==773.1 Maintenance Planning Guideline for Installing Pipe Liners==
 
==773.1 Maintenance Planning Guideline for Installing Pipe Liners==
See [[:Category:735 Culvert Pipe Liner|Culvert Pipe Liner]]
+
'''Printable''' [[media:R319 - Install Pipe Liners.pdf|'''Maintenance Planning Guide for Installing Pipe Liners''']].
==773.2 Maintenance Planning Guideline for Cleaning and Repair of Pipes==
 
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="right"
 
|- 
 
|'''Code:''' R319
 
|}
 
'''Definition'''
 
  
The time and expenses incurred from removing and replacing pipe culverts. Includes time and expenses incurred for installing a new lining in an existing culvert.
+
Index of all [[:Category:170 Maintenance Activity Planning Guidelines#Index of Printable Planning Guides|Maintenance Planning Guidelines]].
  
'''Purpose'''
+
==773.2 Maintenance Planning Guideline for Cleaning and Repair of Pipes==
 
+
'''Printable''' [[media:R319 - Clean & Repair Pipe & Box Culverts - Pipe Culverts.pdf|'''Maintenance Planning Guide for Cleaning and Repair of Pipes''']].
To clean, align, and repair pipe culverts and related structures.
 
 
 
'''Scheduling'''
 
 
 
As needed, year around.
 
 
 
'''Recommended Equipment'''
 
 
 
*Trucks
 
*Water Tank w/Trash Pump
 
*Concrete Mixer
 
*Jack
 
*Loader
 
*Skid Steer Loader
 
*Chainsaws
 
*Tube Flusher
 
Traffic Control Equipment (see [[616.23 Traffic Control for Field Operations|Traffic Control for Field Operations]])
 
 
 
'''Recommended Material'''
 
 
 
*Concrete
 
*Plastic Joint Compound
 
*Form Material
 
*Water
 
*Curing Compound
 
 
 
'''Recommended Procedure'''
 
 
 
1. Call Dig Rite and MoDOT to check for utilities.
 
 
 
2. Place traffic control devices as needed.
 
 
 
3. Fill open joints with joint compound.
 
 
 
4. If headwall, flared end section, or pipe end section is settled, align section with jack or loader and compact material under section for support.
 
 
 
5. If ends of corrugated metal pipe are bent and restricted, open with jack.
 
 
 
6. Clean excess compound and debris from work area.
 
 
 
7. Remove traffic control devices.
 
 
 
'''Safety'''
 
 
 
Call before you dig to locate utilities '''(1-800-DIG-RITE)'''. Watch out for "pinch points." Wear all appropriate PPE. Reference the [http://lnapp1/RI/RIManual.NSF/SHToC?OpenView Safety Policies, Rules & Regulations-Employee Handbook.]
 
  
'''Other Considerations'''
+
Index of all [[:Category:170 Maintenance Activity Planning Guidelines#Index of Printable Planning Guides|Maintenance Planning Guidelines]].
 
 
Check if Corps of Engineers permit is needed.
 
  
 
==773.3 Maintenance Planning Guideline for Cleaning and Repair of Box Culverts==
 
==773.3 Maintenance Planning Guideline for Cleaning and Repair of Box Culverts==
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="right"
+
'''Printable''' [[media:R319 - Clean & Repair Pipe & Box Culverts - Box Culverts.pdf|'''Maintenance Planning Guide for Cleaning and Repair of Box Culverts''']].
|- 
 
|'''Code:''' R319
 
|}
 
'''Definition'''
 
 
 
The time and expenses incurred from removing and replacing pipe culverts. Includes time and expenses incurred for installing a new lining in an existing culvert.
 
 
 
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#ffddcc" width="210px" align="right"
 
|-
 
|'''Concrete Box Culvert, GFRP'''
 
|-
 
|[http://library.modot.mo.gov/RDT/reports/RI99028/RDT01016a.pdf Report 2001]
 
|-
 
|'''See also:''' [http://www.modot.gov/services/OR/byDate.htm Innovation Library]
 
|}
 
 
 
'''Purpose'''
 
 
 
To clean, repair, and fill voids of box culverts and restore roadway drainage.
 
 
 
'''Scheduling'''
 
 
 
As needed, year around.
 
 
 
'''Recommended Equipment'''
 
 
 
*Trucks
 
*Loader, Backhoe, or Excavator
 
*Concrete Mixer
 
*Compressor/Breakers
 
*Water Tank w/Trash Pump
 
*Traffic Control Equipment (see [[616.23 Traffic Control for Field Operations|Traffic Control for Field Operations]])
 
 
 
'''Recommended Material'''
 
 
 
*Concrete
 
*Water
 
*Quarry Run Rock
 
*Form Material
 
*Cement
 
*Agricultural Lime
 
 
 
'''Recommended Procedure'''
 
 
 
1. Call Dig Rite and MoDOT to check for utilities.
 
 
 
2. Place traffic control devices as needed.
 
 
 
<u>Clean Out</u>
 
 
 
1. Remove drift and debris as needed.
 
 
 
<u>Repair</u>
 
 
 
1. Remove bad concrete, form, and pour concrete.
 
 
 
<u>Fill Voids</u>
 
 
 
1. Fill large voids and eroded outlet areas with quarry run rock and if needed grout with concrete.
 
 
 
2. Internal voids along the barrel sides and bottom should be mudjacked.
 
 
 
3. Remove traffic control devices.
 
 
 
'''Safety'''
 
 
 
Call before you dig to locate utilities '''(1-800-DIG-RITE)'''. Watch out for "pinch points." Wear all appropriate PPE. Reference the [http://lnapp1/RI/RIManual.NSF/SHToC?OpenView Safety Policies, Rules & Regulations-Employee Handbook.]
 
