisition'''</big>
===136.8.1.6 Local Public Agency - ROW and Easement Acquisition===
===136.8.1.6 Local Public Agency - ROW and Easement Acquisition===
'''General Summary of the ROW Process'''
'''General Summary of the ROW Process'''


The Local Public Agency (LPA) has been awarded a federal-aid project on the Transportation Implementation Program (TIP). The Reasonable Progress Policy and the schedule set by the LPA fixes timelines to be met. With ROW acquisition involved in your project, you must plan to continue the design and acquire ROW simultaneously. Coordination and planning are key to the success of the LPA. To this end, MoDOT has prepared a simple flow chart to help you visualize and plan the acquisition process for your LPA project.
The Local Public Agency (LPA) has been awarded a federal-aid project on the Transportation Implementation Program (TIP). The Reasonable Progress Policy and the schedule set by the LPA fixes timelines to be met. With ROW acquisition involved in your project, you must plan to continue the design and acquire ROW simultaneously. Coordination and planning are key to the success of the LPA. To this end, MoDOT has prepared a simple flow chart to help you visualize and plan the acquisition process for your LPA project.


[[image:236.18.1.6 Flow Chart.jpg|750px|center|thumb|<center>'''ROW Flow Chart for the LPA'''</center>
[[File:136.8.1.6 flow chart.png|750px|center|thumb|<center> <big>'''ROW Flow Chart for the LPA'''</big> <br> An [https://epg.modot.org/forms/general_files/DE/LPA/ROW_Flowchart.pdf easily printable version of the chart is also available.] </center>]]
<center> An [[media:236.18.1.6 Flow Chart.pdf|easily printable version]] of the chart is also available.</center>]]
 
The goal is to acquire ROW AND certify it clear; at the same time the final Plans Specifications and Estimates (PSE) package is approved. Ultimately, the final PSE should not obstruct the completion of the ROW clearance, and the ROW clearance should not delay the Final PSE.
 
These instructions should be used as a map to identify where you are in the ROW Process and what to do next. Like many maps, it will not tell you how long it takes, but simply how to get there. How long it will take is up to the project sponsor and the designer. Dealing with private property owners can be dynamic and complicated, but is not out of your control. The more time you can allow for this phase, the more likely you are to meet your schedule for construction.
 
'''Square 1'''
 
The ROW Process actually begins during the Preliminary Design Plans (PDP) stage. The approvals you must obtain during PDP directly affect your ability to begin ROW Acquisition. Check with your MoDOT COROW on the status of the environmental and historic clearances. Among other requirements, the environmental categorical exclusion approval must be obtained before the PDP can be approved.
 
Some projects will receive a programmatic categorical exclusion for the environmental clearance and a CE-2 submittal will not be required. All projects will still require a [[127.2 Historic Preservation and Cultural Resources|Section 106 Historic]] clearance. A Section 106 form should be sent to the Missouri Department of Natural Resources (MoDNR) to be reviewed as soon as possible in order to keep the process moving. When the CE-2 has been received and Section 106 has been applied for you may move to the next step.
 
'''Square 2'''


The PDP must be approved prior to submitting ROW Plans for approval. This is because the FHWA intends to ensure the alignment will not change before participating in ROW or Construction costs. When your Preliminary Design plans are approved, please move ahead.  
The goal is to acquire right of way AND certify it clear; at the same time the final Plans Specifications and Estimates (PSE) package is approved. Ultimately, the final PSE should not obstruct the completion of the ROW clearance, and the ROW clearance should not delay the Final PSE.


'''Squares 3 and 4'''
These instructions should be used as a map to identify where you are in the ROW Process and what to do next. Like many maps, it will not tell you how long it takes, but simply how to get there. How long it will take is up to the project sponsor and the designer. Dealing with private property owners can be dynamic and complicated but is not out of your control. The more time you can allow for this phase, the more likely you are to meet your schedule for construction.


Submit ROW Plans to MoDOT for review, if there are comments made, revise them and move to the next square. If no comments are made and the ROW Plans are approved, skip the next square and move directly to Square 5, ROW Plans Approved.
'''Step 1'''
With no time to waste, move ahead to Square 6; review the most recent ROW Cost Estimate for accuracy, age and any new developments with regard to property owners, land sales or new construction. Now is the time to update this cost estimate to ensure you have an accurate number. For a list of eligible and reimbursable ROW costs, contact MoDOT COROW. Now move to the next square.


