Baseline Zero – The current project schedule which is represented in the reporting dashboards

Baseline One – The first historical copy of the schedule. Other historical records can be established if major schedule changes occur and will follow numbering succession (2,3,4 etc.)

Publish – When schedule progression changes are officially updated to the reporting dashboards

Predecessor – A task which must be completed before another task can begin