Difference between revisions of "Recent Policy Changes in the EPG"

From Engineering_Policy_Guide
Jump to navigation Jump to search
m (EPG 153.18)
m (updated)
 
(228 intermediate revisions by 3 users not shown)
Line 1: Line 1:
<div style="padding-bottom: .3em; margin: 0 .5em .5em"></div>
+
<div style="border: 0px solid #74BAAC; background:white"; padding:5px>
{| cellspacing="3"
+
<!--
|valign="top" cellspacinepgg="0" cellpadding="5" style="border: 1px solid #74BAAC; background:#DCEDEA"|
+
INSTRUCTIONS FOR ADDING A DEFAULT DIVISION STYLE OF BOXES
'''[[153.18 Multimodal|EPG 153.18 Multimodal]]'''
 
  
11/24/20: New information is now available for MO53, Preliminary Engineering Master Agreement.
+
1) Copy the next 4 lines of code below
 +
2) Paste code below where you want to insert your update
 +
3) Update the Date and Text
  
'''[[LPA:136.11 Local Public Agency Construction#136.11.13 Documentation Requirements|EPG 136.11.13 Documentation Requirements]]
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">September 20, 1971
 +
----
 +
TEXT FOR RECENT UPDATES SHOULD BE IN THIS AREA
 +
</div>
 +
-->
 +
</br>
 +
<!-- ADD NEW CONTENT BELOW THIS LINE -->
  
11/23/20: MoDOT will no longer be approving specific software for use; the LPA must ensure the software chosen meets the outlined criteria. Guidance about what should be documented in the construction diaries was clarified in [[LPA:136.11 Local Public Agency Construction#136.11.13.1 Project Diaries|EPG 136.11.13.1 Project Diaries]].
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">March 27, 2024
 +
----
 +
*[[751.1_Preliminary_Design|EPG 751.1 Preliminary Design]] and [[751.36_Driven_Piles|EPG 751.36 Driven Piles]] were revised to clarify guidance for field verification of pile driving which affects design and construction.
 +
*[[751.5_Structural_Detailing_Guidelines#751.5.9.2.1.2_Bend_Shapes|EPG 751.5.9.2.1.2 Bend Shapes]]: New article under the general information for reinforcing steel explaining MoDOT’s bent bar shapes used in structures.
 +
*[[751.5_Structural_Detailing_Guidelines#751.5.9.2.7_Length_Calculations|EPG 751.5.9.2.7 Length Calculations]]: Clarified calculations for hook dimensions and bend deductions.
 +
*[[751.11_Bearings#751.11.3.5_Anchor_Bolts|EPG 751.11.3.5]], [[751.12_Barriers,_Railings,_Curbs_and_Fences#751.12.1.3_Type_D_and_H_.2842.CA.BA_and_32.CA.BA_single_sloped_railing.29|751.12.1.3-6]],[[751.22_Prestressed_Concrete_I_Girders#751.22.3.4.1_Reinforcing_Steel_Details|751.22.3.4.1]] and [[751.31_Open_Concrete_Intermediate_Bents|751.31]],[[751.32_Concrete_Pile_Cap_Intermediate_Bents|32]] & [[751.35_Concrete_Pile_Cap_Integral_End_Bents|35]]: Revised references to stirrup pin bend shapes. Revised bar shape dimensions or shape numbers in accordance with revisions to the bill of reinforcing standard drawing.
 +
</div>
  
'''[[751.50 Standard Detailing Notes#I4. Fiber Reinforced Polymer (FRP) Wrap - Bent Cap Shear Strengthening|EPG 751.50, I4. Fiber Reinforced Polymer (FRP) Wrap - Bent Cap Shear Strengthening]]'''
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">March 14, 2024
 +
----
 +
*Changes made to [[902.5_Traffic_Control_Signal_Features_(MUTCD_Chapter_4D)#902.5.23_Signal_Indications_for_Left-Turn_Movements_.E2.80.93_General_.28MUTCD_Section_4D.17.29|902.5.23 Signal Indications for Left-Turn Movements – General (MUTCD Section 4D.17)]] due to new guidelines for Protected Only Left Turns.
 +
</div>
  
11/20/20: New standard notes for Standard Drawing RHB08 to clarify note regarding design force.
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">January 23, 2024
 +
----
 +
*Change made to [[230.1_Horizontal_Alignment#230.1.5_Spiral_Transition_Curves|EPG 230.1.5 Spiral Transition Curves]] due to a change in the 2018 AASHTO Green Book for superelevation runoff lengths for 50+ mph.
 +
*[[616.8_Typical_Applications_(MUTCD_6H)#616.8.1_Temporary_Traffic_Control_for_Contract_Plan_Sheet_Development|616.8.1 Temporary Traffic Control for Contract Plan Sheet Development]] clarifies stationary TMAs will become a new lump sum bid item with applicable new TMA JSP.  Mobile operation TMAs will be incidental to the bid items that utilize such methods to get a task done.
 +
*Clarified guidance for conduit clamp anchors versus anchor bolts in [[751.12_Barriers,_Railings,_Curbs_and_Fences#751.12.1.2.7_Details_of_Mounting_Light_Poles_on_Safety_Barrier_Curbs|EPG 751.12.1.2.7 Details of Mounting Light Poles on Safety Barrier Curbs]] and [[751.50_Standard_Detailing_Notes#H4._Conduit_System|EPG 751.50 - H4. Conduit System]].
 +
*Provided a MASH TL-4 steel barrier alternate for bridges. Creating MO Std Plans 606.61 and Bridge Standard Drawings TTR04 & 05. Adding standard notes to [[751.50_Standard_Detailing_Notes#H9._Thrie_Beam_and_Other_Rail_Types_.28Notes_for_Bridge_Standard_Drawings.29|EPG 751.50 - H9. Thrie Beam and Other Rail Types (Notes for Bridge Standard Drawings).]]
 +
*Updated [[:Category:1048_Pavement_Marking_Material#1048.2.1.1_Qualified_List|EPG 1048.2.1.1 Qualified List]] due to NTPEP has changed their name to AASHTO Product Evaluation and Audit Solutions.
 +
</div>
  
'''[[147.3 Job Order Contracting (JOC)#147.3.6 Closing JOC Contracts|EPG 147.3.6 Closing JOC Contracts]]'''
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">October 18, 2023
 +
----
 +
*Updates were made to [[236.12_Quality_Assurance_Reviews|236.12 Quality Assurance Reviews]] to provide a more accurate description of the current processes and procedures of our QARs.
 +
</div>
  
