User:Hoskir/Revision Request 4308: Difference between revisions
No edit summary |
|||
| (2 intermediate revisions by the same user not shown) | |||
| Line 23: | Line 23: | ||
The approvals you must obtain during PDP directly affect your ability to begin ROW Acquisition. Check with your MoDOT District LPA contact on the status of the environmental and historic clearances. Among other requirements, the environmental categorical exclusion approval must be obtained before the ROW plans can be approved. | The approvals you must obtain during PDP directly affect your ability to begin ROW Acquisition. Check with your MoDOT District LPA contact on the status of the environmental and historic clearances. Among other requirements, the environmental categorical exclusion approval must be obtained before the ROW plans can be approved. | ||
Some projects will receive a programmatic categorical exclusion (PCE) for the National Environmental Policy Act (NEPA) environmental clearance and a CE2 submittal will not be required. All projects will still require a [[127.2_Historic_Preservation_and_Cultural_Resources|Section 106 Historic clearance]], as part of the NEPA approval. When the CE2 or PCE has been approved | Some projects will receive a programmatic categorical exclusion (PCE) for the National Environmental Policy Act (NEPA) environmental clearance and a CE2 submittal will not be required. All projects will still require a [[127.2_Historic_Preservation_and_Cultural_Resources|Section 106 Historic clearance]], as part of the NEPA approval. When the CE2 or PCE has been approved you may move to the next step. | ||
'''Step 3, 4, and 5''' | '''Step 3, 4, and 5''' | ||
| Line 33: | Line 33: | ||
With no time to waste, move ahead to Step 6; review the most recent ROW Cost Estimate for accuracy, age and any new developments with regard to property owners, land sales or new construction. Now is the time to update this cost estimate to ensure you have an accurate number. For a list of eligible and reimbursable ROW costs, contact your MoDOT Central Office ROW. Now move to the next step. | With no time to waste, move ahead to Step 6; review the most recent ROW Cost Estimate for accuracy, age and any new developments with regard to property owners, land sales or new construction. Now is the time to update this cost estimate to ensure you have an accurate number. For a list of eligible and reimbursable ROW costs, contact your MoDOT Central Office ROW. Now move to the next step. | ||
Step 7 | '''Step 7''' | ||
Now that you’re reasonably sure how much it will cost, the LPA must determine who will acquire the ROW (local or consultant) and how it will be paid for (local funding or federal funding). Either one has a direct effect on the other and will decide which path your local agency will take. | Now that you’re reasonably sure how much it will cost, the LPA must determine who will acquire the ROW (local or consultant) and how it will be paid for (local funding or federal funding). Either one has a direct effect on the other and will decide which path your local agency will take. | ||
Resources: | :Resources: | ||
If the LPA is staffed to acquire ROW they can proceed using LPA staff approved under the ROW Training Certification column on the Official [https://www.modot.org/media/49567 LPA Basic Training and ROW Negotiator Training Roster]. ONLY the LPA will be accountable for adherence to the requirements of state laws and the CFR Titles 23 and 49, including the Uniform Act. | :If the LPA is staffed to acquire ROW they can proceed using LPA staff approved under the ROW Training Certification column on the Official [https://www.modot.org/media/49567 LPA Basic Training and ROW Negotiator Training Roster]. ONLY the LPA will be accountable for adherence to the requirements of state laws and the CFR Titles 23 and 49, including the Uniform Act. | ||
If the LPA is not staffed to acquire ROW, they should hire a ROW Consultant from [https://www.modot.org/row-negotiators-and-appraisers MoDOT’s approved list]. These may include appraisers, negotiators, lawyers, mediators or any firm which handles all types of ROW services. The LPA and the ROW Consultant will both be accountable for adherence to the requirements of state laws and the CFR Titles 23 and 49, including the Uniform Act. | :If the LPA is not staffed to acquire ROW, they should hire a ROW Consultant from [https://www.modot.org/row-negotiators-and-appraisers MoDOT’s approved list]. These may include appraisers, negotiators, lawyers, mediators or any firm which handles all types of ROW services. The LPA and the ROW Consultant will both be accountable for adherence to the requirements of state laws and the CFR Titles 23 and 49, including the Uniform Act. | ||
Funding: | :Funding: | ||
If the cost to acquire ROW is within the local funds held by the LPA for this project, then it may be prudent to use local | :If the cost to acquire ROW is within the local funds held by the LPA for this project, then it may be prudent to use local funding. All ROW costs will be paid by the LPA. If the local fundings is insufficient for the ROW cost estimated, the LPA should request federal reimbursement for ROW expenses. | ||
'''Steps 8 and 9''' | '''Steps 8 and 9''' | ||
Fill out the [https://epg.modot.org/forms/LPA/DE/136.8%20Local%20Public%20Agency%20Land%20Acquisition/136.8.1%20Acquisition%20Authority%20Request.docx Acquisition Authority Request (Form 136.8.1)] based on your determination if the LPA is funding the ROW acquisitions or if you have taken the path to request FHWA approval for reimbursement of ROW acquisition costs. | |||
Fill out the [https://epg.modot.org/forms/ | |||
