User:Hoskir/Revision Request 4306
1
Copy 103.1.1 and 1.2
103.1.1 Introduction
The Missouri Highway and Transportation Commission policy states all roadway and bridge contracts shall be approved by the Commission. The goal of MoDOT’s bid opening and award process is to achieve competitive bids by packaging projects in a manner that makes them as attractive as possible to potential bidders. Methods of achieving this goal include, but are not limited to, establishing appropriate bid opening dates for the type of work, maintaining a stable bid opening schedule, and grouping or dividing projects to make them more appealing to bidders.
103.1.2 Bid Openings
Design will conduct bid openings for all roadway and bridge construction projects within the right-of-way of the state highway system. Districts may use General Services to conduct bid openings for “maintenance by contract” projects that cost less than $100,000 and have minimal impacts to traffic, such as tree clearing or signal box repair. All other contracted work like culvert replacement must be included in Design’s regularly scheduled monthly bid openings.
103.1.2.1 Emergency, Imminent Danger, and Urgent Work
There may be instances where a failure on our system that needs to be repaired immediately. If this cannot be performed with MoDOT forces or on-call contract, an emergency or urgent contract may be let.
Emergency projects are defined as those situations in which conditions threaten the movement of traffic. These situations include:
- The road or a lane of the road is closed,
- Existing conditions threaten to close the road,
- There is risk to the safety of the traveling public.
The District Engineer must request an emergency, imminent danger or urgent declaration from the Deputy Director/Chief Engineer. The following information will need to be provided for the declaration:
- Work needed to be complete and cause of damage,
- Current road condition: bridge, road, lane, or shoulder closure,
- Proposed project schedule including plans, specifications, and estimate (PS&E) due date, advertisement date, letting date/award, and completion.
Urgent projects allow for flexibility in setting up the project in SIMS and letting date. However, the project will need to adhere to the minimum 3-week advertisement and be awarded by the Commission.
Emergency projects, following declaration from the Deputy Director/Chief Engineer, may allow for the minimum advertisement period (3 weeks) to be waived, and be awarded immediately following the opening of bids by an Executive Team member or the respective District Engineer. The award of Emergency projects must later be ratified by the Commission at the next regularly held meeting.
103.1.2.1.1 Emergency Contract Procedures
The district will need to provide the emergency declaration to Central Office Bidding and Contract Services (BCS) along with a timeline for the anticipated delivery of plans, specifications and estimate (PS&E) for determining the project’s advertisement, pre-bid meeting, letting and award dates. After the schedule is set, the District Transportation Planning Manager will need to work with Central Office Transportation Planning (TP) and Central Office Financial Services (FS) to determine the funding and add the project to SIMS/STIP by emailing TPStateProg and Obligate groups.
The Project Manager will need to submit a RES as soon as possible.
To federalize the project, BCS will submit a waiver request to the FHWA Division Administrator. This approval will need to be shared with FS along with the projects approved TIP (if it is an MPO area), environmental clearance, right of way clearance, and railroad clearance dates to obligate the project.
In most cases, standard advertising requirements may be shortened for emergency projects. The Design Division will work with the district to determine an appropriate advertising period for emergency projects on a case-by-case basis. It should be noted, bid guaranties (bid bonds) and contract bonds are required on all projects, including emergency projects.
Given the expedited nature of the emergency work, a pre-bid meeting is highly recommended to convey the scope and expected timeline for completion of work, along with communicating expected contractor preparations to meet the accelerated contracting and notice to proceed following award of the project.
103.1.2.1.2 Imminent Danger Procedures
Imminent danger contracts are contracts that need to be awarded quickly due to the safety of the traveling public.
When there is an imminent danger, the district may solicit interest from a minimum of three contractors, if available for the scope of work and expedited mobilization.
If it is extremely urgent solicitation of three contractors may be waived but it is mandatory for federal reimbursement. The contractors must be on the MoDOT approved contractor listing and insured. Depending on the job, solicitations may be conducted by phone or with on-site visits, with follow-up email correspondence to clearly outline the scope of work and timelines for work to be performed. It is important to relay consistent information on the scope and requirements of the project to all prospective contractors and internally within the respective district. Since there are no bidding documents, all work will be performed by force account.
Following communication of project scope and related expectations, and subsequent contractor response, the best responsive contractor is selected by the district. Normal job requirements such as DBE requirements, subcontract forms, schedule submittal, etc. will not be mandatory.
There is no formal contract; however, a confirmation email to the contractor and involved internal parties is required. The district shall complete the award memorandum and email to the State Design Engineer and BCS Engineer for the award to be ratified by the Commission at the next regularly held meeting. Payrolls will be required to verify force accounts.
The contractor will submit pay requests to the district, and the district will verify the amounts to submit a request for payment to FS to facilitate payment to the contractor. Once the complete scope of work is complete, the district shall notify FS for project close out. No other final paperwork or affidavits will be required from the contractor. In the rare instance where federal funding is utilized, FHWA should be contacted to verify whether any additional documentation is required.
103.1.2.1.3 Urgent Contract Procedures
Urgent projects are required to be advertised for a minimum of 3 weeks and will be awarded by the Commission. The urgent declaration allows TP to add the project to the STIP and expedite the design, which may include waiving the solicitation for consultant services. The district will need to work with Bidding and Contract Services on letting the project.
2
Copy 103.1.7
103.1.7 Advertising Projects for Bid opening and Bidding Documents
Under state law, projects must be advertised for bid opening in a newspaper published in the county in which the project will be constructed. Further, FHWA requires a project be advertised at least 3 weeks before bids are to be received. In addition to newspaper advertisements, MoDOT also issues a Notice of Bid Opening, which is available on the MoDOT web site. MoDOT, at the request of the AGC, has elected to hold a standard 5-week advertising period to allow contractors adequate time to properly prepare their bids. Supplemental notices for projects not included in the standard notice may be advertised following the initial 5-week notice, but no later than 3 weeks prior to the respective bid opening. Once a project has been advertised for bid opening, contractors and suppliers may download the Contract Plans, Job Special Provisions, Requests for Bid (aka. Bid Book), and Electronic Deliverables (if any are available) at no cost. All downloads of the electronic files are recorded and used for notification purposes in the event of an addendum. When downloading the electronic files, the contractor has the option to be identified as a plan holder. This "Plan Holders List" is presently available to the public and is located on MoDOT’s website.