11/12/20: Clarified that a Materials Summary is not needed for Job Order Contracts.
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">September 22, 2023
 +
----
 +
*Changes made to EPG guidelines for flags in [[616.6_Temporary_Traffic_Control_Zone_Devices_(MUTCD_6F)#616.6.2.2_Flags_and_Advance_Warning_Rail_System_on_Signs|616.6.2.2 Flags and Advance Warning Rail System on Signs]] and [[616.5_Flagger_Control_(MUTCD_Chapter_6E)#616.5.3.4_Single_Flagger|616.5.3.4 Single Flagger]] to meet the Manual on Uniform Traffic Control Devices (MUTCD).  [[:Category:612_Impact_Attenuators#612.1.4_MoDOT_Equipment.2FMaterials_Stored_in_Bed_of_Protective_Vehicle_Guidelines|612.1.4 MoDOT Equipment/Materials Stored in Bed of Protective Vehicle Guidelines]] was updated to describe how to safely carry loads/cargo in back of the PV as long as it is secure.
 +
</div>
  
'''Wing Lengths and C Bars'''
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">September 19, 2023
 +
----
 +
*Added new EPG article [[907.10_Complete_Streets|907.10 Complete Streets]].
 +
</div>
  
11/12/20: In [[751.1 Preliminary Design#751.1.2.2 Wing Lengths|EPG 751.1.2.2 Wing Lengths]], guidance was added to consider making short turned-back wings sufficiently long so that the Type D barrier end section does not require extensive. In [[751.12 Barriers, Railings, Curbs and Fences#751.12.1.2.1 Slip Forming|EPG 751.12.1.2.1 Slip Forming]], replaced guidance about determining C bars lengths with actual length of C bars.
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">September 15, 2023
 +
----
 +
*[[616.8_Typical_Applications_(MUTCD_6H)|616.8 Typical Applications (MUTCD 6H)]] was updated.
 +
</div>
  
'''[[media:616.8.10 interim.pdf|Fig. 616.8.10 - TMA Flagger - Lane Closure on Two-Lane Highways Using TMA Flaggers - DE/CM/MT]]'''
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">August 22, 2023
 +
----
 +
*Added info and related notes & pay items to EPG for Decorative Pedestrian Fence. Creating Bridge Standard Drawings. Incorporating a Bridge Pre-qualified Listing (BPPL) for decorative fencing in EPG [[751.6_General_Quantities#751.6.1_Index_of_Quantities|751.6.1 Index of Quantities]], [[751.12_Barriers,_Railings,_Curbs_and_Fences#751.12.5_Decorative_Pedestrian_Fence|751.12.5 Decorative Pedestrian Fence]], and [[751.50_Standard_Detailing_Notes|751.50 Standard Detailing Notes]].
 +
</div>
  
11/10/20: Interim guidance for TMA flagger operations is now available in [[616.8 Typical Applications (MUTCD 6H)|EPG 616.8 Typical Applications]].
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">August 14, 2023
 +
----
 +
*Updated guidance that indicates when temporary stop signs should be placed at signalized intersections where the electric is out in EPG [[902.5_Traffic_Control_Signal_Features_(MUTCD_Chapter_4D)#902.5.43.1_Temporary_Stop_Signs_at_Signalized_Intersections|902.5.43.1 Temporary Stop Signs at Signalized Intersections]].
 +
*Updated wind loads in EPG [[751.2_Loads#751.2.2.3_Wind_Loads|751.2.23 Wind Loads]] to current LRFD Bridge design Specifications.
 +
</div>
  
'''[[751.5 Structural Detailing Guidelines|EPG 751.5 Structural Detailing Guidelines]]'''
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">August 11, 2023
 +
----
 +
*Updated EPG [[:Category:753_Bridge_Inspection_Rating|753.15 (Section 15) - Bridge Inspection Rating Manual]] to make the load rating process clearer to users. For efficiency purposes, excel Load Rating Summary Sheets have also been added to the EPG.
 +
</div>
  
11/9/20: Guidance has been added ([[751.5 Structural Detailing Guidelines#751.5.9.2.1.1 Reinforcing Callouts|EPG 751.5.9.2.1.1 Reinforcing Callouts]], for example) to standardize the format for reinforcing callouts.
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">July 21, 2023
 +
----
 +
*Updated and created new graphs for EPG [[751.22_Prestressed_Concrete_I_Girders#751.22.1.3_Typical_Span_Ranges|751.22.1.3 Typical Span Ranges]] and [[751.22_Prestressed_Concrete_I_Girders#751.22.1.4_Span_and_Structure_Lengths|751.21.4 Span and Structure Lengths]] to better reflect current design practices,
 +
</div>
  
'''[[121.3 The Statewide Transportation Improvement Program (STIP)|EPG 121.3 The Statewide Transportation Improvement Program (STIP)]]'''
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">July 19, 2023
 +
----
 +
*Revised [[616.6_Temporary_Traffic_Control_Zone_Devices_(MUTCD_6F)|616.6 Temporary Traffic Control Zone Devices (MUTCD 6F)]] to add Type IV Fluorescent Orange, replacing Type IV Orange and Type IX/XI Fluorescent Orange for trim-line and drum-like channelizers. Type IV Fluorescent Orange will provide better visibility and luminance at driver's normal observation angle. Type IX/XI are designed for higher observation angle performance and incur higher costs to the TTCD.
  
11/5/20: STIP information and the annual process to update the STIP were updated to current practice.
+
*Revised [[:Category:1041_Polypropylene_Culvert_Pipe#1041.7_Polypropylene_Culvert_Pipe_Properties|1041.7 Polypropylene Culvert Pipe Properties]] for current AASHTO references concerning polypropylene storm sewer pipe and NTPEP requirement to be placed on the qualified list. [[750.7_Non-Hydraulic_Considerations#750.7.2_Types|750.7.2]] was also updated to clean up some wording to accurately describe which pipe type is allowable for each group of pipe.
  
'''[[751.50 Standard Detailing Notes#(A2.9)|Updated Standard Detailing Note]]'''
+
*Added guidance on the change from the contractor self perform requirement from 40% to 30% in  [[:Category:108_Prosecution_and_Progress#108.1.1_Review_and_Approval_of_a_Subcontract_Request|108.1.1 Review and Approval of a Subcontract Request]].
  
11/2/20: Verbiage in A2.9 was updated to match new Standard Plan wording.
+
*[[:Category:1017_Slag_Cement|1017 Slag Cement]] was revised to better define slag. Slag cement is the industry terminalolgy and intended material.
  
'''[[:Category:129 Public Involvement|EPG 129 Public Involvement]] and [[127.14 National Environmental Policy Act (NEPA) Classification and Documents#127.14.3.1 Categorical Exclusion|EPG 127.14.3.1 Categorical Exclusion]]'''
+
*Modify referenced ASTM materal standards for HDPE in [[:Category:1060_Electrical_Conduit|1060 Electrical Conduit]] to accurately reflect use as electrical conduit.
  
10/30/20: Updated Programmatic Categorical Exclusion (PCE) and “virtual” public involvement requirements to bring policy into compliance with the federal NEPA regulations. EPG 129 Public Involvement was generally re-written.
+
*[[:Category:1007_Aggregate_for_Base|1007 Aggregate for Base]] processes for the Districts and CM Lab are being updated to establish how comparable and non-comparable tests and material will be handled.  
  
