Difference between revisions of "Other Aspects of Pavement Design"

From Engineering_Policy_Guide
Jump to navigation Jump to search
(Several unnumbered EPG articles compiled. (Alt. Pav't, 4973 hits; Shlder Surf., 3346 hits; Soil Cha., 2975 hits & no appreciable history; Temp Conn., 1304 & no hist; Thickness Det. 4618 hits, no hist))
 
m (Updated CM website links (for increased security))
 
(31 intermediate revisions by 2 users not shown)
Line 1: Line 1:
==Alternate Pavement==
+
==Alternate and Optional Pavement==
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="right"
+
Refer to [[:Category:242 Optional and Alternate Pavement Designs|EPG 242 Optional and Alternate Pavement Designs]].
|- 
 
|'''Examples and Results'''
 
|-
 
|[[Media:AltPvmtExampleProposal.pdf|Request for Bids]]
 
|-
 
|[[Media:AltPvmtExamplePlans.pdf|Pavement Plans]]
 
|-
 
|[[Media:AltPvmtJan07Results.pdf|January 2007 Bid Results]]
 
|-
 
|[[Media:AltPavementOverallResults.pdf|Overall Bid Results]]
 
|}
 
 
 
===Purpose of Alternate Pavement Bidding===
 
In an effort to get the best value, create a competitive environment for concrete and asphalt paving industries and promote innovation, MoDOT requires alternate pavement options in the majority of contracts containing full depth pavement.  When alternate pavements are bid, then it is necessary to calculate a Life-Cycle Cost Adjustment (LCCA) factor.  Future maintenance costs are considered in determining the LCCA factor, thus resulting in the most equivalent specifications possible to draw in the maximum number of bidders for MoDOT paving projects.  While alternate bidding is generally advantageous for all projects, circumstances occasionally arise which cause one pavement type to be preferred over the other (See [[#Specifying One Pavement Type|Specifying One Pavement Type]]).
 
 
 
===Life-Cycle Cost Adjustment (LCCA)===
 
 
 
Area of pavement is used to determine whether an alternate pavement project qualifies for a life cycle cost adjustment factor as calculated by the Design Division or a $0 life cycle cost adjustment factor (see [[#Alternate Categories|Alternate Categories]]). 
 
 
 
The LCCA is a monetary value calculated  for each group of alternates in a project and provides a way to fairly compare bids received for low bid and possible contract award. The value considers future treatments that are routinely applied to concrete and asphalt pavements. Treatments considered for asphalt pavements are cold milling and overlay of the traveled way only at 20 years and of the entire surface at 33 years. Treatments considered for PCCP are pavement repair and diamond grinding of the traveled way at 25 years. The treatment types and timeframes used for calculating the LCCA were jointly agreed upon between MoDOT and contracting industries.
 
 
 
The following examples shows how the LCCA is applied to a full asphalt option and a concrete mainline with asphalt shoulder option:
 
 
 
<div id="examples"></div>
 
<center>[[image:AltPavement LCCA Asphalt.gif]]</center>
 
<center>[[image:AltPavment LCCA Concrete.gif]]</center>
 
 
 
<center>Note that no LCCA is applied to concrete shoulders.</center>
 
 
 
MoDOT’s estimators prepare LCCA factors for inclusion in the contracts' Job Special Provisions for projects containing alternate pavements. The latest published real interest rates from the United States Office of Management and Budget will be used to bring the future costs to present worth.
 
 
 
Two separate LCCA factors will be calculated for the contract, one for the mainline pavement and one for the shoulder pavement (A2 or thicker). This will allow contractors flexibility in bidding thus enabling use of the best valued material for the regional market. Projects with alternate pavements will include a life cycle cost adjustment factor as calculated by the Design Division or a $0 life cycle cost adjustment factor according to the following table:
 
 
 
====Alternate Categories====
 
 
 
While each project has the possibility of differing slightly from any other project, there are some general guidelines to consider when setting up alternate categories. 
 
