These Maintenance planning guidelines apply to [http://epg.modot.mo.gov/files/7/72/232_Major_Highways_Map.pdf major] and minor roads.
+
See [[:Category:170 Maintenance Activity Planning Guidelines#R316 Drainage|Maintenance Planning Guide for Installing Pipe Liners]].
  
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="right"
+
Index of all [[:Category:170 Maintenance Activity Planning Guidelines#Index of Printable Planning Guides|Maintenance Planning Guidelines]].
|
 
|'''Code:''' R316
 
|}
 
 
 
'''Purpose'''
 
To fill voids and realign settled sections of paved ditches.
 
 
 
'''Scheduling'''
 
As needed when the temperature is above freezing.
 
 
 
'''Recommended Equipment'''
 
:* Dump truck
 
:* Water truck
 
:* Mudjack
 
:* Air compressor
 
:* Pavement Drill
 
:* Traffic control equipment, as needed.
 
 
 
'''Recommended Material'''
 
:* Water
 
:* Portland cement
 
:* Agricultural lime
 
 
 
'''Recommended Procedure'''
 
 
 
1. Call Dig Rite and check for MoDOT utilities.
 
 
 
2. Place traffic control devices as needed.
 
 
 
3. Wet paved ditch.
 
 
 
4. Pump and plug predrilled holes.  Begin pumping at low end of section.
 
 
 
5. Clean work area and equipment.
 
 
 
6. Remove traffic control devices.
 
 
 
'''Safety'''
 
Wear all appropriate Personal Protection Equip (PPE). Refer to [http://lnapp1/RI/RIManual.NSF/SHToC?OpenView Safety Policies, Rules & Regulations-Employee Handbook] .
 
 
 
'''Other Considerations'''
 
Production can be increased by drilling in advance.
 
 
 
'''Reference'''
 
[http://www.modot.mo.gov/business/standards_and_specs/Sec0609.pdf Sec 609]
 
  
 