'''[[751.1 Preliminary Design#751.1.2.22 Types of Piling|EPG 751.1.2.22 Types of Piling]] and [[751.24 LFD Retaining Walls#MSE Wall Construction:|EPG 751.24.2.1 Design, MSE Wall Construction: Pipe Pile Spacers Guidance]]'''
+
*Added AASHTO Reference for filter sock to [[806.2_Sediment_Control_Measures|806.2 Sediment Control Measures]] and [[806.8_Storm_Water_Pollution_Prevention_Plan_(SWPPP)#806.8.6.4_Sediment_Control_Measures|806.8.6.4 Sediment Control Measures]].
  
10/30/20: Guidance clarified pile spacer embedment requirements when rock is anticipated within a 5 - 10 ft. zone below the MSE wall leveling pad.
+
*[[616.27_Fleet_Lighting|Fleet Lighting]] and [[:Category:612_Impact_Attenuators#612.1.2_MoDOT_Protective_Vehicle.2FTMA_Marking_and_Lighting|612.1.2 MoDOT Protective Vehicle/TMA Marking and Lighting]] were updated to align with the new typical applications.
  
'''Sand Barrel Impact Attenuator Arrays'''
+
*Shop drawing review and fabrication inspection responsibilities have been updated in [[106.16_Special_Designs_and_Shop_Drawings#106.16.2_Shop_Drawings|106.16.2 Shop Drawings]] and [[:Category:1080_Structural_Steel_Fabrication#1080.2_Fabrication_Inspection_Shipment_Release_.28FISR.29|1080.2 Fabrication Inspection Shipment Release (FISR)]]
  
10/29/20: Guidance in [[:Category:612 Impact Attenuators#612.2 Sand-Filled Impact Attenuators (Sand Barrels)|EPG 612.2 Sand-Filled Impact Attenuators (Sand Barrels)]] and [[:Category:612 Impact Attenuators#Sand-Filled Impact Attenuator Array|EPG 612.3 Construction Inspection Guidelines]] was updated to clarify how the sand barrel impact attenuator arrays are paid for and used in work zones.
+
*Updated [[:Category:950_Automated_Traffic_Enforcement#950.1.4_Violation_Study|950.1.4 Violation Study]] and [[:Category:950_Automated_Traffic_Enforcement#950.1.6_Conditions_for_Intersections_with_Automated_Red-Light_Violation_Enforcement_Equipment_Installed_After_January_2011|950.1.6 Conditions for Intersections with Automated Red-Light Violation Enforcement Equipment Installed After January 2011]]. Clarifcation was added for who at MoDOT will review the data.
  
'''[[:Category:134 Engineering Professional Services#134.2.4 Consultant Solicitation and Selection Process – Standard Solicitation Method for On-Call Cost Plus Fixed Fee Contracts|EPG 134.2.4 Consultant Solicitation and Selection Process – Standard Solicitation Method for On-Call Cost Plus Fixed Fee Contracts]]'''
+
*[[751.10_General_Superstructure#751.10.1.12_Slab_Pouring_Sequences_and_Construction_Joints|751.10.1.12 Slab Pouring Sequences and Construction Joints]] and [[751.50_Standard_Detailing_Notes#H6._Pouring_and_Finishing_Concrete_Slabs|H6. Pouring and Finishing Concrete Slabs]] have been updated to clarify for simple spans and for redecks (both don’t require pouring sequences) that decks shall be poured up grade.
  
10/28/20On-call consultant guidance has been updated.
+
*[[:Category:242_Optional_and_Alternate_Pavement_Designs#242.6_Specifying_One_Pavement_Type|242.6 Specifying One Pavement Type]] was updated to change documentation requirements from Design Exception, to file a memo in eProjects. The State Design Engineer and State Construction and Materials Engineer will still need to be informed when one pavement type is specified on a MoDOT contract.
  
'''[[237.8 Contract Time#237.8.2 Liquidated Damages|EPG 237.8.2 Liquidated Damages]]'''
+
*Added acceeleration/decereation lane guidance lookup table to [[233.2_At-Grade_Intersections_with_Stop_and_Yield_Control#233.2.6_Type_4:_Directional_Median_Opening_with_Downstream_U-Turns|233.2.6 Type 4: Directional Median Opening with Downstream U-Turns]]
 +
</div>
  
10/26/20: Guidance was clarified to provide justification for higher liquidated damages.
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">June 27, 2023
 +
----
 +
*Updated TRB’s NCHRP Report 1043, Guide for Roundabouts in [[233.3_Roundabouts|233.3 Roundabouts]]
  
'''[[:Category:1048 Pavement Marking Material#1048.2.7.3 Acceptance|EPG 1048.2.7.3 Acceptance]]'''
+
*Updated [[:Category:753_Bridge_Inspection_Rating|753 Bridge Inspection Rating]] - A new section was added to the Bridge Inspection Rating Manual - Tunnel Inspection Requirements in Missouri
  
10/22/20: Guidance has been updated to reflect the current process for how acrylic waterborne and high build acrylic waterborne traffic marking are accepted.
+
*Updated [[:Category:941_Permits_and_Access_Requests#941.10_Automated_License_Plate_Readers_and_Pan-Tilt-Zoom_Cameras|941.10 Automated License Plate Readers and Pan-Tilt-Zoom Cameras]] to reflect new approval process with the Department of Public Safety and clearification on existing guidance.
  
'''Minimum Wall Thickness for CIP Piles and Limited Nominal Axial Resistance of CIP Piles Embedded and Tipped in Cohesionless Soils'''
+
*Updates to [[:Category:941_Permits_and_Access_Requests#941.2_Entrance_Requests_Within_Controlled_Access_Right_of_Way|941.2 Entrance Requests Within Controlled Access Right of Way]] have been made to improve coordination between district traffic and right of way staff.
 +
</div>
  
10/19/20: Guidance in [[751.36 Driven Piles|EPG 751.36 Driven Piles]] (particularly in [[751.36 Driven Piles#751.36.2.2.2 Cast-In-Place (CIP) Pile|EPG 751.36.2.2.2 Cast-In-Place (CIP) Pile]], [[751.36 Driven Piles#751.36.5.7.1 Design Values for Individual HP Pile|EPG 751.36.5.7.1 Design Values for Individual HP Pile]], and [[751.36 Driven Piles#751.36.5.10 Pile Nominal Axial Compressive Resistance|EPG 751.36.5.10 Pile Nominal Axial Compressive Resistance]]) was updated to implement maximum axial loads in sands and clarified minimum nominal wall thickness requirements for CIP pile. Numerous standard detailing notes in [[751.50 Standard Detailing Notes#G. Substructure Notes|EPG 751.50, G. Substructure Notes]] for hooks of vertical bar requirements for column and CIP piles were also clarified.
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">May 24, 2023
 +
----
 +
*Added two new Material Inspection Test Methods to 106.3.2:  [[106.3.2.91_TM-91,_Determination_of_Total_Sulfur_in_Fly_Ash_by_Sodium_Carbonate_fusion|106.3.2.91 TM-91, Determination of Total Sulfur in Fly Ash by Sodium Carbonate fusion]] and [[106.3.2.92_TM-92,_Determination_of_Sulfide_sulfur_by_oxidation_of_blended_slag_cements|106.3.2.92 TM-92, Determination of Sulfide sulfur by oxidation of blended slag cements]].
 +
</div>
  
'''[[236.7 Negotiation#236.7.4.4 Agreement for Purchase of Real Estate|EPG 236.7.4.4 Agreement for Purchase of Real Estate, When Agreement for Purchase of Real Estate is Used]]'''
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">May 1, 2023
 +
----
 +
*Updated [[Media:903.2a_Signpost_Selection_Guide_2022-5-23.xls|Signpost Selection Guide]] to show "BREAKAWAY REQUIRED" note for applicable entries in the PSST tab.
  