 
 
The following parameters dictate whether Alternate Pavements are to be set up for a project. Alternates pavements are used according to the criteria in the following table:
 
 
 
{| border="1" class="wikitable" style="margin: 1em auto 1em auto"
 
|+ '''Use of Life Cycle Cost Adjustment Factor for Alternate Pavements'''
 
! rowspan="2" style="background:#BEBEBE" |Area of Pavement* and Shoulder** <u>></u> 14,000 yd<sup>2</sup> total !! colspan="2" style="background:#BEBEBE" text align="center"| Area of Pavement and Shoulder** < 14,000 yd<sup>2</sup> total
 
|-
 
|style="background:#CCCEEE" text align="center"|'''<u>></u> 7,500 yd<sup>2</sup> Continuous''' ||style="background:#CCCEEE" text align="center"|'''< 7,500 yd<sup>2</sup> Continuous'''
 
|-
 
|style="text-align:center"| Use LCCA ||style="text-align:center"| Use LCCA ||style="text-align:center"| No LCCA
 
|-
 
|colspan="3" | * Different pavement surface types (high vs. low) are to be considered when computing the area; pavement thickness may vary. Superpave is a High Type Asphalt Mix.  Bituminous Pavement is a Low Type Asphalt Mix. (Total area of High Type Asphalt Mix Surfaces <u>></u> 14,000 yd<sup>2</sup> OR  Total area of Low Type Asphalt Mix Surfaces <u>></u> 14,000 yd<sup>2</sup>)
 
|-
 
|colspan="3" | **Includes A2 (5 3/4 in.) or thicker shoulders
 
|}
 
 
 
Additional consideration is needed for some contracts with projects in combination.  If the projects are disconnected (separated by relatively large distances) then each project’s pavement areas should be accounted for by project.  If, however, the projects in combination are continuous, in the same area, or in relatively close vicinity of one another, the pavement areas should be considered by contract when determining if alternate pavements should be used.
 
 
 
When alternate pavements are required, the project should be evaluated to determine how to set up the alternate paving categories.
 
 
 
* Areas with different surface mix types (SP or BP) should be in separate alternates.  The binder type/grade is not considered in alternate category determination, however it is taken into account in cost calculations for the LCCA.  An example of this is when the mainline pavement is a SP125 mixture and the outer roads are BP-1.
 
 
 
* Ramps should be placed with the highest priority route or with like surface type (SP or BP).
 
 
 
* Shoulders - If it has been determined that alternate pavement is required on the project then the A2 shoulders should be a separate group of alternates. A3 shoulders are not considered for LCCA’s and should be placed in the roadway category.)
 
 
 
====Information Required for Completion of LCCA====
 
 
 
Since LCCAs are based on future treatments, any area that will have a treatment with a different cost applied to it needs to be broken out as a separate quantity.  '''Therefore, areas submitted should be broken down based on surface mix with consideration of mix design and of binder type''' (i.e., SP125 vs. BP-1 or  SP125C, PG64-22 vs. SP125C, PG76-22 or SP125BSMR vs. SP125B). The following information is necessary:
 
 
 
:1) Area of Traveled Way (See [[#examples|examples]] for details on the areas that are considered/required) - consists of the area within the travel lane (pavement markings) for each set of alternates (per mix design and binder grade).
 
 
 
:2) Total Area of Pavement – Needed for each set of alternates and can usually be obtained from a project’s plans Quantity Sheets or proposal (per mix design and binder grade).
 
 
 
:3) Type of Asphalt Pavement Surface Mix (mix design and binder grade).
 
 
 
One quick check for the correctness of the traveled way submission is that it should theoretically be less than the pay item quantity.
 
 
 
====Time Frame for LCCA Completion====
 
 
 
Districts need to supply the information required for completion of the LCCA factors in the transmittal memorandum that is included with the PS&E submittal by the PS&E due date. This will allow time for the Design Division reviewer to check the submittal, send any review comments as necessary and forward a request to the estimator within the time allotted.
 
 
 
To ensure there is sufficient time to prepare an accurate LCCA by the due date, a request for LCCA should be submitted to the estimators a minimum of one week before the notice with all the required information.  This will allow time to receive material quotes, which may take a few days to receive, and prioritize the request among estimating projects in the current letting.
 
 
 
===Plans For Projects with Alternate Pavements===
 
 
 
Plans for all projects with alternate pavements should contain:
 
[[Image:Alternate Pavement Photo3.gif|right|550 px]]
 
*Typical sections for both alternates, including station limits, and all side road connections.
 
*All [http://www.modot.mo.gov/business/contractor_resources/biditemslisting.htm pay items] for full depth alternate pavements shall be in square yards for the entire pavement surface.
 
*One set of 2B sheets with separate sheets for the items associated with each alternate.
 
*Using the "Estimate 2000" program, the quantities for pavement and other items associated only with the asphalt alternate (designated as "Alternate A") should be designated as "Section 02" and the quantities for pavement and other items associated only with the concrete alternate (designated as "Alternate B") should be designated "Section 03". For A2 shoulders or thicker use "Section 04" for the shoulder type that corresponds with "Section 02" and "Section 05" for the shoulder type that corresponds with "Section 03". This will enable summation of the appropriate subtotals to compile an estimated total cost per alternate.
 
