If a local public agency receives funds from MoDOT but does not use MoDOT QC/QA practices, the guidelines in the Off-Systems Guide Schedule for Federal-Aid Acceptance Sampling and Testing (FAST) table, below, should be followed.
+
The following information establishes procedures for LPA Federal-Aid Acceptance Sampling and Testing (FAST) for all Federal-Aid projects awarded and administered by MoDOT. If a [[:Category:136 Local Public Agency (LPA) Policy|local public agency]] receives federal funds from MoDOT but does not specify, the guidelines in this Off-Systems Guide Schedule for Federal-Aid Acceptance Sampling and Testing (FAST) table should be followed. The acceptance sampling and testing procedures for other materials and construction processes are to be as shown in other articles in the Engineering Policy Guide.  
  
  
Line 10: Line 10:
 
|'''Subgrade Preparation'''||Density/Moisture||After compaction||A minimum of 4 density tests per day for each active grading spread regardless of road surface
 
|'''Subgrade Preparation'''||Density/Moisture||After compaction||A minimum of 4 density tests per day for each active grading spread regardless of road surface
 
|-
 
|-
|'''Aggregate Base<sup>1</sup>''' (roadway and shoulders)||Gradation||Before compaction||One per 5000 tons or fraction thereof per specified gradation per source.  None required if less than 1000 tons of a specified gradation.
+
|rowspan="3"|'''Aggregate Base<sup>1</sup><br/>Type 1, 5, 7''' or '''Stabilized Permeable<sup>2</sup><br/>(roadway and shoulders)||Gradation||Before compaction||One per 2000 tons or fraction thereof per specified gradation per source.
 
|-
 
|-
|rowspan="2"|'''Type 1, 2, 3, 4<sup>2</sup>, 5''' or '''Stabilized Permeable<sup>2'''</sup>||Density/Moisture||After compaction||A minimum of 4 density and moisture tests per day
+
|Density/Moisture|| After compaction||A minimum of 4 density and moisture tests per day for Type 1 and 5 aggregate and 4 penetration and moisture tests for Type 7 aggregate.
 
|-
 
|-
|Plasticity Index||Before compaction||One per project per specified gradation, per source.  None required if less than 1000 tons of specified gradation.
+
|Plasticity Index|| Before compaction|| One per project per specified gradation, per source.
 
|-
 
|-
|rowspan="4"|'''Sand-Soil Base''' or '''Soil-Cement Base''' or '''Soil-Lime Base'''||Gradation||Before compaction||One per 5000 tons or fraction thereof per specified gradation per source.  None required if less than 1000 tons of a specified gradation.
+
|rowspan="4"|'''Sand-Soil Base''' or '''Soil-Cement Base''' or '''Soil-Lime Base''' ||Gradation|| Before compaction|| One per 2000 tons or fraction thereof per specified gradation per source.
 
|-
 
|-
|Density||After compaction||A minimum of 4 density and moisture tests per day
+
|Density|| After compaction|| A minimum of 4 density and moisture tests per day
 
|-
 
|-
|Liquid Limit||Before compaction||One per project per specified gradation, per source.  None required if less than 1000 tons.
+
|Liquid Limit|| Before compaction|| One per project per specified gradation, per source.
 
|-
 
|-
|Plasticity Index||Before compaction||One per project per specified gradation, per source.  None required if less than 1000 tons.
+
|Plasticity Index|| Before compaction|| One per project per specified gradation, per source.
 
|-
 
|-
|'''Crushed Stone''' or '''Gravel Surfacing'''||Gradation||<center>-</center> ||One per project per specified gradation, per source.  None required is less than 1000 tons or 750 cubic yards.
+
|'''Crushed Stone''' or '''Gravel Surfacing'''||Gradation||align="center"| - ||One per project per specified gradation, per source.  Less than 500 tons accepted on certification.
 
|-
 
|-
|rowspan="3"|'''Plant Mix Bit. Base''' or '''Plant Mix Bit. Pavement''' or '''Asphaltic Concrete Pavement'''||Gradation||Before mixing||One per 500 tons or fraction thereof per type of construction.  None required if type of mixture is less than 250 tons.
+
|rowspan="3"|'''Plant Mix Bit. Base''' or '''Plant Mix Bit. Pavement''' or '''Asphaltic Concrete Pavement'''||Gradation ||Before mixing||One per 500 tons or fraction thereof per mix type.  None required if mix type is less than 50 tons/day or 250 tons/project.
 
