Difference between revisions of "237.2 Title Sheet"

From Engineering_Policy_Guide
Jump to navigation Jump to search
m (reformat paragraph)
m (reformat paragraph)
Line 20: Line 20:
 
===237.2.2 Right of Way Access Note===
 
===237.2.2 Right of Way Access Note===
  
A note referring to the type of access control is required on all projects where right of way acquisition is involved.  Four types of right of way access notes are available: (1) normal right of way, (2) controlled access, (3) fully controlled access and (4) partial controlled access.  The three controlled access notes are available on CADD.  If right of way is not required, a note to that effect is shown.
+
A note referring to the type of access control is required on all projects where right of way acquisition is involved.  Four types of right of way access notes are available:
 +
 
 +
:(1) normal right of way,  
 +
:(2) controlled access,  
 +
:(3) fully controlled access and  
 +
:(4) partial controlled access.   
 +
 
 +
The three controlled access notes are available on CADD.  If right of way is not required, a note to that effect is shown.
  
 
===237.2.3 Conventional Symbols===
 
===237.2.3 Conventional Symbols===

Revision as of 11:46, 1 October 2008

237.2 title sheet.jpg


The title sheet identifies the set of plans, conveys the general type of improvement planned, and locates the improvement. Title sheet blanks are available on CADD for district use. The title sheet includes, at least, the following information:

237.2.1 Design Designation

The major criteria under which the improvement is designed are included on the title sheet. These criteria are determined in the appropriate conceptual study report (refer to Conceptual Study), in the location study/environmental report (refer to 128, Conceptual Study), or during design of the project. The design designation consists of:

(1) functional classification,
(2) present daily traffic volume, AADT,
(3) a projected traffic volume, AADT,
(4) design hourly volume percentage, DHV,
(5) directional distribution of traffic percentage, D,
(6) percentage of trucks, T, and
(7) anticipated posted speed, V.

The design hourly traffic volume, directional distribution of traffic, and percentage of trucks may not be required; however, all information available is to be included. The designer is to carefully consider the importance of this information being archived with the plans before arbitrarily removing it from the title sheet.

237.2.2 Right of Way Access Note

A note referring to the type of access control is required on all projects where right of way acquisition is involved. Four types of right of way access notes are available:

(1) normal right of way,
(2) controlled access,
(3) fully controlled access and
(4) partial controlled access.

The three controlled access notes are available on CADD. If right of way is not required, a note to that effect is shown.

237.2.3 Conventional Symbols

237.2.3 conventional.jpg

The blank as furnished to the district contains a basic list of conventional symbols. If additional symbols are used on the plans, the district adds all such symbols.

237.2.4 Location Sketch

The sketch showing the location and limits of the improvement is added to the title sheet by the district. The location sketch shows physical features that will aid in the identification of the proposed road location, including intersecting and adjacent roads, prominent landmarks, towns, section lines, section numbers, and a north arrow. The delineation of the proposed roadway is to be adequate to allow visual identification of its features, such as whether it’s dual or single lane, location of outer roadways, bridges, interchanges, ramps, etc. The major items of work are noted. The project’s beginning and ending points are identified by station and log mile, along with any stationing equations, exceptions, or reverse points. The USGS 7.5 minute series topographic maps may be used as a base from which to develop the location sketch. A graphic scale is included for the location sketch so the scale will be applicable on reduced size prints.

237.2.5 Title Block

The title block is filled out by the district, with the exception of the project number. Design adds this number when necessary.

237.2.6 Index of Sheets

A complete index of the sheets in the plans is shown on the title sheet. Design adds the number of sheets for bridge plans and the standard plans index. This index is completed in CADD.

237.2.7 Length of Project

The length of project is the total length of the improvement less equations and exceptions as noted in the plans. Examples of common exceptions are existing surfaces to be left in place, existing bridges to be used in place, existing intersections, and railroad grade crossings where the exception is the distance between the ends of railroad crossties.