User:Hoskir/Revision Request 4325: Difference between revisions
No edit summary |
No edit summary |
||
| Line 32: | Line 32: | ||
In addition, no additional items of work should be added without first coordinating with the EPS section. Our experience to date has shown that adding specialty items of work may discourage contractors from bidding on a typical maintenance contract because the specialty work may be subcontracted out for additional costs. Many times, specialty items of work or items of work not identified in the list of fixed costs are better managed by negotiating a price with the JOC contractor. Establishment of pricing for any non-fixed cost pay items will be in accordance with [https://www.modot.org/missouri-standard-specifications-highway-construction Sec 109.4.2 or 109.4.3] of the Missouri Standard Specifications for Highway Construction. If no agreement to pricing can be made, then the work will proceed with payment for non-fixed cost items under [https://www.modot.org/missouri-standard-specifications-highway-construction Sec 109.4.4]. | In addition, no additional items of work should be added without first coordinating with the EPS section. Our experience to date has shown that adding specialty items of work may discourage contractors from bidding on a typical maintenance contract because the specialty work may be subcontracted out for additional costs. Many times, specialty items of work or items of work not identified in the list of fixed costs are better managed by negotiating a price with the JOC contractor. Establishment of pricing for any non-fixed cost pay items will be in accordance with [https://www.modot.org/missouri-standard-specifications-highway-construction Sec 109.4.2 or 109.4.3] of the Missouri Standard Specifications for Highway Construction. If no agreement to pricing can be made, then the work will proceed with payment for non-fixed cost items under [https://www.modot.org/missouri-standard-specifications-highway-construction Sec 109.4.4]. | ||
Districts should enter the job specific information (highlighted yellow within the standard templates). Do not include the standard JSP1301 Contract Liquidated Damages. Specific guidance for [[#147.3.4_Term_of_Contract|Term of Contract]], [[#147.3.5_Contract_Award|Contract Award]], and [[#147.3. | Districts should enter the job specific information (highlighted yellow within the standard templates). Do not include the standard JSP1301 Contract Liquidated Damages. Specific guidance for [[#147.3.4_Term_of_Contract|Term of Contract]], [[#147.3.5_Contract_Award|Contract Award]], and [[#147.3.7_How_to_Record_Projects_in_MODOT_Specific_Systems|specific MODOT programs]] can be found within this article. | ||
==147.3.2 Fixed Unit Price List and Non-Fixed Cost Items== | ==147.3.2 Fixed Unit Price List and Non-Fixed Cost Items== | ||
| Line 38: | Line 38: | ||
'''Fixed Unit Price List.''' A fixed unit price list containing unit prices for the various items of work for each job order is included in the JOC bid proposal. Fixed unit prices exclude profit and overhead (which are covered in the adjustment factor) but do account for complete and in-place construction, including all labor, equipment and material required to complete the construction task. All labor, material, equipment and work required by a specification shall be considered part of the fixed unit price, unless otherwise stated elsewhere in the contract. | '''Fixed Unit Price List.''' A fixed unit price list containing unit prices for the various items of work for each job order is included in the JOC bid proposal. Fixed unit prices exclude profit and overhead (which are covered in the adjustment factor) but do account for complete and in-place construction, including all labor, equipment and material required to complete the construction task. All labor, material, equipment and work required by a specification shall be considered part of the fixed unit price, unless otherwise stated elsewhere in the contract. | ||