If you are following the path marked Local, complete the “[https://epg.modot.org/forms/LPA/DE/136.8%20Local%20Public%20Agency%20Land%20Acquisition/136.8.1%20Acquisition%20Authority%20Request.docx Acquisition Authority Request (Form 136.8.1)]” and check the box “Local Public Agency will fund all ROW activities…”, MoDOT - Central Office ROW will grant your approval to begin ROW Acquisition without the use of federal funds. You will be notified when you may begin acquisition. If you check the box “Local Public Agency is requesting Federal Participation in funding ROW activities”, then you must wait for FHWA to obligate those federal funds. | |||
The only thing you should have done at this point regarding ROW Acquisition is title work, ROW plans, cost estimates and, complete the [https://epg.modot.org/forms/LPA/DE/136.8%20Local%20Public%20Agency%20Land%20Acquisition/136.8.2.2%20Right%20of%20Way%20Acquisition%20Schedule.docx Right of Way Scheduling Tool]. These are all eligible for reimbursement under Preliminary Engineering (PE). You may also send a letter to all affected property owners, to advise them of their rights according to the [https://revisor.mo.gov/main/OneChapter.aspx?chapter=523&constit= Eminent Domain Law, RsMO 523.000]. | |||
You will receive an email from MoDOT COROW informing you that the federal funds are now approved, and you may begin the acquisition of ROW and Easements for your project. | |||
'''Step 10''' | |||
If your project is not complicated, you may want to request donation from the owners. If the owners sign those donation documents, and deeds conveying the easements you need, make sure the owners also sign the waiver of compensation letter. This is a federal regulation to ensure they were informed of their rights to compensation for any type of acquisition on their property. Once you have all of them signed, move to the next step. | |||
If your project is complicated, you can begin appraising the realty rights required for the project. Negotiate the offers and justify the administrative settlements, if necessary. Then, for those owners with whom you cannot reach an agreement, you may want to consider Condemnation and the effects of acquiring the parcels through Eminent domain. You have the right to do this, so use it if you must. After all, any project built on all of the easements and ROW originally proposed is a better project than one with less ROW acquired. | |||
''' | '''Step 11''' | ||
In either case, complicated or not, the property owners are paid, and the deeds are recorded. This can be costly so remember to plan for this expense when making the decision on whether to use federal funds or local funds for acquisition. Along the way, be sure to work on completing the final plans package (PSE) for construction. Do not advertise until allowed by MoDOT. | |||
''' | '''Step 12''' | ||
Submit your ROW Clearance Certification | Submit your ROW Clearance Certification to the MoDOT District LPA contact and Central Office ROW. Please do this as early as possible to ensure there is time to review the acquisition files. | ||
If your parcel files are not in order, you will spend whatever additional time it takes to remedy the situation in order to certify the ROW is clear. This must be completed before any construction activity can take place. If the parcels have been acquired according to policies and procedures, MoDOT will advise you that your ROW Clearance Certification | If your parcel files are not in order, you will spend whatever additional time it takes to remedy the situation in order to certify the ROW is clear. This must be completed before any construction activity can take place. If the parcels have been acquired according to policies and procedures, MoDOT will advise you that your ROW Clearance Certification is approved and ready to move the project along. | ||
''' | '''Step 13''' | ||
Congratulations, you have successfully completed the | Congratulations, you have successfully completed the steps involved in ROW Acquisition; ROW Plans, Acquisition Authority, and ROW Clearance Certification. | ||
Should you have any questions, please | Should you have any questions, please contact your MoDOT District LPA contact. | ||
Latest revision as of 12:31, 19 November 2026
1
Copy 136.8.1.6 Local Public Agency - ROW and Easement Acquisition
136.8.1.6 Local Public Agency - ROW and Easement Acquisition
General Summary of the ROW Process
The Local Public Agency (LPA) has been awarded a federal-aid project on the Transportation Implementation Program (TIP). The Reasonable Progress Policy and the schedule set by the LPA fixes timelines to be met. With ROW acquisition involved in your project, you must plan to continue the design and acquire ROW simultaneously. Coordination and planning are key to the success of the LPA. To this end, MoDOT has prepared a simple flow chart to help you visualize and plan the acquisition process for your LPA project.

An easily printable version of the chart is also available.
The goal is to acquire right of way AND certify it clear; at the same time the final Plans Specifications and Estimates (PSE) package is approved. Ultimately, the final PSE should not obstruct the completion of the ROW clearance, and the ROW clearance should not delay the Final PSE.
These instructions should be used as a map to identify where you are in the ROW Process and what to do next. Like many maps, it will not tell you how long it takes, but simply how to get there. How long it will take is up to the project sponsor and the designer. Dealing with private property owners can be dynamic and complicated but is not out of your control. The more time you can allow for this phase, the more likely you are to meet your schedule for construction.
Step 1
The ROW Process actually begins during the Preliminary Design Plans (PDP) stage. The PDP must be approved prior to submitting ROW Plans for approval. This is because the FHWA intends to ensure the alignment will not change before participating in ROW or Construction costs. When your Preliminary Design plans are approved, please move ahead.