10/9/20:  To reflect legal requirements, Tax Lien guidance was added.
+
*Revised [[751.21_Prestressed_Concrete_Slab_and_Box_Beams#751.21.3.4_Prestressing_Strands|EPG 751.21.3.4]] to always use regular-size and fully stressed prestressing strands for the top two prestressing strands for the purpose of supporting the reinforcement cage. The 3/8” support strands are not sufficiently supporting the reinforcement cage.
 +
</div>
  
'''[[:Category:108 Prosecution and Progress#108.16 Project Dates|EPG 108.16 Project Dates]]'''
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">April 26, 2023
 +
----
 +
*Due to a new code of federal regulations relating to bridge weight classifications, [[903.5_Regulatory_Signs#903.5.36_Weight_Limit_Signs_.28R12_Series.29_.28MUTCD_Section_2B.59.29|903.5.36]] has been updated to reflect the changes in signs which will be associated with the new classifications.
 +
</div>
  
9/30/20: EPG 108.16 has been rewritten to reflect the move to AWP.
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">April 20, 2023
 +
----
 +
*A revision to Sec 401.7.6 will clarify that the density requirement applies to only unconfined longitudinal joints. [[:Category:401_Bituminous_Base_and_Pavement#401.2.6_Construction_Requirements_.28Sec_401.7.29|EPG 401.2.6]] pertaining to this spec has been modified.
  
'''[[751.50 Standard Detailing Notes#(J1.21a)|Updated Standard Detailing Note]]'''
+
*Updated [[751.10_General_Superstructure#751.10.4_Conduit_Systems|EPG 751.10.4]] and [[751.50_Standard_Detailing_Notes#H4._Conduit_System|751.50]] to clarify allowed conduit size and junction box size in concrete barrier Type D, Type H, bridge abutment wing and slab.
  
9/28/20: Dowel requirements for inverted U-shape precast coping for large block (panel) MSE walls in Standard Note J1.21a were clarified.  
+
*Added the reasoning behind the 90 day camber for typical bridge projects in [[751.22_Prestressed_Concrete_I_Girders|EPG 751.22]] and consideration of line sag is necessary to retrieve accurate camber measurements in [[:Category:1029_Fabricating_Prestressed_Concrete_Members_for_Bridges#1029.2.13_Inspection_of_Completed_Members|EPG 1029.2.13.]]
  
'''[[751.50 Standard Detailing Notes#(H7.8.2) Use note|New Standard Detailing Note]]'''
+
*Updated [[750.6_Erosion_Control_and_Energy_Dissipation#750.6.3.3_Rock_Ditch_Liner|EPG 750.6.3.3]] clarifying that geotextile is required with Rock Blanket, and now requiring in all installations of Rock Ditch Liner.
  
9/23/20: New Note H7.8.2 is available when requiring epoxy-mastic primer coating on galvanized drain support brackets that come in contact with weathering steel beams/girders.
+
*Updated [[:Category:450_Bituminous_Pavement_Design|EPG 450]] to reflect a change in policy to increase minimum lift thicknesses for Superpave and Bituminous Pavement mixes, as per "four times the nominal maximum aggregate size" as recommended by NCHRP study. Additionally, language was added to explain MSCR Graded binders.
  
'''[[237.5 Special Provisions|EPG 237.5 Special Provisions]]'''
+
*Update to current sheeting types in [[616.6_Temporary_Traffic_Control_Zone_Devices_(MUTCD_6F)|EPG 616.6.]]
 +
</div>
  
9/22/20: Guidance has been clarified and updated to current practice.
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">April 18, 2023
 +
----
 +
*References to LRFD specifications for development lengths and splice lengths have been updated to those of the current version of the AASHTO LRFD Bridge Design Specifications.
 +
*Articles [[751.5_Structural_Detailing_Guidelines|751.5]] and [[751.37_Drilled_Shafts#751.37.6.1_Reinforcement_Design|751.37.6.1]] have been updated to reflect these changes.
 +
</div>
  
'''[[127.27 Guidelines for Obtaining Environmental Clearance for Off-Site Activities|EPG 127.27 Guidelines for Obtaining Environmental Clearance for Off-Site Activities]]'''
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">April 12, 2023
 +
----
 +
*Added verification of signature link and updating language addressing types of appraisals required during condemnations in [[:LPA:136.8_Local_Public_Agency_Land_Acquisition#136.8.5.2_Title_Information|EPG 136.8.5.2]], [[236.7_Negotiation#236.7.1.13_Pre-Negotiation_Preparation|EPG 236.7.1.13]], and [[EPG 236.10_Right_Of_Way_Condemnation#236.10.7.5_Appraisal.2C_Waiver_Valuation_and_Written_Offer_.28RSMo_523.253.29|236.10.7.5]].
 +
</div>
  
9/16/20: Guidance has been updated to reflect current practice.
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">March 8, 2023
 +
----
 +
*Updated the terminology of divisional (formerly median) islands constructed with non-mountable curbs in EPG Articles [[233.2_At-Grade_Intersections_with_Stop_and_Yield_Control#233.2.12_Islands|233.2.12 Islands]], [[643.4_Railroads#643.4.1.14_Railroad_Crossing_Median_Islands|643.4.1.14 Railroad Crossing Median Islands]] and [[901.1_Lighting_to_be_Provided,_Operated,_and_Maintained_at_State_Expense|901.1.2 Basic Lighting and Intersections Including Ramp Terminals at Crossroads]].
 +
</div>
  
'''[[751.36 Driven Piles#751.36.5.8 Additional Provisions for Pile Cap Footings|EPG 751.36.5.8 Additional Provisions for Pile Cap Footings]]'''
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">March 7, 2023
 +
----
 +
*Archived [[:Category:405 Processing Reclaimed Asphalt|405 Processing Reclaimed Asphalt]]. The information in this Article is outdated and has been removed.
 +
</div>
  