'''Square 7'''
The ROW Process actually begins during the Preliminary Design Plans (PDP) stage. The PDP must be approved prior to submitting ROW Plans for approval. This is because the FHWA intends to ensure the alignment will not change before participating in ROW or Construction costs. When your Preliminary Design plans are approved, please move ahead.


Now that you are reasonably sure how much it will cost, the LPA must determine who will acquire the ROW and how it will be paid for. Either one has a direct effect on the other and will decide which path your LPA will take.
'''Step 2'''


'''Square 8A'''
The approvals you must obtain during PDP directly affect your ability to begin ROW Acquisition. Check with your MoDOT District LPA contact on the status of the environmental and historic clearances. Among other requirements, the environmental categorical exclusion approval must be obtained before the ROW plans can be approved.


Local: If the LPA is staffed to acquire ROW, AND the cost is within the local funds held by the LPA for this project, then it may be prudent to use the Local slide to skip the next two squares. Warning, all ROW costs will be paid by the LPA and ONLY the LPA will be accountable for adherence to the requirements of state laws and the CFR Titles 23 and 49, including the Uniform Act.
Some projects will receive a programmatic categorical exclusion (PCE) for the National Environmental Policy Act (NEPA) environmental clearance and a CE2 submittal will not be required. All projects will still require a [[127.2_Historic_Preservation_and_Cultural_Resources|Section 106 Historic clearance]], as part of the NEPA approval. When the CE2 or PCE has been approved you may move to the next step.


'''Square 8B'''
'''Step 3, 4, and 5'''


FHWA: If on the other hand, the local funding is insufficient for the ROW Cost estimated, OR the agency is not staffed to acquire ROW, it is strongly recommended the LPA use the FHWA path to hire a ROW Agent or Firm from MoDOT’s approved list.  
Submit ROW Plans to MoDOT CO ROW for review, if there are comments made, revise them and move ahead. If no comments are made and the ROW Plans are approved, skip the next step and move directly to Step 5, ROW Plans Approved.


'''Squares 9 and 10'''
'''Step 6'''


These may include appraisers, negotiators, lawyers, mediators or any firm which handles all types of ROW services. This path also includes obligating federal funding for the eventual reimbursement of a large percentage of these ROW Costs. The LPA and the ROW Consultant will both be accountable for adherence to the requirements of state laws and the CFR Titles 23 and 49, including the Uniform Act.
With no time to waste, move ahead to Step 6; review the most recent ROW Cost Estimate for accuracy, age and any new developments with regard to property owners, land sales or new construction. Now is the time to update this cost estimate to ensure you have an accurate number. For a list of eligible and reimbursable ROW costs, contact your MoDOT Central Office ROW. Now move to the next step.


'''Square 11'''
'''Step 7'''


The Environmental CE-2 approval was obtained before PDP. Make a copy and hold it until Square 13. Move ahead one square.  
Now that you’re reasonably sure how much it will cost, the LPA must determine who will acquire the ROW (local or consultant) and how it will be paid for (local funding or federal funding). Either one has a direct effect on the other and will decide which path your local agency will take.


'''Square 12'''
:Resources:


The Section 106 Historic Register approval / clearance should be available by this time. If you have approval letter, make a copy and hold until you move ahead one space.  
:If the LPA is staffed to acquire ROW they can proceed using LPA staff approved under the ROW Training Certification column on the Official [https://www.modot.org/media/49567 LPA Basic Training and ROW Negotiator Training Roster]. ONLY the LPA will be accountable for adherence to the requirements of state laws and the CFR Titles 23 and 49, including the Uniform Act.


'''Square 13'''
:If the LPA is not staffed to acquire ROW, they should hire a ROW Consultant from [https://www.modot.org/row-negotiators-and-appraisers MoDOT’s approved list]. These may include appraisers, negotiators, lawyers, mediators or any firm which handles all types of ROW services. The LPA and the ROW Consultant will both be accountable for adherence to the requirements of state laws and the CFR Titles 23 and 49, including the Uniform Act.


Fill out the [https://epg.modot.org/forms/general_files/DE/LPA/Acquisition_Authority_Request(Form_136.8.1).docx Acquisition Authority Request (Form 136.8.1)]. If you have taken the path of FHWA, use the A-Date Request form to have MoDOT review and forward it to FHWA and obligate federal funds for ROW Acquisition. Move ahead and wait.
:Funding:


'''Square 14'''
:If the cost to acquire ROW is within the local funds held by the LPA for this project, then it may be prudent to use local funding. All ROW costs will be paid by the LPA. If the local fundings is insufficient for the ROW cost estimated, the LPA should request federal reimbursement for ROW expenses.