|-
 
|-
|Density||After compaction||One sample per day unless undesirable results are achieved, then another sample will be requiredThe results of the re-test will become the acceptance.
+
|Density|| After compaction|| 2 roadway cores/day and 2 longitudinal unconfined joint cores/day < 100 tons
 +
4 roadway cores/day and 4 longitudinal unconfined joint cores/day ≥ 100 tonsRandom Procedures per ASTM D 3665-07.
 
|-
 
|-
|Asphalt Content||Before compaction|| One per day, using an approved AASHTO method for determining asphalt content.
+
|Asphalt Content||Before compaction ||One per day, using an approved AASHTO method for determining asphalt content.
 
|-
 
|-
|rowspan="5"|'''PCC Pavement''' or '''PCC Base'''||Gradation (both coarse and fine aggregates)||Batch plant||One per 5000 tons or fraction thereof per specified gradation, per source.  None required if less than 1000 tons of a specified gradation.
+
|rowspan="4"|'''PCC Pavement''' or '''PCC Base'''||Gradation (both coarse and fine aggregates)||Batch plant|| One per 2000 cubic yards or fraction thereof per specified gradation, per source.
 
|-
 
|-
|Gradation Deleterious (coarse aggregate)||Batch plant||One per project per specified gradation, per source. None required if less than 1000 tons of a specified gradation.
+
|Deleterious (coarse aggregate)||Batch plant|| One per 2000 cubic yards or fraction thereof per specified gradation, per source.
 
|-
 
|-
|Air Content||Jobsite||Air tests are to be made at the beginning of each pour and for each 100 cubic yards thereafter.
+
|Air Content/Slump|| Jobsite|| Air and consistency tests are to be made at the beginning of each pour and for each 100 cubic yards/mix design/pour/day thereafter.
 
|-
 
|-
|Slump||Jobsite||Consistency of concrete should be determined each time an air-entrainment test is made.
+
|Compressive Strength|| Jobsite||One set3 of specimens should be made at the beginning of each pour and every 100 cubic yards/mix design/pour/day thereafter. <sup>4</sup>
 
|-
 
|-
|Compressive Strength||Jobsite||Two routine specimens should be created from the first pour of each class of concrete in any one day and every 200 cubic yards thereafter.<sup>'''3'''</sup>
+
|rowspan="4"|'''Concrete Masonry''' <br/>Structural items including but not limited to: Bridges, CIP retaining walls, box culverts, bolted-down footings||Gradation (both coarse and fine aggregates)||Batch plant||One per 1000 cubic yards or fraction thereof per specified gradation, per source.
 
|-
 
|-
|rowspan="5"|'''Concrete Masonry''' (structures, box culverts, curb & gutter, sidewalk, etc.)||Gradation (both coarse and fine aggregates)||Batch plant||One per 1000 tons or fraction thereof per specified gradation, per source.  None required if less than 100 tons of a specified gradation.
+
|Deleterious (coarse aggregate)||Batch plant||One per 1000 cubic yards or fraction thereof per specified gradation, per source.
 
|-
 
|-
|Deleterious (coarse aggregate)||Batch plant||One per 1000 tons or fraction thereof per specified gradation, per source.  None required if less than 100 tons of a specified gradation.
+
|Air Content/Slump||Jobsite|| Air and consistency tests are to be made at the beginning of each pour and for each 100 cubic yards/mix design/pour/day thereafter.
 
|-
 
|-
|Air Content||Jobsite||Air tests are to be made at the beginning of each pour on structures and for each 100 cubic yards thereafter.
+
|Compressive Strength|| Jobsite||One set<sup>3</sup> of specimens should be made at the beginning of each pour and every 100 cubic yards/mix design/pour/day thereafter. <sup>4</sup>
 
|-
 
|-
|Slump||Jobsite||Consistency of concrete should be determined each time an air-entrainment test is made.
+
|rowspan="4"|'''Concrete Masonry''' <br/>Incidental Concrete (curb & gutter, sidewalk, etc.)||Gradation (both coarse and fine aggregates)||Batch plant||One per 1000 cubic yards or fraction thereof per specified gradation, per source.
 