'''Non-Fixed Cost Items.''' These are contingent items of work for which a description and fixed cost is not set forth in the pay item list. Payment for non-fixed cost pay items will be determined in accordance with Sec 109.4.2, 109.4.3, or 109.4.4. The agreed price for non-fixed cost pay items includes reasonable profit and overhead; therefore, they are not further adjusted by the contract Adjustment Factor (i.e. they will be paid using an Adjustment Factor of 1.000). The approval level for non-fixed cost pay items shall be as indicated in [[#147.3. | '''Non-Fixed Cost Items.''' These are contingent items of work for which a description and fixed cost is not set forth in the pay item list. Payment for non-fixed cost pay items will be determined in accordance with Sec 109.4.2, 109.4.3, or 109.4.4. The agreed price for non-fixed cost pay items includes reasonable profit and overhead; therefore, they are not further adjusted by the contract Adjustment Factor (i.e. they will be paid using an Adjustment Factor of 1.000). The approval level for non-fixed cost pay items shall be as indicated in [[#147.3.8.4_Change_Order_Approvals|EPG 147.3.8.4]]. | ||
==147.3.3 Adjustment Factor== | ==147.3.3 Adjustment Factor== | ||
| Line 80: | Line 80: | ||
==147.3.5 Contract Award== | ==147.3.5 Contract Award== | ||
The contract award amount should match the STIP amount, which represents the two year budget. The district will update the yellow highlighted percentage of work expected to be required as daytime, nighttime or weekend hours to help the bidder determine the factor for the required work based on project specific requirements. See [[#147.3. | The contract award amount should match the STIP amount, which represents the two year budget. The district will update the yellow highlighted percentage of work expected to be required as daytime, nighttime or weekend hours to help the bidder determine the factor for the required work based on project specific requirements. See [[#147.3.7.1_STIP_Information_Management_System_(SIMS)|SIMS]] below for specific entry. | ||
==147.3. | ==147.3.6 Traffic Control Plan Types== | ||
The JOC contracts shall include Traffic Control Plans (TCP). | The JOC contracts shall include Traffic Control Plans (TCP). | ||
| Line 98: | Line 98: | ||
* Then right-click in the job directory and select Paste. | * Then right-click in the job directory and select Paste. | ||
==147.3. | ==147.3.7 How to Record Projects in MODOT Specific Systems== | ||
===147.3. | ===147.3.7.1 STIP Information Management System (SIMS)=== | ||
JOCs should be in the March or April Letting. The district will need to program the amount in the STIP that will cover the budget of both years. | JOCs should be in the March or April Letting. The district will need to program the amount in the STIP that will cover the budget of both years. | ||
| Line 108: | Line 108: | ||
[[File:SIMS_example.png|border|800px]] | [[File:SIMS_example.png|border|800px]] | ||
====147.3. | ====147.3.7.1.1 Accelerated JOC Projects==== | ||
If a JOC project is terminated, the district may accelerate the future JOC project. The District Planning Manager will need to have it entered into SIMS by mid-January for approvals to be completed to meet the April letting submittals. See the Amendment Schedule found on [https://modotgov.sharepoint.com/sites/tp/Shared%20Documents/Forms/AllItems.aspx?id=%2Fsites%2Ftp%2FShared%20Documents%2FStatewide%20Programming%2FSTIP%20References%2FSourceFiles%2FAmendments&viewid=539f9e8a%2Dc677%2D42c9%2D895b%2D6b4215bbd4cf&FolderCTID=0x012000DD605E2170F8084F9DE64F06975E86E0&share=cgrTaKYp%5FQ3oT7Pe4fjRD8rHEgUDg78tYkid5b3Xtbk3DOV4hw Transportation Planning SharePoint Site]. | If a JOC project is terminated, the district may accelerate the future JOC project. The District Planning Manager will need to have it entered into SIMS by mid-January for approvals to be completed to meet the April letting submittals. See the Amendment Schedule found on [https://modotgov.sharepoint.com/sites/tp/Shared%20Documents/Forms/AllItems.aspx?id=%2Fsites%2Ftp%2FShared%20Documents%2FStatewide%20Programming%2FSTIP%20References%2FSourceFiles%2FAmendments&viewid=539f9e8a%2Dc677%2D42c9%2D895b%2D6b4215bbd4cf&FolderCTID=0x012000DD605E2170F8084F9DE64F06975E86E0&share=cgrTaKYp%5FQ3oT7Pe4fjRD8rHEgUDg78tYkid5b3Xtbk3DOV4hw Transportation Planning SharePoint Site]. | ||
====147.3. | ====147.3.7.1.2 Closing JOC Contracts in SIMS==== | ||
After close out of JOC contracts, enter the following Reason Description for cost differences greater than 10% into SIMS, <u>Final Cost Justification</u> page with the type of ''Completed Project'': | After close out of JOC contracts, enter the following Reason Description for cost differences greater than 10% into SIMS, <u>Final Cost Justification</u> page with the type of ''Completed Project'': | ||