  
'''Other Considerations'''
+
Index of all [[:Category:170 Maintenance Activity Planning Guidelines#Index of Printable Planning Guides|Maintenance Planning Guidelines]].
 
 
Check if Corps of Engineers permit is needed.
 
  
 
==773.4 Maintenance Planning Guideline for Replacing Pipes and Box Culverts==
 
==773.4 Maintenance Planning Guideline for Replacing Pipes and Box Culverts==
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="right"
+
'''Printable''' [[media:R319 - Replace Pipe & Box Culverts.pdf|'''Maintenance Planning Guide for Replacing Pipe & Box Culverts''']].
|- 
 
|'''Code:''' R319
 
|}
 
'''Definition'''
 
 
 
The time and expenses incurred from removing and replacing pipe culverts. Includes time and expenses incurred for installing a new lining in an existing culvert.
 
 
 
'''Purpose'''
 
  
To replace deteriorated pipe and box culverts, which have caused the roadway or entrance to settle.
+
Index of all [[:Category:170 Maintenance Activity Planning Guidelines#Index of Printable Planning Guides|Maintenance Planning Guidelines]].
 
 
'''Scheduling'''
 
 
 
As needed, year around.
 
 
 
'''Recommended Equipment'''
 
 
 
*Trucks
 
*Backhoe, Excavator, Loader, or Motorgrader
 
*Mechanical Compactor
 
*Dragline
 
*Crane
 
*Breaker
 
*Trenching Protective System/ Sheeting
 
*Traffic Control Equipment (see [[616.23 Traffic Control for Field Operations|Traffic Control for Field Operations]])
 
 
 
'''Recommended Material'''
 
 
 
*Pipe & Accessories
 
*Joint Compound
 
*Roadway Surface Material
 
*Precast Box Culvert
 
*Backfill Material
 
 
 
'''Recommended Procedure'''
 
 
 
1. Call Dig Rite and MoDOT to check for utilities.
 
 
 
2. Develop trenching safety plan with competent person and supervisor.
 
 
 
3. Place traffic control devices as needed.
 
 
 
4. Remove existing pipe or box.
 
 
 
5. Install protective system in trench, if necessary.
 
 
 
6. Prepare subgrade.
 
 
 
7. Place new pipe or box and seal joints.
 
 
 
8. Remove protective system.
 
 
 
9. Compact material in lifts around and over pipe or box.
 
 
 
10. Place and compact surfacing material.
 
 
 
11. Clean work area.
 
 
 
12. Remove traffic control devices.
 
 
 
'''Safety'''
 
 
 
Call before you dig to locate utilities (1-800-DIG-RITE). Hard hats are required. Watch for sharp edges and "pinch points." Wear all appropriate PPE. Refer to Risk Management On Line Manual Section 2.4 for [http://lnapp1/RI/RIManual.NSF/2cfd1a8d7c4213d7862562d900795ea7/c997dd19e850254f86256df60052ada1?OpenDocument Trenching and Shoring Procedures.] Also comply with the [http://lnapp1/RI/RIManual.NSF/SHToC?OpenView Safety Policies, Rules & Regulations-Employee Handbook.]
 
 
 
'''Other Considerations'''
 
 
 
If entire roadway is to be closed, local news media, schools, emergency services, and law enforcement agencies should be informed in advance.
 
 
 
'''References'''
 
 
 
Standard Specification [http://modot.mo.gov/business/standards_and_specs/Sec0725.pdf Sec 725], [http://modot.mo.gov/business/standards_and_specs/Sec0726.pdf Sec 726] and [http://modot.mo.gov/business/standards_and_specs/Sec0733.pdf Sec 733].
 
 
 
{|
 
|[[Image:773 Replacing Pipe and Box Culverts1.jpg|400px]] || [[Image:773 Replacing Pipe and Box Culverts2.jpg|400px]]
 
|-
 
|text align="center"|'''Sawcut Pavement for Culvert Replacement''' || text align="center"|'''Open Trench for Culvert Replacement'''
 
|-
 
|[[Image:773 Replacing Pipe and Box Culverts3.jpg|400px]] || [[Image:773 Replacing Pipe and Box Culverts4.jpg|400px]]
 
|-
 
|text align="center"|'''Setting Grade for Culvert Bedding''' || text align="center"|'''Fine Grading Culvert Bed'''
 
|-
 
|[[Image:773 Replacing Pipe and Box Culverts5.jpg|400px]] || [[Image:773 Replacing Pipe and Box Culverts6.jpg|400px]]
 