|-
 
|-
|Compressive Strength||Jobsite||Two routine specimens should be created from the first pour of each class of concrete in any one day and every 200 cubic yards thereafter.<sup>'''3'''</sup>
+
|Deleterious (coarse aggregate)|| Batch plant|| One per 1000 cubic yards or fraction thereof per specified gradation, per source.
 
|-
 
|-
|colspan="4"|<sup>'''1'''</sup> When aggregate base shown in the contract is to be measured and paid for by area, convert the area to tons and follow the sampling frequency shown in this table.  When converting, use the factor .06 tons/sq. yd./1 in. thickness of compacted base.
+
|Air Content/Slump|| Jobsite|| Air and consistency tests are to be made at the beginning of each pour and for each 100 cubic yards/mix design/pour/day thereafter.
 
|-
 
|-
|colspan="4"|<sup>'''2'''</sup> Gradation only for Type 4 and Stabilized Permeable Base.
+
|Compressive Strength|| Jobsite|| One set<sup>3</sup> of specimens should be made at the beginning of each pour and every 100 cubic yards/mix design/pour/day thereafter when the total quantity on the concrete tickets per mix design is ≥ 3cy.<sup>5</sup>
 
|-
 
|-
|colspan="4"|<sup>'''3'''</sup> Air and slump tests are required for each set of cylinders created.
+
|Precast Items ||Gradation/Deleterious/Air Content/Slump ||Manufacture Plant ||Obtain plant certification when using MoDOT approved plant otherwise quality plan will need to be submitted.
 +
|-
 +
|Coating of Structural Steel<sup>6</sup>||Environmental Conditions/Surface Profile/Mil Thickness||Jobsite|| One test/day as it applies for working being performed
 +
|-
 +
|colspan="4"|''' <sup>1</sup>''' When aggregate base shown in the contract is to be measured and paid for by area, convert the area to tons and follow the sampling frequency shown in this table. When converting, use the factor .06 tons/sq. yd./1 in. thickness of compacted base.
 +
|-
 +
|colspan="4"|''' <sup>2</sup>''' Gradation only for Type 4 and Stabilized Permeable Base.
 +
|-
 +
|colspan="4"|''' <sup>3</sup>''' One set of cylinders shall consist of 2 - 6” x 12” cylinder molds or 3 - 4” x 8” cylinder molds. To determine if ultimate (contractual) strength has been obtained, one set of cylinders must be tested and the average strength of all cylinders will determine ultimate strength of in place concrete.
 +
|-
 +
|colspan="4"|''' <sup>4</sup>''' Air and slump tests are required for each set of cylinders created.
 +
|-
 +
|colspan="4"|''' <sup>5</sup>''' Compressive strength test can be waived if the concrete to be placed in any one day is less than 3 C.Y. and an air, slump, and compressive strength test was performed the preceding day on that class of concrete.
 +
|-
 +
|colspan="4"|''' <sup>6</sup>''' Painting contractor is required to be part of certification program such as NACE, SSPC or equivalent.
 
|}
 
|}

Latest revision as of 13:54, 12 June 2015

The following information establishes procedures for LPA Federal-Aid Acceptance Sampling and Testing (FAST) for all Federal-Aid projects awarded and administered by MoDOT. If a local public agency receives federal funds from MoDOT but does not specify, the guidelines in this Off-Systems Guide Schedule for Federal-Aid Acceptance Sampling and Testing (FAST) table should be followed. The acceptance sampling and testing procedures for other materials and construction processes are to be as shown in other articles in the Engineering Policy Guide.


