Difference between revisions of "Category:138 Project Development Chronology"

From Engineering_Policy_Guide
Jump to navigation Jump to search
m (article renumbered, from 1500 to 138)
 
m (article construction)
Line 45: Line 45:
 
[[237.2 Title Sheet# 237.2.1 Design Designation |'''Traffic.''']] Whether the road to be improved is a major or minor roadway and its level of anticipated traffic are key elements in determining basic design controls for the improvement.  Improvement projects on interstate roadways are designed for traffic projected 20 years beyond the date design of the improvement is completed.  All other roadway improvements are designed for traffic projected 20 years beyond the date of construction begins.
 
[[237.2 Title Sheet# 237.2.1 Design Designation |'''Traffic.''']] Whether the road to be improved is a major or minor roadway and its level of anticipated traffic are key elements in determining basic design controls for the improvement.  Improvement projects on interstate roadways are designed for traffic projected 20 years beyond the date design of the improvement is completed.  All other roadway improvements are designed for traffic projected 20 years beyond the date of construction begins.
  
'''Anticipated Posted Speed.'''  It is desirable to select design criteria for roadway improvement projects that reflect the anticipated posted speed of the completed improvement.  Selection of these criteria must also reflect the function of the roadway, its impact on the surrounding community and the wise use of resources.
+
'''Anticipated Posted Speed.'''  It is desirable to select design criteria for roadway improvement projects that reflect the anticipated posted speed (previously called "design speed") of the completed improvement.  Selection of these criteria must also reflect the function of the roadway, its impact on the surrounding community and the wise use of resources.
  
 
'''Traffic Control Devices.'''  [[:category:620 Pavement Marking|Signing and marking]] for both [[:category:900 TRAFFIC CONTROL|permanent]] and [[:Category:616 Temporary Traffic Control|temporary traffic control]] are directly related to highway design.  Effective signing and marking supplement a well-designed geometric layout by informing, warning and controlling traffic.
 
'''Traffic Control Devices.'''  [[:category:620 Pavement Marking|Signing and marking]] for both [[:category:900 TRAFFIC CONTROL|permanent]] and [[:Category:616 Temporary Traffic Control|temporary traffic control]] are directly related to highway design.  Effective signing and marking supplement a well-designed geometric layout by informing, warning and controlling traffic.

Revision as of 09:48, 29 February 2008

129 Idea to Reality Graphic.jpg



This article is a brief outline of the process involved in the path of an improvement project from the initial identification of a “need” to a completed project serving the public.

138.1 Idea to Meet Transportation Need

MoDOT considers an area’s safety concerns, growth, traffic patterns and transportation needs. When a need is identified, MoDOT meets with local government, community leaders and transportation users to discuss the project.

138.2 Public Consulted

At this stage, MoDOT announces to the public what improvement is proposed to address the need. Response from the interested groups and individuals is collected and considered as development of the improvement continues.

138.3 Planning

MoDOT proposes and evaluates several possible improvement locations. The Missouri Highway and Transportation Commission reviews public comments and other information concerning the proposed improvement before further development of the improvement.

138.4 Impact Assessment

Teams of MoDOT specialists evaluate the improvement’s impact on wetlands, wildlife, homeowners, businesses, etc. The proposed improvement is also sent to the Federal Highway Administration (FHWA) for approval. Other Federal agencies, such as the Environmental Protection Agency, Department of Interior, Corps of Engineers, Federal Emergency Management Agency and State agencies such as the Missouri Department of Natural Resources and the State Emergency Management Agency may need to grant approval for the improvement to proceed.


1500.5 public consulted.jpg


138.5 Public Consulted Again Before Project Approval

MoDOT holds additional public hearings to gather public comments during development of the improvement. The Commission gives final approval for the project’s location and design details.

138.6 Design

138.6.1 Value Engineering. Value Engineering (VE) helps assure the full value of every transportation tax dollar is realized. In highway construction it encourages designers to provide cost efficient designs and contractors to employ innovative construction methods to reduce costs.

138.6.2 Preliminary Plans. A preliminary plan shows preliminary geometric details and includes design criteria, proposed alignment, profile, tentative grade, tentative right of way, schematic intersection or interchange layouts, bypasses and pertinent topographic features. The preliminary plan develops and conveys basic design criteria, basic geometric details and recommendations upon which the detail plans are to be developed.

138.6.3 Surveys. A survey physically establishes the location in the field in accord with the approved location. The survey includes the location of all man-made features in relation to the established centerline and also includes elevations on National Geodetic Survey (NGS) or United States Geodetic Survey (USGS) datum necessary to locate grades, culverts, bridges, and to compute excavation quantities.

138.6.4 Right of Way Plans. Detail plans are prepared to provide the information and details necessary to construct transportation improvements to criteria required to address the need of the improvement. The plans show all existing topographic features and the disposition of existing improvements affected by the proposed construction and indicates the right of way necessary to allow room for the improvement’s construction and maintenance, and in sufficient detail to write deeds and acquire the right of way to the dimensions shown on the plans.

138.6.5 Basic Design Criteria

Traffic. Whether the road to be improved is a major or minor roadway and its level of anticipated traffic are key elements in determining basic design controls for the improvement. Improvement projects on interstate roadways are designed for traffic projected 20 years beyond the date design of the improvement is completed. All other roadway improvements are designed for traffic projected 20 years beyond the date of construction begins.

Anticipated Posted Speed. It is desirable to select design criteria for roadway improvement projects that reflect the anticipated posted speed (previously called "design speed") of the completed improvement. Selection of these criteria must also reflect the function of the roadway, its impact on the surrounding community and the wise use of resources.

Traffic Control Devices. Signing and marking for both permanent and temporary traffic control are directly related to highway design. Effective signing and marking supplement a well-designed geometric layout by informing, warning and controlling traffic.

Hydraulics and Drainage. Drainage structures must be properly selected and sized to allow the flow of water without negatively impacting adjacent upstream and downstream property owners. Depending on the drainage area, differing methods and criteria are available to properly design drainage structure.

Groundbreaking

138.7 Construction

The site of the improvement is cleared of rock and debris and heavy equipment begins grading. Crews lay pipes under the roadbed to provide drainage and build bridges over other roadways ditches and rivers.

138.8 Road Opening

The roadbed is paved with asphalt or concrete. Signs are installed. The road is now complete and ready for travel.

138.9 Road Maintenance

MoDOT maintains the facility to meet the needs of travelers. Should the road eventually be found to not meet travelers’ needs, a new “need” will be identified and the process to improve the facility begins again.