If you are following the path marked Local, complete the “Request for ROW Authority (A-Date) Notice to Proceed” and check the box “Local Public Agency will fund all ROW activities…”, MoDOT COROW will grant your approval to begin ROW Acquisition without the use of federal funds in ROW. You will be notified when you may begin acquisition. If you check the box “Local Public Agency is requesting Federal Participation in funding ROW activities", then you must wait for FHWA to obligate those federal funds.
'''Steps 8 and 9'''


The only thing you should have done at this point with regard to ROW Acquisition is title work, ROW plans, cost estimates and complete the ROW Scheduling Tool. These are all eligible for reimbursement under Preliminary Engineering (PE). You may also send a letter to all affected property owners, to advise them of their rights according to the [https://revisor.mo.gov/main/OneChapter.aspx?chapter=523&constit= Eminent Domain Law, RsMO 523.000].  
Fill out the [https://epg.modot.org/forms/LPA/DE/136.8%20Local%20Public%20Agency%20Land%20Acquisition/136.8.1%20Acquisition%20Authority%20Request.docx Acquisition Authority Request (Form 136.8.1)] based on your determination if the LPA is funding the ROW acquisitions or if you have taken the path to request FHWA approval for reimbursement of ROW acquisition costs.  


'''Square 15'''
If you are following the path marked Local, complete the “[https://epg.modot.org/forms/LPA/DE/136.8%20Local%20Public%20Agency%20Land%20Acquisition/136.8.1%20Acquisition%20Authority%20Request.docx Acquisition Authority Request (Form 136.8.1)]” and check the box “Local Public Agency will fund all ROW activities…”, MoDOT - Central Office ROW will grant your approval to begin ROW Acquisition without the use of federal funds. You will be notified when you may begin acquisition. If you check the box “Local Public Agency is requesting Federal Participation in funding ROW activities”, then you must wait for FHWA to obligate those federal funds.


You will get an email, phone call or a letter telling you the federal funds are now approved, and you may begin the acquisition of ROW and Easements for your project.
The only thing you should have done at this point regarding ROW Acquisition is title work, ROW plans, cost estimates and, complete the [https://epg.modot.org/forms/LPA/DE/136.8%20Local%20Public%20Agency%20Land%20Acquisition/136.8.2.2%20Right%20of%20Way%20Acquisition%20Schedule.docx Right of Way Scheduling Tool]. These are all eligible for reimbursement under Preliminary Engineering (PE). You may also send a letter to all affected property owners, to advise them of their rights according to the [https://revisor.mo.gov/main/OneChapter.aspx?chapter=523&constit= Eminent Domain Law, RsMO 523.000].


'''Squares 16A and 17A'''
You will receive an email from MoDOT COROW informing you that the federal funds are now approved, and you may begin the acquisition of ROW and Easements for your project.


If your project is not complicated, you may want to request donation from the owners. Move to the next square. If the owners sign those donation documents, and deeds conveying the easements you need, make sure the owners also sign the waiver of compensation letter. This is a federal regulation to ensure they were informed of their rights to compensation for any type of acquisition on their property. Once you have all of them signed, move one square.
'''Step 10'''


'''Square 18A'''
If your project is not complicated, you may want to request donation from the owners. If the owners sign those donation documents, and deeds conveying the easements you need, make sure the owners also sign the waiver of compensation letter. This is a federal regulation to ensure they were informed of their rights to compensation for any type of acquisition on their property. Once you have all of them signed, move to the next step.


In either case, complicated or not, the deeds must be recorded. This can be costly so remember to plan for this expense when making the decision on whether to use federal funds or local funds for acquisition. Along the way, be sure to work on completing the final plans package (PSE) for construction. Do not advertise until allowed by MoDOT.
If your project is complicated, you can begin appraising the realty rights required for the project. Negotiate the offers and justify the administrative settlements, if necessary. Then, for those owners with whom you cannot reach an agreement, you may want to consider Condemnation and the effects of acquiring the parcels through Eminent domain. You have the right to do this, so use it if you must. After all, any project built on all of the easements and ROW originally proposed is a better project than one with less ROW acquired.