Type of Construction or Material Tests to be Made (if specified) Sampled Minimum Number of Tests
Grading - Embankment Density/Moisture After compaction A minimum of 4 density tests per day for each active grading spread regardless of road surface
Subgrade Preparation Density/Moisture After compaction A minimum of 4 density tests per day for each active grading spread regardless of road surface
Aggregate Base1
Type 1, 5, 7
or Stabilized Permeable2
(roadway and shoulders)
Gradation Before compaction One per 2000 tons or fraction thereof per specified gradation per source.
Density/Moisture After compaction A minimum of 4 density and moisture tests per day for Type 1 and 5 aggregate and 4 penetration and moisture tests for Type 7 aggregate.
Plasticity Index Before compaction One per project per specified gradation, per source.
Sand-Soil Base or Soil-Cement Base or Soil-Lime Base Gradation Before compaction One per 2000 tons or fraction thereof per specified gradation per source.
Density After compaction A minimum of 4 density and moisture tests per day
Liquid Limit Before compaction One per project per specified gradation, per source.
Plasticity Index Before compaction One per project per specified gradation, per source.
Crushed Stone or Gravel Surfacing Gradation - One per project per specified gradation, per source. Less than 500 tons accepted on certification.
Plant Mix Bit. Base or Plant Mix Bit. Pavement or Asphaltic Concrete Pavement Gradation Before mixing One per 500 tons or fraction thereof per mix type. None required if mix type is less than 50 tons/day or 250 tons/project.
Density After compaction 2 roadway cores/day and 2 longitudinal unconfined joint cores/day < 100 tons

4 roadway cores/day and 4 longitudinal unconfined joint cores/day ≥ 100 tons. Random Procedures per ASTM D 3665-07.

Asphalt Content Before compaction One per day, using an approved AASHTO method for determining asphalt content.
PCC Pavement or PCC Base Gradation (both coarse and fine aggregates) Batch plant One per 2000 cubic yards or fraction thereof per specified gradation, per source.
Deleterious (coarse aggregate) Batch plant One per 2000 cubic yards or fraction thereof per specified gradation, per source.
Air Content/Slump Jobsite Air and consistency tests are to be made at the beginning of each pour and for each 100 cubic yards/mix design/pour/day thereafter.
Compressive Strength Jobsite One set3 of specimens should be made at the beginning of each pour and every 100 cubic yards/mix design/pour/day thereafter. 4
Concrete Masonry
Structural items including but not limited to: Bridges, CIP retaining walls, box culverts, bolted-down footings
Gradation (both coarse and fine aggregates) Batch plant One per 1000 cubic yards or fraction thereof per specified gradation, per source.
Deleterious (coarse aggregate) Batch plant One per 1000 cubic yards or fraction thereof per specified gradation, per source.
Air Content/Slump Jobsite Air and consistency tests are to be made at the beginning of each pour and for each 100 cubic yards/mix design/pour/day thereafter.
Compressive Strength Jobsite One set3 of specimens should be made at the beginning of each pour and every 100 cubic yards/mix design/pour/day thereafter. 4
Concrete Masonry
Incidental Concrete (curb & gutter, sidewalk, etc.)
Gradation (both coarse and fine aggregates) Batch plant One per 1000 cubic yards or fraction thereof per specified gradation, per source.
Deleterious (coarse aggregate) Batch plant One per 1000 cubic yards or fraction thereof per specified gradation, per source.
Air Content/Slump Jobsite Air and consistency tests are to be made at the beginning of each pour and for each 100 cubic yards/mix design/pour/day thereafter.
Compressive Strength Jobsite One set3 of specimens should be made at the beginning of each pour and every 100 cubic yards/mix design/pour/day thereafter when the total quantity on the concrete tickets per mix design is ≥ 3cy.5
Precast Items Gradation/Deleterious/Air Content/Slump Manufacture Plant Obtain plant certification when using MoDOT approved plant otherwise quality plan will need to be submitted.
Coating of Structural Steel6 Environmental Conditions/Surface Profile/Mil Thickness Jobsite One test/day as it applies for working being performed
1 When aggregate base shown in the contract is to be measured and paid for by area, convert the area to tons and follow the sampling frequency shown in this table. When converting, use the factor .06 tons/sq. yd./1 in. thickness of compacted base.
2 Gradation only for Type 4 and Stabilized Permeable Base.
3 One set of cylinders shall consist of 2 - 6” x 12” cylinder molds or 3 - 4” x 8” cylinder molds. To determine if ultimate (contractual) strength has been obtained, one set of cylinders must be tested and the average strength of all cylinders will determine ultimate strength of in place concrete.
4 Air and slump tests are required for each set of cylinders created.
5 Compressive strength test can be waived if the concrete to be placed in any one day is less than 3 C.Y. and an air, slump, and compressive strength test was performed the preceding day on that class of concrete.
6 Painting contractor is required to be part of certification program such as NACE, SSPC or equivalent.