| Line 118: | Line 118: | ||
''The cost estimate deviated from the actual cost due to this being a Job Order Contract.'' | ''The cost estimate deviated from the actual cost due to this being a Job Order Contract.'' | ||
===147.3. | ===147.3.7.2 Bid Tabs +=== | ||
Each JOC should have two line items, | Each JOC should have two line items, | ||
| Line 132: | Line 132: | ||
[[File:PLUS_report.png|border|800px]] | [[File:PLUS_report.png|border|800px]] | ||
===147.3. | ===147.3.7.3 AASHTOWare Project- Preconstruction=== | ||
After the .xml file is uploaded, the Project Description on the General Tab should be “Job Order Contract and the type of work”. Only the first letter of JOC should be capitalized. Do not capitalize the type of work. | After the .xml file is uploaded, the Project Description on the General Tab should be “Job Order Contract and the type of work”. Only the first letter of JOC should be capitalized. Do not capitalize the type of work. | ||
: Example: Job Order Contract for asphalt pavement repair<li> | |||
The Contract Budget Item will need to be marked as “fixed cost” when it gets reviewed so the bidder cannot bid on this item. By including this item as a fixed cost, the allowed budget amount will be available for project administration without applying the factor to the budget amount. | |||
[[File:contract_budget_item.png|border|700px]] | |||
==147.3.8 Administration Guidelines for Construction== | |||
==147.3. | ===147.3.8.1 Issuing Job Orders=== | ||
The engineer will collaborate with the contractor when developing an individual job order. At any given time, the contractor may be performing more than one job order. | |||
The total cost of an individual job order will be determined by multiplying the fixed unit prices of each fixed cost pay item by the appropriate quantity and then multiplying the total cost of all fixed unit pay items by the adjustment factor. Any non-fixed cost pay items would be added to this total but not expanded by the adjustment factor. | The total cost of an individual job order will be determined by multiplying the fixed unit prices of each fixed cost pay item by the appropriate quantity and then multiplying the total cost of all fixed unit pay items by the adjustment factor. Any non-fixed cost pay items would be added to this total but not expanded by the adjustment factor. | ||
{| | |||
|- | |||
|+ '''Example Job Order''' | |||
Item Description Fixed Unit Price Quantity Price | Item Description Fixed Unit Price Quantity Price | ||
SP125C (PG70-22) Per Ton (100.1-500 Tons) (Over 9 feet wide) $84.00 425.6 tons $35,750.40 | SP125C (PG70-22) Per Ton (100.1-500 Tons) (Over 9 feet wide) $84.00 425.6 tons $35,750.40 | ||
Revision as of 11:00, 17 November 2026
1
Copy 147.3 Job Order Contracting (JOC)
MoDOT uses a contracting process called Job Order Contracting (JOC). This contracting process allows MoDOT to award fixed price construction contracts with indefinite delivery and indefinite quantity (ID/IQ) at individual work locations within the project limits. ID/IQ is governed by FHWA through 23 CFR 635 Subpart F. JOCs are typically used for on-call maintenance repair contracts, including asphalt and concrete pavement repair, guardrail and guard cable repair, bridge repair and fence repair. JOCs can be used for other construction and maintenance contracts. All non-standard JOCs (see list of standard JOCs and links in box below) regardless of funding source, shall be submitted to Engineering Policy Services (EPS) for review of contractual compliance, constructability, and federal reimbursement eligibility, prior to PS&E submittal.
The JOC bid proposal must specify the minimum and maximum program budget to be awarded during a specified contract term. MoDOT is not bound to issue a minimum or maximum number of job orders during the contract term. The maximum budget represents MoDOT’s estimate of needed repairs. Job orders will be issued as repairs are needed, but expenditures could fall below the budget limit if repairs are fewer than anticipated.
JOCs shall have a Disadvantaged Business and Enterprise (DBE) goal set by MoDOT’s Business Development and Compliance. See EPG 146 for additional information.