*No pay item listed in Section 02 or 03 should be listed in Section 01.  This would lead to differing bids and cause confusion when administering the contract.  For example, if the base quantities differ, include the appropriate total base quantities in Sections 02 and 03, but not Section 01.
 
*For shoulder rumble strips, include the bituminous rumble strip pay item with the asphalt alternate, and the concrete rumble strip pay item with the concrete alternate.
 
*Job Special Provision ALTERNATE FOR PAVEMENTS JSP-96-04 should be inserted in the Job Special Provisions. The Life Cycle Cost adjustment factor is calculated by the Central Office.
 
 
 
Below are design guidelines for different project scenarios:
 
 
 
====Separate Grading and Paving Projects with 18 in. Rock Base====
 
 
 
*Subgrade profile and cross sections should be designed for the thicker pavement alternate.
 
*If the thinner option is constructed, the contractor will be responsible for maintaining the profile grade.  In the paving project the addition of subgrade material for the thinner pavement design will be paid for as Subgrading and Shouldering, Class 2.
 
 
 
====Separate Grading and Paving Projects without 18 in. Rock Base====
 
 
 
*Subgrade, profile and cross sections should be designed for the thinner pavement alternate.
 
*If the thicker option is constructed the contractor will be responsible for maintaining the profile grade.  In the paving project the removal of subgrade material for the thicker pavement design will be paid for as Subgrading and Shouldering, Class 1.
 
*Crossroad structures should be designed to accommodate a minimum cover based on the thicker pavement design.
 
 
 
====Combined Grading and Paving Project====
 
 
 
*Subgrade profile and cross sections should be designed for the thinner pavement alternate.
 
*The contractor will be responsible for maintaining the profile grade for either alternate pavement with no direct pay.
 
*Crossroad structures should be designed to accommodate a minimum cover based on the thicker pavement design.
 
 
 
===Specifying One Pavement Type===
 
The core team should always look at pavement options that bring the best value to the project. Consideration should be given to initial construction cost, long-term maintenance cost, and continuity with existing pavement. Also, impacts to local residents and businesses along the route should be considered.
 
 
 
Pavements having prevailing issues that make only one type of pavement desirable should be examined to determine the feasibility of alternate bids on pavement.  These may include circumstances such as widening existing pavements with safety and durability issues due to differing pavement types in the driving lanes, urban construction, consideration of how the pavement type effects the major item of work for the project (e.g., if major item of work for the project is bridge work the life cycle costs may be insignificant to the total project cost), total amount of paving compared to existing pavement, project staging and project scoping with regard to long-range transportation goals.
 
 
 
In unique circumstances, the core team may determine there is a need to specify one pavement type over another on a project. The core team decision, which will include the concurrence of the Pavement Team member and the Design Liaison Engineer, is documented through the [[131.1 Design Exception Process|Design Exception]] process.
 
 
 
 
==Approaches and Driveways==
 
==Approaches and Driveways==
 
Refer to [[233.2 At-Grade Intersections with Stop and Yield Control#233.2.10 Driveway and Approach Pavement Design Criteria|EPG 233.2.10 Driveway and Approach Pavement Design Criteria]].
 
Refer to [[233.2 At-Grade Intersections with Stop and Yield Control#233.2.10 Driveway and Approach Pavement Design Criteria|EPG 233.2.10 Driveway and Approach Pavement Design Criteria]].
Line 127: Line 9:
 
==Shoulder Surface==
 
==Shoulder Surface==
 
[[image:Shoulder Surface Photo.jpg|right|300 px]]
 
[[image:Shoulder Surface Photo.jpg|right|300 px]]
Paved shoulders and aggregate stabilized shoulders provide a secure surface to accomodate vehicles for emergencies and other uses. Paved shoulders are an integral part of the pavement structure and are considered as part of the pavement design configuration. See [[231.4 Shoulder Width|Shoulder Width]] for additional information
+
Paved shoulders and aggregate stabilized shoulders provide a secure surface to accommodate vehicles for emergencies and other uses. Paved shoulders are an integral part of the pavement structure and are considered as part of the pavement design configuration. See [[231.4 Shoulder Width|Shoulder Width]] for additional information
 
{|style="padding: 0.3em; margin-right:5px; border:2px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="left"  
 