9/16/20: Guidance has been updated to clarify pile uplift design requirements for pile cap footing and to implement DSB-16-02 requirements.
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">February 9, 2023
 +
----
 +
*Updated [[:Category:401_Bituminous_Base_and_Pavement#401.2.3_Job_Mix_Formula_.28Sec_401.4.29|EPG 401.2.3]] and [[:Category:403_Asphaltic_Concrete_Pavement#403.1.4_Job_Mix_Formula|EPG 403.1.4]] so that District Materials may approve mix transfers if the mix quantity per project is 250 tons or less provided the mix type and contract binder grade match what’s listed on the plan sheets or change order.
 +
</div>
  
'''[[:Category:203 Roadway and Drainage Excavation, Embankment and Compaction#203.2.3.1.2 Embankment in Place (Contractor-Furnished Borrow)|EPG 203.2.3.1.2 Embankment in Place (Contractor-Furnished Borrow)]]'''
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">February 1, 2023
 +
----
 +
*[[616.6_Temporary_Traffic_Control_Zone_Devices_(MUTCD_6F)#616.6.87_Temporary_Rumble_Strips_.28MUTCD_6F.87.29|616.6.87 Temporary Rumble_Strips  (MUTCD_6F.87)]] has been updated to discontinue short-term temporary rumble strips and continue the use of long-term temporary rumble strips.
  
9/16/20: Contractor-furnished borrow guidance has been updated to current practice.
+
*Added FS37_Carbon_Reduction_Program_(CRP)_Funds to [[153.11_Financial_Services|EPG 153.11 Financial Services]]
 +
</div>
  
'''[[127.2 Historic Preservation and Cultural Resources|EPG 127.2 Historic Preservation and Cultural Resources]]'''
+
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">January 27, 2023
 +
----
 +
*Updated [[:Category:139_Design_-_Build|EPG 139 Design-Build]]</br>
 +
This revision updates the Design-Build guidance and processes for invoice reviews, risk to identify auditing, and other minor revisions.
  
9/11/20: Guidance has been updated to reflect changes in the Section 106 processes that have incrementally occurred over the last few years.
+
*Updated [[:Category:134_Engineering_Professional_Services|EPG 134 Engineering Professional Services]]</br>
 +
Revisions to EPG 134 better emphasize how conflicts of interest are identified, better defines the solicitation and selection process, rating/scoring of consultants, and brings the entire process up to current practices.
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">January 19, 2023
 +
----
 +
*Updated [[LPA:136.4_Consultant_Selection_and_Consultant_Contract_Management|EPG 136.4]]
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">January 18, 2023
 +
----
 +
*Revising various specs and EPG articles ([[751.1_Preliminary_Design#751.1.2.9_Girder_Type_Selection|EPG 751.1.2.9]], [[751.6_General_Quantities|751.6]], [[751.14_Steel_Superstructure#751.14.5.8_Protective_Coating_Requirements|751.14.5.8]], [[751.50_Standard_Detailing_Notes|751.50]], [[:Category:1045_Paint_for_Structural_Steel|1045]]) for updates to preferred paint systems. Adding organic zinc coatings and removing calcium sulfonate.
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">January 10, 2023
 +
----
 +
*Update [[903.6_Warning_Signs#903.6.11_Chevron_Alignment_Sign_.28W1-8.29_.28MUTCD_Section_2C.09.29|EPG 903.6.11]] Chevron Alignment Sign (W1-8)
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">January 1, 2023
 +
----
 +
*Updated [[616.8_Typical_Applications_(MUTCD_6H)]]</br>
 +
*Added new Typical Applications Effective January 1, 2023
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">December 12, 2022
 +
----
 +
*Renamed and updated 127.28 Linking Planning and the National Environmental Policy Act (NEPA) to [[127.28_Planning_and_Environmental_Linkages_(PEL)_and_the_National_Environmental_Policy_Act_(NEPA)|127.28 Planning and Environmental Linkages (PEL) and the National Environmental Policy Act (NEPA)]]. The intent and definition of a PEL has changed since the EPG article was written. This update makes it current to practice.
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">December 6, 2022
 +
----
 +
*[[910.5_ITS_Improvements_Procurement#910.5.1_ITS_Procurement_Overview|910.5.1]] - Added 2 CFR 200.216 reference on prohibited vendors
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">November 28, 2022
 +
----
 +
*Added new EPG Article [[153.4 Administrative|153.4 Administrative]] in [[:Category:153 Agreements and Contracts|EPG 153 Agreements and Contracts]]
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">November 15, 2022
 +
----
 +
*[[131.2_Proprietary_Items_and_Public_Interest_Findings|EPG 131.2]] - Removed FHWA and CFR references due to the Changes in 2019 no longer requiring it.
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">November 10, 2022
 +
----
 +
*Correcting language related to NEPA and plan development milestones in EPG  [[127.1_Request_for_Environmental_Services#127.1.2.2_Preliminary_Plans_Stage|127.1.2.2]],  [[:Category:235_Preliminary_Plans#235.1_Purpose|235.1]], [[:Category:235_Preliminary_Plans#235.2_Procedure|235.2]], [[:Category:235_Preliminary_Plans#235.6_Approval_of_Preliminary_Plan|235.6]], [[236.13_Designing_Right_of_Way_Plans|236.13]]
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">November 01, 2022
 +
----
 +
*Modified [[LPA:136.1 Introduction#136.1.3.2 Preliminary and Final Design|EPG 136.1.3.2]], [[LPA:136.7 Design#136.7.2.1.6.1 Minimum Plan Requirements|EPG 136.7.2.1.6.1]], and [[LPA:136.7 Design#136.7.2.2.5.1 General Guidance|EPG 136.7.2.2.5.1]].  Added clarification of the requirement to have LPA preliminary plans reviewed and approved prior to submitting ROW plans for review and approval and provide the approval on a specific memo.
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">October 24, 2022
 +
----
 +
*[[:Category:403_Asphaltic_Concrete_Pavement#403.1_Construction_Inspection_for_Sec_403|EPG Section 403.1]] has been revised primarily to incorporate a longstanding separate Word doc, which explained sampling, testing and acceptance procedures for projects with Superpave mixes.  Additional revisions were made to update in accordance with current construction and materials specifications.
 +
 
 +
*[[903.3_Ground-Mounted_Sign_Supports#903.3.4.4_Pipe_Posts|903.3.4.4]] was updated to eliminate redundant 3" pipe post and update capacities.
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">October 21, 2022
 +
----
 +
*[[:Category:712_Structural_Steel_Construction#712.1.5_High_Strength_Bolts_.28Sec_712.7.29|EPG 712.1.5]] updated to reflect modified testing requirements for high strength bolts.
 +
</div>
 +
 