|-
 
|text align="center"|'''Laying Culvert Pipe''' || text align="center"|'''Installing Pipe Connecting Band'''
 
|-
 
|[[Image:773 Replacing Pipe and Box Culverts7.jpg|400px]] || [[Image:773 Replacing Pipe and Box Culverts8.jpg|400px]]
 
|-
 
|text align="center"|'''Backfilling around Culvert Pipe''' || text align="center"|'''Spreading and Compacting Pipe Fill'''
 
|-
 
|[[Image:773 Replacing Pipe and Box Culverts9.jpg|400px]] || [[Image:773 Replacing Pipe and Box Culverts10.jpg|400px]]
 
|-
 
|text align="center"|'''Laying Hot Mix Asphalt''' || text align="center"|'''Finished Product'''
 
|}
 
  
 
==773.5 Maintenance Planning Guideline for Cleaning and Reshaping Earth Ditches==
 
==773.5 Maintenance Planning Guideline for Cleaning and Reshaping Earth Ditches==
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="right"
+
'''Printable''' [[media:R316 - Clean & Reshape Ditches - Earth.pdf|'''Maintenance Planning Guide for Cleaning and Reshaping Earth Ditches''']].
|- 
 
|'''Code:''' R316
 
|}
 
'''Definition'''
 
 
 
The time and expenses incurred for the installation, repair and maintenance of roadway drainage ditches, structures, and all slide repairs. This includes installing and maintaining pavement drainage systems.
 
 
 
'''Purpose'''
 
 
 
To keep the roadbed dry and maintain stability and proper drainage while keeping culvert pipes open.
 
 
 
'''Scheduling'''
 
 
 
As needed, year around.
 
 
 
'''Recommended Equipment'''
 
 
 
*Motor Grader
 
*Loader
 
*Backhoe, Excavator, or Dragline
 
*Dump Trucks
 
*Broadcast Spreader
 
*Eye Level &/or Transit
 
*Traffic Control Equipment (see [[616.23 Traffic Control for Field Operations|Traffic Control for Field Operations]])
 
 
 
'''Recommended Material'''
 
 
 
*Seed
 
*Mulch
 
*Silt Fence, Straw Bales, Rock (for Berms), Triangular Silt Dyke, Coir Fiber Logs
 
*Sod
 
*Erosion Control Blankets
 
 
 
'''Recommended Procedure'''
 
 
 
1. Call Dig Rite and check for MoDOT utilities.
 
 
 
2. Place traffic control devices as needed.
 
 
 
3. Shape ditch and remove material as needed.
 
 
 
4. Clean loose material from roadway.
 
 
 
5. Set up erosion control as necessary.
 
 
 
6. Seed and mulch as necessary.
 
 
 
7. Remove traffic control devices.
 
 
 
'''Safety'''
 
 
 
Call before you dig to locate utilities ('''1- 800-DIG-RITE'''). Watch for traffic when operating equipment on the roadway. Wear all appropriate PPE. Also comply with the [http://lnapp1/RI/RIManual.NSF/SHToC?OpenView Safety Policies, Rules & Regulations-Employee Handbook.]
 
 
 
'''Other Considerations'''
 
 
 
When excavating in lawn areas, adjacent property owners should be contacted prior to beginning work, if possible, to explain intent of operation.
 
 
 
'''References'''
 
 
 
Standard Specification [http://modot.mo.gov/business/standards_and_specs/Sec0802.pdf Sec 802], [http://modot.mo.gov/business/standards_and_specs/Sec0803.pdf Sec 803], [http://modot.mo.gov/business/standards_and_specs/Sec0805.pdf Sec 805], [http://modot.mo.gov/business/standards_and_specs/Sec0806.pdf Sec 806] and Standard Plan [http://modot.mo.gov/business/standards_and_specs/documents/80610.pdf 806.10.]
 
  
{|
+
Index of all [[:Category:170 Maintenance Activity Planning Guidelines#Index of Printable Planning Guides|Maintenance Planning Guidelines]].
|[[Image:773 Clean and Reshape Earth Ditches1.jpg|400px]] || [[Image:773 Clean and Reshape Earth Ditches2.jpg|400px]]
 
|-
 
|text align="center"|'''Downstream Culvert Ditch (Silted In)''' || text align="center"|'''Digging Out Culvert Ditch'''
 
|-
 
||[[Image:773 Clean and Reshape Earth Ditches3.jpg|400px]] || [[Image:773 Clean and Reshape Earth Ditches4.jpg|400px]]
 
|-
 
|text align="center"|'''Digging Out Culvert Ditch''' || text align="center"|'''Digging Out Culvert Ditch'''
 
|-
 
||[[Image:773 Clean and Reshape Earth Ditches5.jpg|400px]] || [[Image:773 Clean and Reshape Earth Ditches6.jpg|400px]]
 
|-
 
|text align="center"|'''Graded Culvert Ditch''' || text align="center"|'''Mulched and Seeded Ditch - Finished Product'''
 
|}
 

Revision as of 08:46, 31 July 2009