'''Squares 16B, 17B and 18B'''
'''Step 11'''


If your project is complicated, you can begin to get property appraised, have those appraisals reviewed and move to the next square. Negotiate the offers and justify settlements, if necessary and move on. Then, for those owners with whom you cannot reach an agreement, you may want to consider Condemnation and the effects of acquiring the parcels thru Eminent domain. You have the right to do this, so use it if you must. After all, any project built on all of the easements and ROW originally proposed is a better project than one with less ROW acquired.  
In either case, complicated or not, the property owners are paid, and the deeds are recorded. This can be costly so remember to plan for this expense when making the decision on whether to use federal funds or local funds for acquisition. Along the way, be sure to work on completing the final plans package (PSE) for construction. Do not advertise until allowed by MoDOT.


'''Square 19'''
'''Step 12'''


Submit your ROW Clearance Certification Statement to MoDOT COROW. Please do this as early as possible to ensure there is time to review the acquisition files. Many times, ROW personnel will be available to come to your city or county to perform the review. In most cases, this may be more efficient; if there are any changes to be made, it typically can be handled on the spot.  
Submit your ROW Clearance Certification to the MoDOT District LPA contact and Central Office ROW. Please do this as early as possible to ensure there is time to review the acquisition files.  


If your parcel files are not in order, you will spend whatever additional time it takes to remedy the situation in order to certify the ROW is clear. This must be completed before any construction activity can take place. If the parcels have been acquired according to policies and procedures, MoDOT will advise you that your ROW Clearance Certification Statement is approved and ready to move the project along.  
If your parcel files are not in order, you will spend whatever additional time it takes to remedy the situation in order to certify the ROW is clear. This must be completed before any construction activity can take place. If the parcels have been acquired according to policies and procedures, MoDOT will advise you that your ROW Clearance Certification is approved and ready to move the project along.


'''Square 20'''
'''Step 13'''


Congratulations, you have successfully completed the three steps involved in ROW Acquisition; ROW Plans, Acquisition Authority, and ROW Clearance Certification Statement.  
Congratulations, you have successfully completed the steps involved in ROW Acquisition; ROW Plans, Acquisition Authority, and ROW Clearance Certification.


Should you have any questions, please refer to the remainder of this LPA-LAM or contact your MoDOT Federal-Aid Project representative.
Should you have any questions, please contact your MoDOT District LPA contact.

Latest revision as of 12:31, 19 November 2026

1

Copy 136.8.1.6 Local Public Agency - ROW and Easement Acquisition


136.8.1.6 Local Public Agency - ROW and Easement Acquisition

General Summary of the ROW Process

The Local Public Agency (LPA) has been awarded a federal-aid project on the Transportation Implementation Program (TIP). The Reasonable Progress Policy and the schedule set by the LPA fixes timelines to be met. With ROW acquisition involved in your project, you must plan to continue the design and acquire ROW simultaneously. Coordination and planning are key to the success of the LPA. To this end, MoDOT has prepared a simple flow chart to help you visualize and plan the acquisition process for your LPA project.

ROW Flow Chart for the LPA
An easily printable version of the chart is also available.

The goal is to acquire right of way AND certify it clear; at the same time the final Plans Specifications and Estimates (PSE) package is approved. Ultimately, the final PSE should not obstruct the completion of the ROW clearance, and the ROW clearance should not delay the Final PSE.

These instructions should be used as a map to identify where you are in the ROW Process and what to do next. Like many maps, it will not tell you how long it takes, but simply how to get there. How long it will take is up to the project sponsor and the designer. Dealing with private property owners can be dynamic and complicated but is not out of your control. The more time you can allow for this phase, the more likely you are to meet your schedule for construction.

Step 1

The ROW Process actually begins during the Preliminary Design Plans (PDP) stage. The PDP must be approved prior to submitting ROW Plans for approval. This is because the FHWA intends to ensure the alignment will not change before participating in ROW or Construction costs. When your Preliminary Design plans are approved, please move ahead.

Step 2

The approvals you must obtain during PDP directly affect your ability to begin ROW Acquisition. Check with your MoDOT District LPA contact on the status of the environmental and historic clearances. Among other requirements, the environmental categorical exclusion approval must be obtained before the ROW plans can be approved.

Some projects will receive a programmatic categorical exclusion (PCE) for the National Environmental Policy Act (NEPA) environmental clearance and a CE2 submittal will not be required. All projects will still require a Section 106 Historic clearance, as part of the NEPA approval. When the CE2 or PCE has been approved you may move to the next step.

