==773.1 Maintenance Planning Guideline for Installing Pipe Liners==
 
==773.1 Maintenance Planning Guideline for Installing Pipe Liners==
See [[:Category:735 Culvert Pipe Liner|Culvert Pipe Liner]]
+
See [[:Category:170 Maintenance Activity Planning Guidelines#R319 Pipe Culvert Repairs (LF)|Maintenance Planning Guide for Installing Pipe Liners]].
==773.2 Maintenance Planning Guideline for Cleaning and Repair of Pipes==
 
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="right"
 
|- 
 
|'''Code:''' R319
 
|}
 
'''Definition'''
 
  
The time and expenses incurred from removing and replacing pipe culverts. Includes time and expenses incurred for installing a new lining in an existing culvert.
+
Index of all [[:Category:170 Maintenance Activity Planning Guidelines#Index of Printable Planning Guides|Maintenance Planning Guidelines]].
  
'''Purpose'''
+
==773.2 Maintenance Planning Guideline for Cleaning and Repair of Pipes==
 
+
See [[:Category:170 Maintenance Activity Planning Guidelines#R319 Pipe Culvert Repairs (LF)|Maintenance Planning Guide for Cleaning and Repair of Pipes]].
To clean, align, and repair pipe culverts and related structures.
 
 
 
'''Scheduling'''
 
 
 
As needed, year around.
 
 
 
'''Recommended Equipment'''
 
 
 
*Trucks
 
*Water Tank w/Trash Pump
 
*Concrete Mixer
 
*Jack
 
*Loader
 
*Skid Steer Loader
 
*Chainsaws
 
*Tube Flusher
 
Traffic Control Equipment (see [[616.23 Traffic Control for Field Operations|Traffic Control for Field Operations]])
 
 
 
'''Recommended Material'''
 
 
 
*Concrete
 
*Plastic Joint Compound
 
*Form Material
 
*Water
 
*Curing Compound
 
  
'''Recommended Procedure'''
+
Index of all [[:Category:170 Maintenance Activity Planning Guidelines#Index of Printable Planning Guides|Maintenance Planning Guidelines]].
 
 
1. Call Dig Rite and MoDOT to check for utilities.
 
 
 
2. Place traffic control devices as needed.
 
 
 
3. Fill open joints with joint compound.
 
 
 
4. If headwall, flared end section, or pipe end section is settled, align section with jack or loader and compact material under section for support.
 
 
 
5. If ends of corrugated metal pipe are bent and restricted, open with jack.
 
 
 
6. Clean excess compound and debris from work area.
 
 
 
7. Remove traffic control devices.
 
 
 
'''Safety'''
 
 
 
Call before you dig to locate utilities '''(1-800-DIG-RITE)'''. Watch out for "pinch points." Wear all appropriate PPE. Reference the [http://lnapp1/RI/RIManual.NSF/SHToC?OpenView Safety Policies, Rules & Regulations-Employee Handbook.]
 
 
 
'''Other Considerations'''
 
 
 
Check if Corps of Engineers permit is needed.
 
  
 
==773.3 Maintenance Planning Guideline for Cleaning and Repair of Box Culverts==
 
==773.3 Maintenance Planning Guideline for Cleaning and Repair of Box Culverts==
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="right"
+
See [[:Category:170 Maintenance Activity Planning Guidelines#R319 Pipe Culvert Repairs (LF)|Maintenance Planning Guide for Cleaning and Repair of Box Culverts]].
|- 
 
|'''Code:''' R319
 
|}
 
'''Definition'''
 
 
 
The time and expenses incurred from removing and replacing pipe culverts. Includes time and expenses incurred for installing a new lining in an existing culvert.
 
 
 
'''Purpose'''
 
 
 
To clean, repair, and fill voids of box culverts and restore roadway drainage.
 
 
 
'''Scheduling'''
 
 
 
As needed, year around.
 
 
 
'''Recommended Equipment'''
 
 
 
*Trucks
 
*Loader, Backhoe, or Excavator
 
*Concrete Mixer
 
*Compressor/Breakers
 
*Water Tank w/Trash Pump
 
*Traffic Control Equipment (see [[616.23 Traffic Control for Field Operations|Traffic Control for Field Operations]])
 
 
 
'''Recommended Material'''
 
 
 
*Concrete
 
*Water
 
*Quarry Run Rock
 
*Form Material
 
*Cement
 
*Agricultural Lime
 
 
 
'''Recommended Procedure'''
 
 
 
1. Call Dig Rite and MoDOT to check for utilities.
 
 
 
2. Place traffic control devices as needed.
 
 
 
<u>Clean Out</u>
 
 
 
1. Remove drift and debris as needed.
 
 
 
<u>Repair</u>
 
 
 
1. Remove bad concrete, form, and pour concrete.
 
 
 
<u>Fill Voids</u>
 
 
 
1. Fill large voids and eroded outlet areas with quarry run rock and if needed grout with concrete.
 
 
 
2. Internal voids along the barrel sides and bottom should be mudjacked.
 
 
 
3. Remove traffic control devices.
 
 
 
'''Safety'''
 
 
 
Call before you dig to locate utilities '''(1-800-DIG-RITE)'''. Watch out for "pinch points." Wear all appropriate PPE. Reference the [http://lnapp1/RI/RIManual.NSF/SHToC?OpenView Safety Policies, Rules & Regulations-Employee Handbook.]
 
 
 
'''Other Considerations'''
 
  
Check if Corps of Engineers permit is needed.
+
Index of all [[:Category:170 Maintenance Activity Planning Guidelines#Index of Printable Planning Guides|Maintenance Planning Guidelines]].
  