All JOCs shall be reviewed for NEPA compliance. A Request for Environmental Services (RES) shall be submitted to the Environmental Section at the appropriate project development stage. Job Order Contracts are allowed one RES submittal (a Final RES) submitted annually for the term of the JOC, because they do not change significantly. See EPG 127.1 Request for Environmental Services for additional information.
| JSP Packages for Asphalt Pavement Repair, Bridge, Combined Guardrail/Guard Cable, Concrete Pavement Repair, Fence, Guard Cable and Guardrail |
| Contact a Design Liaison for additional guidance. |
147.3.1 JOC Development
MoDOT Engineering Policy Services conducts an annual internal MoDOT meeting in the fall to discuss lessons learned from the previous calendar year’s job order contracts. Design staff incorporates changes into the next calendar year’s contracts, and updates the job special provision (JSP) templates for distribution to the districts.
The EPS section also updates the fixed costs to reflect the new market value. In the event the costs change significantly, the EPS section coordinates with Bidding and Contract Services (BCS) and the industry to ensure the fixed costs are satisfactory. The fixed costs in the draft proposals should not be adjusted by the districts, without prior input from the EPS section. It is important to have agreement on the fixed unit price list with industry to eliminate any outliers that could cause contractors to bid risk in the adjustment factor.
In addition, no additional items of work should be added without first coordinating with the EPS section. Our experience to date has shown that adding specialty items of work may discourage contractors from bidding on a typical maintenance contract because the specialty work may be subcontracted out for additional costs. Many times, specialty items of work or items of work not identified in the list of fixed costs are better managed by negotiating a price with the JOC contractor. Establishment of pricing for any non-fixed cost pay items will be in accordance with Sec 109.4.2 or 109.4.3 of the Missouri Standard Specifications for Highway Construction. If no agreement to pricing can be made, then the work will proceed with payment for non-fixed cost items under Sec 109.4.4.
Districts should enter the job specific information (highlighted yellow within the standard templates). Do not include the standard JSP1301 Contract Liquidated Damages. Specific guidance for Term of Contract, Contract Award, and specific MODOT programs can be found within this article.
147.3.2 Fixed Unit Price List and Non-Fixed Cost Items
Fixed Unit Price List. A fixed unit price list containing unit prices for the various items of work for each job order is included in the JOC bid proposal. Fixed unit prices exclude profit and overhead (which are covered in the adjustment factor) but do account for complete and in-place construction, including all labor, equipment and material required to complete the construction task. All labor, material, equipment and work required by a specification shall be considered part of the fixed unit price, unless otherwise stated elsewhere in the contract.
Non-Fixed Cost Items. These are contingent items of work for which a description and fixed cost is not set forth in the pay item list. Payment for non-fixed cost pay items will be determined in accordance with Sec 109.4.2, 109.4.3, or 109.4.4. The agreed price for non-fixed cost pay items includes reasonable profit and overhead; therefore, they are not further adjusted by the contract Adjustment Factor (i.e. they will be paid using an Adjustment Factor of 1.000). The approval level for non-fixed cost pay items shall be as indicated in EPG 147.3.8.4.
147.3.3 Adjustment Factor
The contractor will bid an Adjustment Factor for profit and overhead, including, but not limited to, the business and construction related costs as defined below. It is the responsibility of the contractor to verify the fixed unit prices provided in the contract and to modify their bid for the adjustment factor accordingly.
Business Costs. Business related costs consist of profit, overhead costs, subcontractor profit and overhead, taxes, finance costs, and other costs including but not limited to;
- insurance, bonds and indemnification
- project meetings, training, management and supervision
- project office staff and equipment
- employee or subcontractor wage rates that exceed prevailing wages
- fringe benefits, payroll taxes, worker’s compensation, insurance costs and any other payment mandated by law in connection with labor that exceeds the labor rate allowances
- business risks such as the risk of lower than expected volumes of work, smaller than anticipated job orders, poor subcontractor performance, and inflation or material cost fluctuations
Construction Costs. Construction related costs include but are not limited to;
- personnel safety equipment
- security requirements
- excess material waste
- daily and final clean-up
- costs resulting from inadequate supply of materials, fuel, electricity, or skilled labor
- costs resulting from productivity loss
- working in extreme and adverse weather conditions
- any other discreet items of work required to complete a particular job order
General Costs. The above lists are not exhaustive and are intended to provide general examples of cost items to be included in the contractor’s Adjustment Factor as defined in the contract.