Step 2
The approvals you must obtain during PDP directly affect your ability to begin ROW Acquisition. Check with your MoDOT District LPA contact on the status of the environmental and historic clearances. Among other requirements, the environmental categorical exclusion approval must be obtained before the ROW plans can be approved.
Some projects will receive a programmatic categorical exclusion (PCE) for the National Environmental Policy Act (NEPA) environmental clearance and a CE2 submittal will not be required. All projects will still require a Section 106 Historic clearance, as part of the NEPA approval. When the CE2 or PCE has been approved you may move to the next step.
Step 3, 4, and 5
Submit ROW Plans to MoDOT CO ROW for review, if there are comments made, revise them and move ahead. If no comments are made and the ROW Plans are approved, skip the next step and move directly to Step 5, ROW Plans Approved.
Step 6
With no time to waste, move ahead to Step 6; review the most recent ROW Cost Estimate for accuracy, age and any new developments with regard to property owners, land sales or new construction. Now is the time to update this cost estimate to ensure you have an accurate number. For a list of eligible and reimbursable ROW costs, contact your MoDOT Central Office ROW. Now move to the next step.
Step 7
Now that you’re reasonably sure how much it will cost, the LPA must determine who will acquire the ROW (local or consultant) and how it will be paid for (local funding or federal funding). Either one has a direct effect on the other and will decide which path your local agency will take.
- Resources:
- If the LPA is staffed to acquire ROW they can proceed using LPA staff approved under the ROW Training Certification column on the Official LPA Basic Training and ROW Negotiator Training Roster. ONLY the LPA will be accountable for adherence to the requirements of state laws and the CFR Titles 23 and 49, including the Uniform Act.
- If the LPA is not staffed to acquire ROW, they should hire a ROW Consultant from MoDOT’s approved list. These may include appraisers, negotiators, lawyers, mediators or any firm which handles all types of ROW services. The LPA and the ROW Consultant will both be accountable for adherence to the requirements of state laws and the CFR Titles 23 and 49, including the Uniform Act.
- Funding:
- If the cost to acquire ROW is within the local funds held by the LPA for this project, then it may be prudent to use local funding. All ROW costs will be paid by the LPA. If the local fundings is insufficient for the ROW cost estimated, the LPA should request federal reimbursement for ROW expenses.
Steps 8 and 9
Fill out the Acquisition Authority Request (Form 136.8.1) based on your determination if the LPA is funding the ROW acquisitions or if you have taken the path to request FHWA approval for reimbursement of ROW acquisition costs.
If you are following the path marked Local, complete the “Acquisition Authority Request (Form 136.8.1)” and check the box “Local Public Agency will fund all ROW activities…”, MoDOT - Central Office ROW will grant your approval to begin ROW Acquisition without the use of federal funds. You will be notified when you may begin acquisition. If you check the box “Local Public Agency is requesting Federal Participation in funding ROW activities”, then you must wait for FHWA to obligate those federal funds.
The only thing you should have done at this point regarding ROW Acquisition is title work, ROW plans, cost estimates and, complete the Right of Way Scheduling Tool. These are all eligible for reimbursement under Preliminary Engineering (PE). You may also send a letter to all affected property owners, to advise them of their rights according to the Eminent Domain Law, RsMO 523.000.
You will receive an email from MoDOT COROW informing you that the federal funds are now approved, and you may begin the acquisition of ROW and Easements for your project.
Step 10
If your project is not complicated, you may want to request donation from the owners. If the owners sign those donation documents, and deeds conveying the easements you need, make sure the owners also sign the waiver of compensation letter. This is a federal regulation to ensure they were informed of their rights to compensation for any type of acquisition on their property. Once you have all of them signed, move to the next step.
If your project is complicated, you can begin appraising the realty rights required for the project. Negotiate the offers and justify the administrative settlements, if necessary. Then, for those owners with whom you cannot reach an agreement, you may want to consider Condemnation and the effects of acquiring the parcels through Eminent domain. You have the right to do this, so use it if you must. After all, any project built on all of the easements and ROW originally proposed is a better project than one with less ROW acquired.
Step 11
In either case, complicated or not, the property owners are paid, and the deeds are recorded. This can be costly so remember to plan for this expense when making the decision on whether to use federal funds or local funds for acquisition. Along the way, be sure to work on completing the final plans package (PSE) for construction. Do not advertise until allowed by MoDOT.
Step 12
Submit your ROW Clearance Certification to the MoDOT District LPA contact and Central Office ROW. Please do this as early as possible to ensure there is time to review the acquisition files.
If your parcel files are not in order, you will spend whatever additional time it takes to remedy the situation in order to certify the ROW is clear. This must be completed before any construction activity can take place. If the parcels have been acquired according to policies and procedures, MoDOT will advise you that your ROW Clearance Certification is approved and ready to move the project along.
Step 13
Congratulations, you have successfully completed the steps involved in ROW Acquisition; ROW Plans, Acquisition Authority, and ROW Clearance Certification.
Should you have any questions, please contact your MoDOT District LPA contact.