 +
<!-- OLD UPDATES BELOW THIS LINE
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">September 13, 2022
 +
----
 +
Updated wording in [[806.1 Erosion Control Measures#806.1.7 Temporary Seeding|EPG 806.1.7 Temporary Seeding]], [[806.1 Erosion Control Measures#806.1.7.1 Design Considerations|EPG 806.1.7.1 Design Considerations]] and [[806.8 Storm Water Pollution Prevention Plan (SWPPP)|EPG 806.8.6.3.7.1 Temporary Seeding and Mulching ]]to be in sync with the July 2022 Revisions
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">September 8, 2022
 +
----
 +
Updated the guidance for [[:Category:129 Public Involvement|EPG Category:129 Public Involvement]]
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">September 6, 2022
 +
----
 +
Updated Request for Environmental Services(RES) Instruction Manual in [[:Category:101 Standard Forms|EPG Category:101 Standard Forms]], [[127.1 Request for Environmental Services|EPG 127.1 Request for Environmental Services]] and [[:Category:128 Conceptual Studies|EPG Category:128 Conceptual Studies]]
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">September 1, 2022
 +
----
 +
Updated figures  [[Media:136.6.15_e106_Example_2022.pdf|136.6.15 Example e106 Form]] and [[Media:136.6.16 2022.pdf|136.6.16 LPA Project Checklist for Adverse Effects]] in [[LPA:136.6 Environmental and Cultural Requirements|EPG LPA:136.6 Environmental and Cultural Requirements]]
 +
 
 +
Updated the table in [[153.21 Traffic|EPG 153.21 Traffic]] TR06 was modified and TR07 and TR30 were removed
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">August 31, 2022
 +
----
 +
Noise Ordinance Signing overhauled to [[903.5 Regulatory Signs#903.5.43 Engine Brake Muffler Required Signing|EPG 903.5.43 Engine Brake Muffler Required Signing]]
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">July 28, 2022
 +
----
 +
Update to [[:616.14 Work Zone Safety and Mobility Policy#616.14.3.4_Work_Zone_Review_Team|EPG 616.14.3.4 Work Zone Review Team]] - During work zone reviews, video recording is used to help viewing work zone after the formal review if there is questions of the work zone.  The video recording allows to retain up to 5 buisiness days and then shall be deleted
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">July 25, 2022
 +
----
 +
The [[:Category:753 Bridge Inspection Rating|Bridge Inspection Rating Manual]] has been updated
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">July 20, 2022
 +
----
 +
Removed Warning lights from [[616.19 Quality Standards for Temporary Traffic Control Devices|EPG 616.19 Quality Standards for Temporary Traffic Control Devices]], [[616.23 Traffic Control for Field Operations|EPG 616.23 Traffic Control for Field Operations]], [[616.4 Pedestrian and Worker Safety (MUTCD Chapter 6D)|EPG 616.4 Pedestrian and Worker Safety (MUTCD Chapter 6D)]], [[616.6 Temporary Traffic Control Zone Devices (MUTCD 6F)|EPG 616.6 Temporary Traffic Control Zone Devices (MUTCD 6F)]] and [[616.7 Type of Temporary Traffic Control Zone Activities (MUTCD 6G)|EPG 616.7 Type of Temporary Traffic Control Zone Activities (MUTCD 6G)]]
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">June 29, 2022
 +
----
 +
[[620.6 Colored Pavements#620.6.1 School Logo Pavement Markings|EPG 620.6.1 School Logo Pavement Markings]] - This new guidance clarifies that these markings are not permitted
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">June 27, 2022
 +
----
 +
File Naming Convention for all eProject Documents - New guidelines are available in [[237.13 Contract Plan File Name Convention#237.13.1 Design Contract Plans|EPG 237.13.1 Design Contract Plans]] for a filing convention that is searchable without bringing undue pressure or constraint upon the districts
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">June 24, 2022
 +
----
 +
[[751.14 Steel Superstructure|EPG 751.14 Steel Superstructure]] - Guidance for tension flanges with holes was clarified in [[751.14 Steel Superstructure#Tension Flanges with Holes|EPG 751.14.2.2 Analysis Methods]], [[751.14 Steel Superstructure#Holes in the tension flange1|EPG 751.14.5.1 Bearing Stiffeners]] and [[751.14 Steel Superstructure#Holes in the tension flange2|EPG 751.14.5.2 Int. Diaphragms and Cross Frames]]
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">June 21, 2022
 +
----
 +
Pushbutton Locations - In [[902.6 Pedestrian Control Features (MUTCD Chapter 4E)#902.6.8 Pedestrian Detectors (MUTCD Section 4E.08)|EPG 902.6.8 Pedestrian Detectors]] and in the [https://epg.modot.org/forms/CM/ADA_Checklist.pdf ADA Checklist], guidance has been updated to reflect the minimum distance of pushbuttons from the curb line has been returned to 30 inches
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">June 3, 2022
 +
----
 +
[[236.5 Property Management#236.5.25.5 Risk Assessment|EPG 236.5.25.5 Risk Assessment]] - Sovereign immunity limits increased in January 2022 and MoDOT's per occurrence coverage increased from $3.0 M to $3.5 M
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">June 1, 2022
 +
----
 +
In [[751.11 Bearings#751.11.3.6 Girder/Beam Chairs|EPG 751.11.3.6 Girder/Beam Chairs]], [[751.22 Prestressed Concrete I Girders#751.22.3.5 Strands at Girder Ends|EPG 751.22.3.5 Strands at Girder Ends]] and [[751.22 Prestressed Concrete I Girders#751.22.3.7 Closed Concrete Intermediate Diaphragms|EPG 751.22.3.7 Closed Concrete Intermediate Diaphragms through EPG 751.22.3.11 Steel Intermediate Diaphragms]], guidance was revised to decrease the footprint of girder/beam chairs, clarify and expand concrete diaphragm details to incorporate larger girders, and remove web coil ties in bulb-tees and NU girders to reflect the recent change to standard drawings
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">May 20, 2022
 +
----
 +
[[907.8 Speed Trailers Deployed by Others|EPG 907.8 Speed Trailers Deployed by Others]] - This new article provides guidance for speed trailer deployment to aid local law enforcement in the proper use of these devices
 +
 
