103.2 Contract Bond for Sec 103.4

From Engineering_Policy_Guide
Revision as of 08:09, 28 June 2010 by Smithk (talk | contribs) (Per CM, additional guidance for Sec 103.4 in this new article)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Sec. 103.4 provides information regarding the contract bond.

The contractor may be reimbursed for contract bond if an invoice of the bond cost is provided. The mobilization line item is reduced by the bond amount when the bond is reimbursed. The reduction in mobilization is achieved by issuing a change order in the SM system. If the change order is exclusively issued to pay bond, then the contractor’s signature on the change order may be waived. Higher level change order approvals of a bond reimbursement change order are not required except for approval by FHWA on full oversight jobs.