Category:407 Tack Coat
This item is used for impervious surfaces such as portland cement concrete, asphaltic concrete or bituminous surfaces prior to resurfacing to improve the bond between the existing surface and the roadway pavement. In contracts the grade of emulsified asphalt is selected by the contractor.
Contents
407.1 Construction Inspection for Sec 407
407.1.1 Description (Sec 407.1)
The purpose of a tack coat is to improve the bond between the existing surface and the mat.
407.1.2 Material (Sec 407.2)
See Materials Inspection and EPG 1015 Bituminous Material.
407.1.3 Equipment (Sec 407.3)
See Distributor in Paving Equipment.
407.1.4 Construction Requirements (Sec 407.4)
See Spreading in Paving Operations.
Application (Sec 407.4.2) If the tack coat is too heavy or too light, an inadequate bond is created and the mat may slip during compaction, which results in shoving and checking. In addition, a slippage failure (cracking) may occur after the pavement has been subjected to traffic. Bleeding may also occur if the tack coat is too heavy.
The tack coat must be uniformly applied to the existing surface at the rate specified in the contract. Generally, the application rate between the existing pavement and the first lift should be in the range of 0.05 to 0.10 gal/yd2. . A tack coat is required between each lift of bituminous pavement. The application rate between lifts should be in the range of 0.02 to 0.05 gal/yd2.
Depending on the condition of the existing surface, the application rate may need to be adjusted from the specified rate. This is acceptable as long as approval is obtained from the RE and the rate is within the applicable range mentioned above. For example, an open textured surface, such as an SP250 mix, requires more tack than a surface that is tight or dense, such as an SP125 mix. A milled surface requires additional tack because of the increased surface area (from the grooves left by the cutting teeth on the milling machine). A dry, aged pavement also requires a heavier tack coat than a newer pavement. These conditions, and any other possibilities, must be considered when a tack coat is applied.
There is no requirement governing the overlap of a tack coat. However, the best results are generally obtained with a double or triple lap. Therefore, the height of the spray bar on the distributor should be adjusted accordingly.
The tack coat must be allowed to break (cure) prior to spreading mix. Shortly after the tack coat has been applied, its color will change from brown to black as the water in the emulsion begins to evaporate. The emulsion also becomes “tacky” to the touch. The amount of time it takes for the tack coat to break depends on the type and grade of emulsion used, the application rate, the temperature of the existing surface, and the environmental conditions. The tack coat is said to have “set” once all of the water in the emulsion has evaporated. Typically, an emulsion sets in 1 to 2 hours.
If there is reason to believe that the tack coat is being diluted with a material other than water or that the dilution rate is other than what has been reported, a sample should be taken and shipped to the Central Laboratory.
- Tack (Sec 407.4.2.1)
- It is extremely important that the tack coat remains on the existing surface in order to create an adequate bond between the existing surface and the mat. Usually, tack is only applied within the length of the lane drop. The tack coat should be allowed to set before it is subjected to construction traffic. Otherwise, the vehicle tires will pick up the tack. At the very least, the amount of construction traffic, including haul trucks, should be minimized.
- The tacked surface should be covered with mix the same day. If this is not possible because of equipment problems (plant or paver breakdowns), sand must be lightly distributed over the tacked surface before opening to traffic. This will “blot” the tack, preventing it from being picked up by the traffic, and provide friction to the surface. When paving resumes, the excess sand must be removed before the mix is spread.
407.1.5 Method of Measurement (Sec 407.5)
The quantity of emulsion to be paid for will be determined in accordance with Standard Specification Section 1015.7.2 and rounded to the nearest 10 gallons. The following equation should be used:
- Where:
- Gc = corrected gallons at 60°F
- Gb = beginning gallons
- Ge = ending gallons
- C = dilution rate
- T = application temperature
Example At the beginning of the day, the tank contains 1675 gallons of emulsion. At the end of the day, the tank contains 1450 gallons of emulsion. The application temperature of the emulsion is 125°F. Water is not being used to cut the emulsion (C = 0.00). Therefore:
- Gc=220.7 Gallons
- Gc=220 Gallons
Now suppose that the emulsion is being cut by 30% with water (C = 0.30). Therefore:
- Gc=154.5 Gallons
- Gc=150 Gallons
407.2 Materials Inspection for Sec 407
Tack Coat material shall be sampled and inspected in accordance with EPG 1015 Bituminous Material.
407.3 Maintenance Tacking or Tack Coating
Maintenance uses tacking or tack-coating by applying a light spray application of cutback or emulsified asphalt to impervious surfaces such as Portland cement concrete, asphaltic concrete, or bituminous surfaces prior to resurfacing.
407.3.1 Purpose
The purpose of the tack coat is to improve the bond between the existing surface and the roadway pavement. A tack coat shall be applied to provide a bond between old and new wearing courses. The best results occur when the tack is applied to a dry and clean surface, free of loose material.
407.3.2 Application Rates
The application rate will vary from 0.03 to 0.15 gal/yd2, depending on the condition of the old pavement surface. The pavement course surface should be evaluated to determine the amount of tack to be applied. A viscous material should be used because very little penetration of the asphaltic oil into the pavement surface is expected. The tack coat should be allowed to become tacky or sticky before the surface course is laid. Emulsions are recommended for tacking on heavily traveled routes. Too much tack can create a slippage plane between the old pavement and the new pavement overlay as the tack coat acts as a lubricant instead of an adhesive. Also too much tack could result in bleeding of the tack through to the new overlay surface, which can produce a slick pavement condition. After application of the tack, time must be allowed for the tack to break. Breaking is the phenomenon when the asphalt and water in the emulsion separate, beginning the curing process (brown to black color). Traffic should be kept off the tacked area.
407.3.3 Products
Asphalt emulsions commonly used for tack coats are diluted SS-1, SS-1h, SCC-1 and CSS-1h. Refer to Standard Specification Section 407 for additional information regarding tack coats.