 +
[[:Category:941 Permits and Access Requests#941.10 Automated License Plate Readers and Pan-Tilt-Zoom Cameras|EPG 941.10 Automated License Plate Readers and Pan-Tilt-Zoom Cameras]] - Guidance for the License Plate Reader (LPR) was clarified and expanded for proper LPR installations as identified through processing initial requests
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">May 19, 2022
 +
----
 +
[[:Category:747 Bridge Reports and Layouts#747.2.2.4 HEC-RAS GEO Files for Stream Crossings|EPG 747.2.2.4 HEC-RAS GEO Files for Stream Crossings]] - This subarticle was retitled and its guidance updated to reflect the current use of the "HEC-RAS Convertor for Open Roads Designer" spreadsheet
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">May 16, 2022
 +
----
 +
The guidelines, book job guidelines, JSP packages, book job JSP packages and contractor pdf files were updated in [[:Category:402 Bituminous Surface Leveling|EPG 402 Bituminous Surface Leveling]] and [[:Category:409 Seal Coat|EPG 409 Seal Coat]]
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">May 11, 2022
 +
----
 +
[[751.9 LFD Seismic#751.9.3.1.1 Anchor Bolts|EPG 751.9.3.1.1 Anchor Bolts through EPG 751.9.3.1.4 Concrete Shear Blocks]], [[751.11 Bearings#Anchor Bolts|EPG 751.11.2.1 Elastomeric Bearings]], [[751.11 Bearings#751.11.3.5 Anchor Bolts|EPG 751.11.3.5 Anchor Bolts]], [[751.22 Prestressed Concrete I Girders#751.22.2.7 Dowel Bars|EPG 751.22.2.7 Dowel Bars]] and [[751.22 Prestressed Concrete I Girders#751.22.3.14 Concrete Shear Blocks|EPG 751.22.3.14 Concrete Shear Blocks]] - Guidance for the design of bearing anchor bolt, dowel bar and shear block has been expanded and clarified
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">April 29, 2022
 +
----
 +
[[:Category:105 Control of Work#105.15 Project Acceptance|EPG 105.15 Project Acceptance]] - Guidance for project acceptance has been clarified and updated to current practice in EPG 105.15, [[:Category:108 Prosecution and Progress#8. Date of Final Inspection|EPG 108.16.1 Informational Dates]] and [[:Category:109 Measurement and Payment#109.8 Final Acceptance and Payment (for Sec 109.8)|EPG 109.8 Final Acceptance and Payment]]
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">April 21, 2022
 +
----
 +
[[:Category:712 Structural Steel Construction#712.1.4.1.3 Shear Connector Welding|EPG 712.1.4 Welding]] - Guidance for stud welding has been updated to align with Sec 712.6.3. Also, outdated references to field welder cards has been removed
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">April 20, 2022
 +
----
 +
Construction Inspection Guidance for Records to be Maintained - [[:Category:137 Construction Inspection Guidance for Records to be Maintained#137.1 Location|EPG 137.1 Location]] and [[:Category:137 Construction Inspection Guidance for Records to be Maintained#137.6 Close Out Procedure for External CM SharePoint Quality Management Documents|EPG 137.6 Close Out Procedure for External CM SharePoint Quality Management Documents]] now present updated information about how CM Division stores electronic contract documents
 +
 
 +
Guidance for PSST anchor installations has been updated and clarified. [[903.3 Ground-Mounted Sign Supports#903.3.4.3 Perforated Square Steel Tube Posts (PSST)|EPG 903.3.4.3 Perforated Square Steel Tube Posts (PSST)]]
 +
 
 +
Seeding, Mulching and Temporary Seeding - Guidance in [[:Category:802 Mulching|EPG 802 Mulching]], [[:Category:805 Seeding|EPG 805 Seeding]], [[806.1 Erosion Control Measures|EPG 806.1 Erosion Control Measures]] and [[806.8 Storm Water Pollution Prevention Plan (SWPPP)#806.8.6.3.7.1 Temporary Seeding and Mulching (MO Specifications Sec 802 and Sec 805)|EPG 806.8.6.3.7.1 Temporary Seeding and Mulching]] reflects the new standard seed mixes, fertilizer, and lime rates (as shown in the new [https://www.modot.org/media/37677 Standard Plan 805.00 Seeding]) to promote a more effective vegetative establishment, allowing for quicker project  finalization.  MoDOT is obligated to stabilize disturbed areas with permanent building materials or perennial vegetative cover to minimize erosion and sedimentation of disturbed areas. New guidance for cool season and warm season grasses is available. Mulching will not be required for final seeded areas where temporary seeding is planned for temporary stabilization of areas to receive warm season grasses.  A new [[media:Table 805.2.4a.docx|Guide for Grass Species]] is available in [[:Category:805 Seeding#805.2.4 Acceptance (Sec 805.4)|EPG 805.2.4 Acceptance]] to assist with general inspection and acceptance of vegetative covers.
 +
 
 +
Pre-MASH 2016 Temporary Traffic Control Device Sunset Dates - Guidance in [[:Category:612 Impact Attenuators|EPG 612 Impact Attenuators]], [[616.6 Temporary Traffic Control Zone Devices (MUTCD 6F)#616.6.1 Types of Devices (MUTCD 6F.01)|EPG 616.6 Temporary Traffic Control Zone Devices]], [[616.18 Construction Inspection Guidelines for Sec 616#For Sec. 616.3.2|EPG 616.18 Construction Inspection Guidelines for Sec 616]], [[616.19 Quality Standards for Temporary Traffic Control Devices#https://epg.modot.org/index.php?title=616.6_Temporary_Traffic_Control_Zone_Devices_%28MUTCD_6F%29#616.6.84_Temporary_Traffic_Control_Signals_.28MUTCD_6F.84.29|EPG 616.19 Quality Standards for Temporary Traffic Control Devices]], [[616.23 Traffic Control for Field Operations#616.23.2.5 Temporary Traffic Control Devices|EPG 616.23 Traffic Control for Field Operations]], [[617.1 Temporary Traffic Barriers|EPG 617.1 Temporary Traffic Barriers]], [[617.2 Construction Inspection Guidelines for Sec 617|EPG 617.2 Construction Inspection Guidelines for Sec 617]], [[:Category:1063 Temporary Traffic Control Devices#1063.2 Procedure|EPG 1063 Temporary Traffic Control Devices]] and [[:Category:1064 Temporary Concrete Traffic Barrier|EPG 1064 Temporary Concrete Traffic Barrier]] now reflects that all temporary traffic control devices on a project must be NCHRP 350 or MASH 2016 Test Level 3 compliant. The use of two-loop temporary Type F concrete traffic barrier shall not be allowed after January 1, 2023.
 +
 
 +
[[:Category:403 Asphaltic Concrete Pavement#Lots|EPG 403.1.19 Acceptance of Material]] - The maximum number of contractor QC sublots that can be used for one lot of superpave asphalt pavement is 28. Regardless of lot size, QA testing will always be at a frequency of one per four sublots. Any remaining quantity less than 4000 tons, that cannot be treated as a separate lot, will be combined with the previous full lot and the pay factors will be determined on the combined lot.
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">April 18, 2022
 +
----
 +
*Guidance Documents Needed for Property Closings - In [[236.7 Negotiation#236.7.1.13 Pre-Negotiation Preparation|EPG 236.7.1.13 Pre-Negotiation Preparation]] and [[236.7 Negotiation#236.7.4.1 Purpose|EPG 236.7.4.1 Purpose]], additional guidance is available for greater clarity about what is needed from property owners to close on the properties either with MoDOT or a title company.
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">April 11, 2022
 +
----
 +
*In [[751.22 Prestressed Concrete I Girders#751.22.2.5 Pretensioned Anchorage Zones|EPG 751.22.2.5 Pretensioned Anchorage Zones]], the bursting resistance guidance now allows a larger number of bonded strands for many of these girders, effectively increasing the span limits for the girders. Guidance was expanded in [[751.22 Prestressed Concrete I Girders#751.22.3.2.1 Type 2 Girder|EPG 751.22.3.2.1 through 751.22.3.2.6]] to eliminate or reduce conflict between the lowest middle two strands and the B bars.
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">April 5, 2022
 +
----
 +
*Guidance about the timelines for completing the Section 106 of the National Historic Preservation Act review process has been clarified in [[127.2 Historic Preservation and Cultural Resources#127.2.5 Approximate Timelines for Section 106 Compliance|EPG 127.2.5 Approximate Timelines for Section 106 Compliance]]
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">March 28, 2022
 +
----
 +
*Coil Ties in Prestressed Girder Webs in several [[751.50 Standard Detailing Notes#(G1.9.1)|EPG 751.50 Standard Detailing Notes]], references to web coil ties in bulb-tee and NU girders have been removed since these are now no longer being used.
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">March 16, 2022
 +
----
 +
*Guidance has been expanded to produce more uniform administration of delay claims. - [[:Category:109 Measurement and Payment#109.11 Compensation for Project Delays (for Sec 109.11)|EPG 109.11 Compensation for Project Delays]]
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">March 16, 2022
 +
----
 +
*The recommended replacement age for signal cabinets was updated to 25 years from 20 years in [[902.4 Signal Installations and Equipment#902.4.2.1 Controller and Cabinet Replacement Program|EPG 902.4.2.1 Controller and Cabinet Replacement Program]].
 +
</div>
 +
 