Step 3, 4, and 5

Submit ROW Plans to MoDOT CO ROW for review, if there are comments made, revise them and move ahead. If no comments are made and the ROW Plans are approved, skip the next step and move directly to Step 5, ROW Plans Approved.

Step 6

With no time to waste, move ahead to Step 6; review the most recent ROW Cost Estimate for accuracy, age and any new developments with regard to property owners, land sales or new construction. Now is the time to update this cost estimate to ensure you have an accurate number. For a list of eligible and reimbursable ROW costs, contact your MoDOT Central Office ROW. Now move to the next step.

Step 7

Now that you’re reasonably sure how much it will cost, the LPA must determine who will acquire the ROW (local or consultant) and how it will be paid for (local funding or federal funding). Either one has a direct effect on the other and will decide which path your local agency will take.

Resources:
If the LPA is staffed to acquire ROW they can proceed using LPA staff approved under the ROW Training Certification column on the Official LPA Basic Training and ROW Negotiator Training Roster. ONLY the LPA will be accountable for adherence to the requirements of state laws and the CFR Titles 23 and 49, including the Uniform Act.
If the LPA is not staffed to acquire ROW, they should hire a ROW Consultant from MoDOT’s approved list. These may include appraisers, negotiators, lawyers, mediators or any firm which handles all types of ROW services. The LPA and the ROW Consultant will both be accountable for adherence to the requirements of state laws and the CFR Titles 23 and 49, including the Uniform Act.
Funding:
If the cost to acquire ROW is within the local funds held by the LPA for this project, then it may be prudent to use local funding. All ROW costs will be paid by the LPA. If the local fundings is insufficient for the ROW cost estimated, the LPA should request federal reimbursement for ROW expenses.

Steps 8 and 9

Fill out the Acquisition Authority Request (Form 136.8.1) based on your determination if the LPA is funding the ROW acquisitions or if you have taken the path to request FHWA approval for reimbursement of ROW acquisition costs.

If you are following the path marked Local, complete the “Acquisition Authority Request (Form 136.8.1)” and check the box “Local Public Agency will fund all ROW activities…”, MoDOT - Central Office ROW will grant your approval to begin ROW Acquisition without the use of federal funds. You will be notified when you may begin acquisition. If you check the box “Local Public Agency is requesting Federal Participation in funding ROW activities”, then you must wait for FHWA to obligate those federal funds.

The only thing you should have done at this point regarding ROW Acquisition is title work, ROW plans, cost estimates and, complete the Right of Way Scheduling Tool. These are all eligible for reimbursement under Preliminary Engineering (PE). You may also send a letter to all affected property owners, to advise them of their rights according to the Eminent Domain Law, RsMO 523.000.

You will receive an email from MoDOT COROW informing you that the federal funds are now approved, and you may begin the acquisition of ROW and Easements for your project.

Step 10

If your project is not complicated, you may want to request donation from the owners. If the owners sign those donation documents, and deeds conveying the easements you need, make sure the owners also sign the waiver of compensation letter. This is a federal regulation to ensure they were informed of their rights to compensation for any type of acquisition on their property. Once you have all of them signed, move to the next step.

If your project is complicated, you can begin appraising the realty rights required for the project. Negotiate the offers and justify the administrative settlements, if necessary. Then, for those owners with whom you cannot reach an agreement, you may want to consider Condemnation and the effects of acquiring the parcels through Eminent domain. You have the right to do this, so use it if you must. After all, any project built on all of the easements and ROW originally proposed is a better project than one with less ROW acquired.

Step 11

In either case, complicated or not, the property owners are paid, and the deeds are recorded. This can be costly so remember to plan for this expense when making the decision on whether to use federal funds or local funds for acquisition. Along the way, be sure to work on completing the final plans package (PSE) for construction. Do not advertise until allowed by MoDOT.

Step 12

Submit your ROW Clearance Certification to the MoDOT District LPA contact and Central Office ROW. Please do this as early as possible to ensure there is time to review the acquisition files.

If your parcel files are not in order, you will spend whatever additional time it takes to remedy the situation in order to certify the ROW is clear. This must be completed before any construction activity can take place. If the parcels have been acquired according to policies and procedures, MoDOT will advise you that your ROW Clearance Certification is approved and ready to move the project along.

Step 13

Congratulations, you have successfully completed the steps involved in ROW Acquisition; ROW Plans, Acquisition Authority, and ROW Clearance Certification.

Should you have any questions, please contact your MoDOT District LPA contact.