Difference between revisions of "1035.4 Laboratory Testing Guidelines for Sec 1035"

From Engineering_Policy_Guide
Jump to navigation Jump to search
m (info from lab manual)
 
m (→‎1035.2 Sample Record: Per CM, updated link)
(4 intermediate revisions by the same user not shown)
Line 1: Line 1:
 
 
This artilce establishes procedures for Laboratory testing and reporting samples of reinforced concrete arch culvert, storm drain and sewer pipe.
 
This artilce establishes procedures for Laboratory testing and reporting samples of reinforced concrete arch culvert, storm drain and sewer pipe.
  
Line 16: Line 15:
 
===1035.2 Sample Record===
 
===1035.2 Sample Record===
  
All sample records shall be completed in SiteManager, as described in [[Automation Sec 3510]]. Test results shall be reported on the appropriate templates under the Tests tab. Compression test results for concrete cylinders shall include the notation in remarks, "Specimens submitted for compressive strength at the age indicated." Compression test results for concrete cores shall include the notation in remarks, "Sample submitted for the determinations indicated." Absorption test results for concrete cores or pieces from the wall of the section shall indicate acceptance, qualified acceptance or rejection. Appropriate remarks, as described in [[106.9 Reporting Test Results|106.9 Reporting Test Results]], are to be included in the remarks to clarify conditions of acceptance or rejection.
+
All sample records shall be completed in SiteManager, as described in [http://contribute.modot.mo.gov/business/materials/pdf/vol_3/MMV3CONT.pdf Automation Section]. Test results shall be reported on the appropriate templates under the Tests tab. Compression test results for concrete cylinders shall include the notation in remarks, "Specimens submitted for compressive strength at the age indicated." Compression test results for concrete cores shall include the notation in remarks, "Sample submitted for the determinations indicated." Absorption test results for concrete cores or pieces from the wall of the section shall indicate acceptance, qualified acceptance or rejection. Appropriate remarks, as described in [[106.20 Reporting|EPG 106.20 Reporting]], are to be included in the remarks to clarify conditions of acceptance or rejection.
  
 
[[Category:1035 Reinforced Concrete Arch Culvert]]
 
[[Category:1035 Reinforced Concrete Arch Culvert]]

Revision as of 11:18, 10 October 2013

This artilce establishes procedures for Laboratory testing and reporting samples of reinforced concrete arch culvert, storm drain and sewer pipe.

1035.4.1 Procedure

Tests consist of compression and absorption.

Compression Test. Samples may consist of two standard concrete cylinders'made in accordance with AASHTO T23 or one core drilled from the wall of the pipe in accordance with AASHTO T280.

a) Concrete cylinders shall be tested in accordance with AASHTO T22. Test results and calculations shall be recorded through SiteManager.
b) Drilled cores shall be tested in accordance with AASHTO T280. Test results and calculations shall be recorded through SiteManager.

Absorption Test. Samples shall be tested in accordance with AASHTO T280. Test results and calculations shall be recorded through SiteManager.

1035.2 Sample Record

All sample records shall be completed in SiteManager, as described in Automation Section. Test results shall be reported on the appropriate templates under the Tests tab. Compression test results for concrete cylinders shall include the notation in remarks, "Specimens submitted for compressive strength at the age indicated." Compression test results for concrete cores shall include the notation in remarks, "Sample submitted for the determinations indicated." Absorption test results for concrete cores or pieces from the wall of the section shall indicate acceptance, qualified acceptance or rejection. Appropriate remarks, as described in EPG 106.20 Reporting, are to be included in the remarks to clarify conditions of acceptance or rejection.