147.3.4 Term Of Contract
JOC repairs are budgeted and paid for by Fiscal Year (FY). A standard term of contract should be two years and run from July 1 to June 30. JOC jobs should be let in March and April. There may be situations when JOC jobs may be let outside this period, such as an unsuccessfully awarded contract. In these situations, the JOC contract should follow the standard PS&E chart for the next available Notice to Proceed (NTP) date while keeping the end of term as June 30. There should not be a situation where a JOC contract would be less than one year. For example, a JOC contract is re-let in August, the NTP would be in October, however the end of term of the contract would not be the following June 30, but instead the end of term of the contract would be June 30 of the following second year.
147.3.4.1 Contract Termination
JOC contracts may be terminated early as specified in each contract per the Term of Contract JSP. Is the district satisfied with performance of the contractor? Are the existing bid prices reasonable?
147.3.5 Contract Award
The contract award amount should match the STIP amount, which represents the two year budget. The district will update the yellow highlighted percentage of work expected to be required as daytime, nighttime or weekend hours to help the bidder determine the factor for the required work based on project specific requirements. See SIMS below for specific entry.
147.3.6 Traffic Control Plan Types
The JOC contracts shall include Traffic Control Plans (TCP).
Example TCP for the Job Order Contracts exist as seed files in ProjectWise. These example plans are based on what has been used on past contracts and are for example purposes only.
The JOC TCP files are located in ProjectWise at \Documents\CADD_Standards\ORD Standards\Connect_Config\WorkSpaces\MoDOT\Standards\Seed\Roadway\Job Order Contracting\
All district ProjectWise users will have read-only access to the files.
The following is the process for obtaining a clean copy of all the files at one time:
- Select all of the files, right-click and select Copy.
- Then right-click in the job directory and select Paste.
147.3.7 How to Record Projects in MODOT Specific Systems
147.3.7.1 STIP Information Management System (SIMS)
JOCs should be in the March or April Letting. The district will need to program the amount in the STIP that will cover the budget of both years.
Example: JOC for concrete repair has Contract Estimate of $600,000.
147.3.7.1.1 Accelerated JOC Projects
If a JOC project is terminated, the district may accelerate the future JOC project. The District Planning Manager will need to have it entered into SIMS by mid-January for approvals to be completed to meet the April letting submittals. See the Amendment Schedule found on Transportation Planning SharePoint Site.
147.3.7.1.2 Closing JOC Contracts in SIMS
After close out of JOC contracts, enter the following Reason Description for cost differences greater than 10% into SIMS, Final Cost Justification page with the type of Completed Project:
The cost estimate deviated from the actual cost due to this being a Job Order Contract.
147.3.7.2 Bid Tabs +
Each JOC should have two line items,
- Line 0010 - Pay Item 6189916 Contract Budget DLR
- Line 0020 - Pay Item 6189916 Adjustment Factor DLR
The Bid Price for the Misc. Adjustment Factor should remain as $1.00, and the Quantity for the Misc. Contract Budget should align with the Contract Award section.
147.3.7.3 AASHTOWare Project- Preconstruction
After the .xml file is uploaded, the Project Description on the General Tab should be “Job Order Contract and the type of work”. Only the first letter of JOC should be capitalized. Do not capitalize the type of work.
- Example: Job Order Contract for asphalt pavement repair
The Contract Budget Item will need to be marked as “fixed cost” when it gets reviewed so the bidder cannot bid on this item. By including this item as a fixed cost, the allowed budget amount will be available for project administration without applying the factor to the budget amount.
147.3.8 Administration Guidelines for Construction
147.3.8.1 Issuing Job Orders
The engineer will collaborate with the contractor when developing an individual job order. At any given time, the contractor may be performing more than one job order.
The total cost of an individual job order will be determined by multiplying the fixed unit prices of each fixed cost pay item by the appropriate quantity and then multiplying the total cost of all fixed unit pay items by the adjustment factor. Any non-fixed cost pay items would be added to this total but not expanded by the adjustment factor.