119.1 Definitions: Difference between revisions

From Engineering Policy Guide
Jump to navigation Jump to search
No edit summary
Tag: visualeditor
No edit summary
Line 8: Line 8:




[[index.php?title=Category:119 Project Schedules]]
[[Category:119 Project Schedules]]

Revision as of 14:42, 18 March 2025

Baseline 0 – The current project schedule which is represented in the reporting dashboards

Baseline 1 – The first historical copy of the schedule. Other historical records can be established if major schedule changes occur and will follow numbering succession (2,3,4 etc.)

Publish – When schedule progression changes are officially updated to the reporting dashboards

Predecessor – A task which must be completed before another task can begin