Difference between revisions of "121.7 Program Estimates"

From Engineering_Policy_Guide
Jump to navigation Jump to search
(Per Bidding and TP, estimate guidance was clarified to reflect current practice in estimating. This new article is clarified info removed from EPG 104.7)
 
m
Line 9: Line 9:
 
|[[media:104.7 EngFac SFY 16 to 18.pdf|Engineering Factors Report]]
 
|[[media:104.7 EngFac SFY 16 to 18.pdf|Engineering Factors Report]]
 
|-
 
|-
|[[media:Fig 237.7.docx|Costs for Non-Contractual Items]]  
+
|[[media:Fig 237.6.docx|Costs for Non-Contractual Items]]  
 
|}
 
|}
  

Revision as of 14:56, 30 August 2019

Related Information
MoDOT's STIP website
Figures
Engineering Factors Report
Costs for Non-Contractual Items

The Program Estimate shall not use the cost per mile pricing. The Program Estimate shall be developed at the preliminary plan stage after 30% of the plans are completed.

The best type of Program Estimate that can be produced at this stage of project development is a historic-based estimate. Based on the quantities calculated from the preliminary plans and historical data from previous bid openings, a fairly accurate Program Estimate can be produced.

The preliminary plans should provide enough detail to allow a fairly accurate Program Estimate of the major project quantities. Generally, 80% of the cost of a project will be included in the 20% of the pay items that comprise the major items of the project. All other anticipated construction costs should also be included in the Program Estimate.

As details of the project become finalized, the Program Estimate is refined and updated in the STIP, as part of the annual STIP update, until the fiscal year it is scheduled to be awarded.

In addition, estimates of right of way costs based on generic land values will not be considered to provide the level of confidence that MoDOT requires to make STIP commitments.

Tentative right of way lines included on preliminary plans will provide a reasonable estimate of the easements and right of way required for each project. These can then be combined with an estimated amount for each property to arrive at a fairly accurate right of way estimate.

104.7 Estimates.jpg
Historic Engineering Factors Reports
CY 2006 - 2008
CY 2007 - 2009
FY 2008 - 2010
FY 2010 - 2012
FY 2011 - 2013
FY 2012 - 2014
FY 2013 - 2015
FY 2014 - 2016
FY 2015 - 2017
FY 2016 - 2018

All other anticipated right of way and construction costs should also be included in the Program Estimate. These may include Heritage and Homestead Valuation adjustment costs for large utility relocations, right of way easements necesssary for cornstruction activities,non-contractual, incentive/disincentive clauses, contract acceleration clauses, major environmental mitigation costs, etc.

The Engineering Factors Report is a useful document to help calculate a project's future engineering costs such as preliminary and construction engineering and right of way incidentals. The report is updated annually.