{|style="padding: 0.3em; margin-right:5px; border:2px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="left"  
 
|-
 
|-
Line 134: Line 16:
 
|[[:Category:350 Design for Bases and Aggregate Surfaces|EPG 350 Design for Bases and Aggregate Surfaces]]
 
|[[:Category:350 Design for Bases and Aggregate Surfaces|EPG 350 Design for Bases and Aggregate Surfaces]]
 
|}
 
|}
Shoulders on urban roadways with access control (major or minor) are to be paved. In no case will a paved or aggregate surface be used directly behind a mountable curb along the outer edge of a roadway. A curb and gutter will only be used with an anticipated posted speed less than 50 mph.
+
Shoulders on urban roadways with access control (major or minor) are to be paved. In no case will a paved or aggregate surface be used directly behind a mountable curb along the outer edge of a roadway. A curb and gutter will only be used with a posted speed less than 50 mph.
  
Currently shoulder designs are categorized as A1, A2 and A3.
+
Currently shoulder designs for new roadway construction are categorized as Type A1, A2 and A3.  The Type A1, A2 and A3 designations should not be used when adding shoulders to existing pavements, (see [[231.4 Shoulder Width#231.4.3 Shoulder Widening Projects|EPG 231.4.3 Shoulder Widening Projects]]).
  
Type A1 shoulder design is comprised of asphalt or concrete on a prepared aggregate subgrade placed the same thickness as the mainline pavement. This shoulder type should be used sparingly, in instances that can be justified such as where there is an imminent need for use of the shoulder as a lane.
+
Type A1 shoulder design is comprised of asphalt or concrete on a prepared aggregate subgrade placed the same thickness as the mainline pavement. This shoulder type is to be used sparingly, in instances that can be justified such as where there is an imminent need for use of the shoulder as a lane.
  
Type A2 shoulder design consists of asphalt, concrete or roller compacted concrete on a prepared aggregate subgrade with the final surface placed 5 ¾ in. thick. This shoulder should be used on all interstate routes and for major roadways with significant traffic.
+
Type A2 shoulder design consists of asphalt, concrete or roller compacted concrete on a prepared aggregate subgrade with the final surface placed 5 ¾ in. thick. Type A2 shoulders are used on all interstate routes and for major roadways with significant traffic.
  
Type A3 shoulder design consists of asphalt, concrete, or roller compacted concrete on a prepared aggregate subgrade with the final surface placed either 3 ¾ in. thick (asphalt) or 4 in. thick (concrete or roller compacted concrete). This shoulder should be used on major routes with relatively lower traffic volumes and on minor routes where a paved shoulder will be provided.
+
Type A3 shoulder design consists of asphalt, concrete, or roller compacted concrete on a prepared aggregate subgrade with the final surface placed either 3 ¾ in. thick (asphalt) or 4 in. thick (concrete or roller compacted concrete). This shoulder type is used on major routes (non-interstate only) with relatively lower traffic volumes and on minor routes where a paved shoulder will be provided.
  
Where a paved shoulder is provided on major routes, the full thickness of the travel way pavement should be extended laterally to a longitudinal joint either 1 ft. or 2 ft. outside the travel way. This widening should extend 2 ft. for interstate and 1 ft. for all other locations. In instances where short segments of pavement are placed, butted at each end by pavement that is not widened, approval may be obtained to omit the widening.
+
For new construction, a paved shoulder is provided on major routes, the full thickness of the travel way pavement should be extended laterally to a longitudinal joint either 1 ft. or 2 ft. outside the travel way. This widening is to extend 2 ft. for interstate and 1 ft. for all other locations. In instances where short segments of pavement are placed, butted at each end by pavement that is not widened, approval may be obtained to omit the widening.
 +
<div id="For resurfacing projects on roadways with shoulders 4"></div>
 +
For resurfacing projects on roadways with shoulders 4 feet or narrower, when shoulder improvements are also anticipated as part of the scope of work, the same asphalt surface mix used on the travelway should be extended the entire shoulder width.  This will allow for a single monolithic pavement operation for the shoulder, reducing additional lane drops and construction time.  All shoulders wider than 4 feet should have the same asphalt surface mix used on the travelway extended onto the shoulder a minimum of 18 inches. An alternate mix type may be specified beyond 18 inches when the shoulder is wider than 4 feet. This will provide a continuous surface mix for placing rumble strips/stripes. (See [[:Category:626 Rumble Strips|EPG 626 Rumble Strips]].) 
  
 
Ramp shoulders should be consistent with the mainline. For ramps with integral curbs, the shoulder material and thickness will be specified in the pavement thickness determination.
 
