119.7 Project Schedule Communication and Collaboration

From Engineering Policy Guide
Revision as of 15:57, 18 March 2025 by Hoskir (talk | contribs) (new article for 119 per RR4027)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Project core Team Members are encouraged to review all schedules on a regular basis for critical path task durations via the project delivery Reporting Dashboards.

Core Team Members should regularly communicate with project managers about the duration of critical path tasks such as bridge plans, environmental review(s) and permitting, right-of-way acquisition, railroad coordination, utility coordination, etc. to ensure adequate durations are accounted for in the project schedule and adjustments made as needs are identified throughout the project.