Difference between revisions of "Talk:127.9 Floodplain Management"

From Engineering_Policy_Guide
Jump to navigation Jump to search
(127.9.2 Process)
 
m (address the comment)
Line 2: Line 2:
  
 
''If there is to be an encroachment into the regulatory floodway, MoDOT must issue a "No-Rise" Certification as required by SEMA to obtain a floodplain development permit that is needed for any encroachment into the 100-year floodplain, regardless of whether it also takes place within the regulatory floodway.''
 
''If there is to be an encroachment into the regulatory floodway, MoDOT must issue a "No-Rise" Certification as required by SEMA to obtain a floodplain development permit that is needed for any encroachment into the 100-year floodplain, regardless of whether it also takes place within the regulatory floodway.''
 +
 +
Sam Masters:  The short answer to your question is "No, they are not the same".  However, your question does illustrate the need to "clarify" the information in this article.  I have created a link to another article entitled "748.9 National Flood Insurance Program (NFIP)".  This article contains [[748.9 National Flood Insurance Program (NFIP)#748.9.3 Floodway|a map]] which describes the relationship between the "regulatory floodway" and the "100-year floodplain".  Further "clarifications" to the 127.9 article are possible in the very near future.

Revision as of 09:50, 24 November 2008

Could you explain the meaning of the second to last sentence in 127.9.2? Should the first reference to "regulatory floodway" be changed to "100-year floodplain"?

If there is to be an encroachment into the regulatory floodway, MoDOT must issue a "No-Rise" Certification as required by SEMA to obtain a floodplain development permit that is needed for any encroachment into the 100-year floodplain, regardless of whether it also takes place within the regulatory floodway.

Sam Masters: The short answer to your question is "No, they are not the same". However, your question does illustrate the need to "clarify" the information in this article. I have created a link to another article entitled "748.9 National Flood Insurance Program (NFIP)". This article contains a map which describes the relationship between the "regulatory floodway" and the "100-year floodplain". Further "clarifications" to the 127.9 article are possible in the very near future.