 +
<div style="margin: 15px; border:1px solid black; width:97%; background-color:white; padding:5px; border-radius:5px; box-shadow:10px 10px 5px #888888">Feb 15, 2022
 +
----
 +
*Right of Way Mediation in [[236.7 Negotiation#Prior to offering mediation|EPG 236.7.2.19 Acquisition by Mediation]] and [[236.11 Mediation#Prior to offering mediation|EPG 236.11.1.3 Purpose]], guidance has been updated to reflect current process and procedures, including the MoDOT Impasse Letter.
 +
</div>
 +
 
 +
OLD UPDATES BETWEEN COMMENTS-->

Latest revision as of 15:08, 27 March 2024


March 27, 2024
March 14, 2024
January 23, 2024
October 18, 2023
September 22, 2023
September 19, 2023
September 15, 2023
August 22, 2023
August 14, 2023
August 11, 2023
July 21, 2023
July 19, 2023
  • Revised 616.6 Temporary Traffic Control Zone Devices (MUTCD 6F) to add Type IV Fluorescent Orange, replacing Type IV Orange and Type IX/XI Fluorescent Orange for trim-line and drum-like channelizers. Type IV Fluorescent Orange will provide better visibility and luminance at driver's normal observation angle. Type IX/XI are designed for higher observation angle performance and incur higher costs to the TTCD.
  • Revised 1041.7 Polypropylene Culvert Pipe Properties for current AASHTO references concerning polypropylene storm sewer pipe and NTPEP requirement to be placed on the qualified list. 750.7.2 was also updated to clean up some wording to accurately describe which pipe type is allowable for each group of pipe.
  • 1017 Slag Cement was revised to better define slag. Slag cement is the industry terminalolgy and intended material.
  • Modify referenced ASTM materal standards for HDPE in 1060 Electrical Conduit to accurately reflect use as electrical conduit.
  • 1007 Aggregate for Base processes for the Districts and CM Lab are being updated to establish how comparable and non-comparable tests and material will be handled.
  • 242.6 Specifying One Pavement Type was updated to change documentation requirements from Design Exception, to file a memo in eProjects. The State Design Engineer and State Construction and Materials Engineer will still need to be informed when one pavement type is specified on a MoDOT contract.
June 27, 2023
  • Updated 753 Bridge Inspection Rating - A new section was added to the Bridge Inspection Rating Manual - Tunnel Inspection Requirements in Missouri
May 1, 2023
  • Revised EPG 751.21.3.4 to always use regular-size and fully stressed prestressing strands for the top two prestressing strands for the purpose of supporting the reinforcement cage. The 3/8” support strands are not sufficiently supporting the reinforcement cage.
April 26, 2023
  • Due to a new code of federal regulations relating to bridge weight classifications, 903.5.36 has been updated to reflect the changes in signs which will be associated with the new classifications.
April 20, 2023
  • A revision to Sec 401.7.6 will clarify that the density requirement applies to only unconfined longitudinal joints. EPG 401.2.6 pertaining to this spec has been modified.
  • Updated EPG 751.10.4 and 751.50 to clarify allowed conduit size and junction box size in concrete barrier Type D, Type H, bridge abutment wing and slab.
  • Added the reasoning behind the 90 day camber for typical bridge projects in EPG 751.22 and consideration of line sag is necessary to retrieve accurate camber measurements in EPG 1029.2.13.
  • Updated EPG 750.6.3.3 clarifying that geotextile is required with Rock Blanket, and now requiring in all installations of Rock Ditch Liner.
  • Updated EPG 450 to reflect a change in policy to increase minimum lift thicknesses for Superpave and Bituminous Pavement mixes, as per "four times the nominal maximum aggregate size" as recommended by NCHRP study. Additionally, language was added to explain MSCR Graded binders.
April 18, 2023
  • References to LRFD specifications for development lengths and splice lengths have been updated to those of the current version of the AASHTO LRFD Bridge Design Specifications.
  • Articles 751.5 and 751.37.6.1 have been updated to reflect these changes.
April 12, 2023
March 8, 2023
March 7, 2023
February 9, 2023
  • Updated EPG 401.2.3 and EPG 403.1.4 so that District Materials may approve mix transfers if the mix quantity per project is 250 tons or less provided the mix type and contract binder grade match what’s listed on the plan sheets or change order.
February 1, 2023
January 27, 2023

This revision updates the Design-Build guidance and processes for invoice reviews, risk to identify auditing, and other minor revisions.

Revisions to EPG 134 better emphasize how conflicts of interest are identified, better defines the solicitation and selection process, rating/scoring of consultants, and brings the entire process up to current practices.

January 19, 2023
January 18, 2023
January 10, 2023
January 1, 2023
December 12, 2022
December 6, 2022
  • 910.5.1 - Added 2 CFR 200.216 reference on prohibited vendors
November 28, 2022
November 15, 2022
  • EPG 131.2 - Removed FHWA and CFR references due to the Changes in 2019 no longer requiring it.
November 10, 2022
November 01, 2022
  • Modified EPG 136.1.3.2, EPG 136.7.2.1.6.1, and EPG 136.7.2.2.5.1. Added clarification of the requirement to have LPA preliminary plans reviewed and approved prior to submitting ROW plans for review and approval and provide the approval on a specific memo.
October 24, 2022
  • EPG Section 403.1 has been revised primarily to incorporate a longstanding separate Word doc, which explained sampling, testing and acceptance procedures for projects with Superpave mixes. Additional revisions were made to update in accordance with current construction and materials specifications.
  • 903.3.4.4 was updated to eliminate redundant 3" pipe post and update capacities.
October 21, 2022
  • EPG 712.1.5 updated to reflect modified testing requirements for high strength bolts.