Difference between revisions of "771.19 Chip Seal to Entire Deck"

From Engineering_Policy_Guide
Jump to navigation Jump to search
(New page: {|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="right" |- |'''Code:''' R322 |} Chip sea...)
 
m
 
(7 intermediate revisions by 2 users not shown)
Line 1: Line 1:
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="right"  
+
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#ffddcc" width="210px" align="right"  
|-
+
|-
|'''Code:''' R322
+
|'''Bridge Deck, Sealer'''
 +
|-
 +
|[https://spexternal.modot.mo.gov/sites/cm/CORDT/or07009.pdf Report 2007]
 +
|-
 +
|'''See also:''' [https://www.modot.org/research-publications Research Publications]
 
|}
 
|}
  
Chip seals help to seal bridge decks with excessive cracking to prevent intrusion of water and chlorides into the bridge deck. The work should be performed in July and August.
+
See [[:Category:170 Maintenance Activity Planning Guidelines#R322 Bridge Preventative Maintenance|R322 Bridge Seal Coats Maintenance Planning Guidelines]].
  
==Materials==
+
Index of all [[:Category:170 Maintenance Activity Planning Guidelines#Index of Printable Planning Guides|Maintenance Planning Guidelines]].
*Liquid asphalt – EA 90P or CRS-2P
 
*Cover aggregate – Iron Mountain trap rock, Joplin chat, or other approved materials
 
  
==Procedures==
+
[[Category:771 Bridge Preventive Maintenance Guidelines|771.19]]
1. Deck should be thoroughly sounded out and deck repairs made.
 
 
 
2. Deck should be cleaned, flushed, and dry prior to sealing.
 
 
 
3. Cover expansion devices or other features that are not to be sealed over.
 
 
 
4. Chip seals are to extend a minimum of 30 ft. beyond each bridge end.
 
 
 
5. Apply liquid asphalt at a rate of 0.3 to 0.5 gal./yd<sup>2</sup> depending on size of cover aggregate and slope of bridge deck.
 
 
 
6. Spread 25 to 30 lbs. of cover aggregate per yd<sup>2</sup> immediately following application of liquid asphalt and roll as soon as possible. Adequate cover aggregate must be applied to prevent tracking. Cover aggregate shall not be placed within 2 ft. of curb.
 
 
 
7. Lightly broom excess chips after seal is properly cured (when chips are securely held), then open lane to traffic.
 
 
 
8. Repeat for adjacent lanes.
 
 
 
9. Return two to three days later to again thoroughly sweep bridge deck to remove loose aggregate. Remove aggregate on lower chords and substructure caps.
 
 
 
==Safety==
 
Watch for flying rock chips and traffic in adjacent lanes. Consider the need to install Loose Gravel signs until the loose aggregate is removed from the bridge deck.
 
 
 