 
==773.4 Maintenance Planning Guideline for Replacing Pipes and Box Culverts==
 
==773.4 Maintenance Planning Guideline for Replacing Pipes and Box Culverts==
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="right"
+
See [[:Category:170 Maintenance Activity Planning Guidelines#R319 Pipe Culvert Repairs (LF)|Maintenance Planning Guide for Replacing Pipe & Box Culverts]].
|- 
 
|'''Code:''' R319
 
|}
 
'''Definition'''
 
 
 
The time and expenses incurred from removing and replacing pipe culverts. Includes time and expenses incurred for installing a new lining in an existing culvert.
 
 
 
'''Purpose'''
 
 
 
To replace deteriorated pipe and box culverts, which have caused the roadway or entrance to settle.
 
 
 
'''Scheduling'''
 
 
 
As needed, year around.
 
 
 
'''Recommended Equipment'''
 
 
 
*Trucks
 
*Backhoe, Excavator, Loader, or Motorgrader
 
*Mechanical Compactor
 
*Dragline
 
*Crane
 
*Breaker
 
*Trenching Protective System/ Sheeting
 
*Traffic Control Equipment (see [[616.23 Traffic Control for Field Operations|Traffic Control for Field Operations]])
 
 
 
'''Recommended Material'''
 
 
 
*Pipe & Accessories
 
*Joint Compound
 
*Roadway Surface Material
 
*Precast Box Culvert
 
*Backfill Material
 
 
 
'''Recommended Procedure'''
 
 
 
1. Call Dig Rite and MoDOT to check for utilities.
 
 
 
2. Develop trenching safety plan with competent person and supervisor.
 
 
 
3. Place traffic control devices as needed.
 
 
 
4. Remove existing pipe or box.
 
 
 
5. Install protective system in trench, if necessary.
 
 
 
6. Prepare subgrade.
 
 
 
7. Place new pipe or box and seal joints.
 
 
 
8. Remove protective system.
 
 
 
9. Compact material in lifts around and over pipe or box.
 
 
 
10. Place and compact surfacing material.
 
 
 
11. Clean work area.
 
 
 
12. Remove traffic control devices.
 
 
 
'''Safety'''
 
 
 
Call before you dig to locate utilities (1-800-DIG-RITE). Hard hats are required. Watch for sharp edges and "pinch points." Wear all appropriate PPE. Refer to Risk Management On Line Manual Section 2.4 for [http://lnapp1/RI/RIManual.NSF/2cfd1a8d7c4213d7862562d900795ea7/c997dd19e850254f86256df60052ada1?OpenDocument Trenching and Shoring Procedures.] Also comply with the [http://lnapp1/RI/RIManual.NSF/SHToC?OpenView Safety Policies, Rules & Regulations-Employee Handbook.]
 
 
 
'''Other Considerations'''
 
 
 
If entire roadway is to be closed, local news media, schools, emergency services, and law enforcement agencies should be informed in advance.
 
  
'''References'''
+
Index of all [[:Category:170 Maintenance Activity Planning Guidelines#Index of Printable Planning Guides|Maintenance Planning Guidelines]].
  
Standard Specification [http://modot.mo.gov/business/standards_and_specs/Sec0725.pdf Sec 725], [http://modot.mo.gov/business/standards_and_specs/Sec0726.pdf Sec 726] and [http://modot.mo.gov/business/standards_and_specs/Sec0733.pdf Sec 733].
+
==773.5 Maintenance Planning Guideline for Cleaning and Reshaping Earth Ditches==
 +
See [[:Category:170 Maintenance Activity Planning Guidelines#R316 Drainage|Maintenance Planning Guide for Cleaning and Reshaping Earth Ditches]].
  
{|
+
Index of all [[:Category:170 Maintenance Activity Planning Guidelines#Index of Printable Planning Guides|Maintenance Planning Guidelines]].
|[[Image:773 Replacing Pipe and Box Culverts1.jpg|400px]] || [[Image:773 Replacing Pipe and Box Culverts2.jpg|400px]]
 
|-
 
|text align="center"|'''Sawcut Pavement for Culvert Replacement''' || text align="center"|'''Open Trench for Culvert Replacement'''
 
|-
 
|[[Image:773 Replacing Pipe and Box Culverts3.jpg|400px]] || [[Image:773 Replacing Pipe and Box Culverts4.jpg|400px]]
 
|-
 
|text align="center"|'''Setting Grade for Culvert Bedding''' || text align="center"|'''Fine Grading Culvert Bed'''
 
|-
 
|[[Image:773 Replacing Pipe and Box Culverts5.jpg|400px]] || [[Image:773 Replacing Pipe and Box Culverts6.jpg|400px]]
 
|-
 
|text align="center"|'''Laying Culvert Pipe''' || text align="center"|'''Installing Pipe Connecting Band'''
 
|-
 
|[[Image:773 Replacing Pipe and Box Culverts7.jpg|400px]] || [[Image:773 Replacing Pipe and Box Culverts8.jpg|400px]]
 
|-
 
|text align="center"|'''Backfilling around Culvert Pipe''' || text align="center"|'''Spreading and Compacting Pipe Fill'''
 
|-
 
|[[Image:773 Replacing Pipe and Box Culverts9.jpg|400px]] || [[Image:773 Replacing Pipe and Box Culverts10.jpg|400px]]
 
|-
 
|text align="center"|'''Laying Hot Mix Asphalt''' || text align="center"|'''Finished Product'''
 
|}
 

Latest revision as of 08:04, 22 July 2016