Ramp shoulders should be consistent with the mainline. For ramps with integral curbs, the shoulder material and thickness will be specified in the pavement thickness determination.
Line 158: Line 42:
 
Specific recommendations for cut, fill, and bridge spill fill slopes are contained in soil survey reports. For those projects on which soil survey reports have not been made, such reports with specific slope recommendations are requested from the district construction and materials engineer.
 
Specific recommendations for cut, fill, and bridge spill fill slopes are contained in soil survey reports. For those projects on which soil survey reports have not been made, such reports with specific slope recommendations are requested from the district construction and materials engineer.
  
'''Effects of Soils on Pavement Designs.''' For flexible types of pavement, bases and subbases provide uniformity of support and strength and serve to distribute the load to the underlying soil over an area greater than the contact area of the tire. The weaker or more unstable the underlying soil, the greater is the required area of load distribution, and consequently the greater the required pavement thickness. For rigid pavements, bases provide uniformity of support and a means of preventing pumping.
+
'''Effects of Soils on Pavement Designs.''' For flexible types of pavement, bases and subbases provide uniformity of support and strength and serve to distribute the load to the underlying soil over an area greater than the contact area of the tire. The weaker or more unstable the underlying soil, the greater the required area of load distribution and, consequently, the greater the required pavement thickness. For rigid pavements, bases provide uniformity of support and a means of preventing pumping.
  
 
'''Unsuitable Soils.''' Unsuitable soils are those which have unstable, non-uniform or otherwise undesirable subgrade support characteristics. Highly plastic clays may have detrimental volume change characteristics (shrink-swell) from removal of overburden or changes in moisture content. This may be a particular problem when encountered in pockets, in varying thicknesses and when transitioning from cuts to fills. Silts are susceptible to rutting and pumping if compacted wet or in proximity to available moisture and may remain susceptible to pumping and frost heave from capillary action after paving. Particular problem materials include the "underclays" found beneath coal beds in Pennsylvanian age strata and gleys or gumbotils often found associated with glacial tills. Differential settlement, rutting and fatigue cracking in pavements is common when these materials are left in the subgrade.
 
'''Unsuitable Soils.''' Unsuitable soils are those which have unstable, non-uniform or otherwise undesirable subgrade support characteristics. Highly plastic clays may have detrimental volume change characteristics (shrink-swell) from removal of overburden or changes in moisture content. This may be a particular problem when encountered in pockets, in varying thicknesses and when transitioning from cuts to fills. Silts are susceptible to rutting and pumping if compacted wet or in proximity to available moisture and may remain susceptible to pumping and frost heave from capillary action after paving. Particular problem materials include the "underclays" found beneath coal beds in Pennsylvanian age strata and gleys or gumbotils often found associated with glacial tills. Differential settlement, rutting and fatigue cracking in pavements is common when these materials are left in the subgrade.
Line 168: Line 52:
 
'''Importance of Uniformity.''' Since one key to satisfactory pavement performance is uniformity of underlying support, it is important that subgrades be composed of materials of reasonably uniform characteristics. To achieve uniformity of subgrade support, selection of borrow areas, earthwork balancing, and cross hauling are items which are given consideration including use of contract furnished borrow (embankment in place).
 
'''Importance of Uniformity.''' Since one key to satisfactory pavement performance is uniformity of underlying support, it is important that subgrades be composed of materials of reasonably uniform characteristics. To achieve uniformity of subgrade support, selection of borrow areas, earthwork balancing, and cross hauling are items which are given consideration including use of contract furnished borrow (embankment in place).
  
'''Compressible Foundations.''' Compressible foundations, often encountered in stream bottoms, are normally detected during the soil survey and are referred to the Construction and Materials Division for detailed investigation. This investigation will usually include undisturbed foundation soil sampling, testing and analyses to determine settlement and strength properties. Compressible foundations may be unstable or only marginally stable during the consolidation process and application of embankment loads must be carefully monitored and controlled. Use is often made of restricted loading rates, construction delays, embankment control stakes, pore pressure measurement devices, and flattened or bermed slopes. Where settlements are expected to be high and of very long term duration, vertical sand or wick drains may be used to accelerate settlement but must be used with great care since they may contribute to stability problems. Separate paving and grading projects may be especially helpful in mitigating some of the settlement and stability problems associated with compressible foundations.
+
'''Compressible Foundations.''' Compressible foundations, often encountered in stream bottoms, are normally detected during the soil survey and are referred to the Construction and Materials Division for detailed investigation. This investigation will usually include undisturbed foundation soil sampling, testing and analyses to determine settlement and strength properties. Compressible foundations may be unstable or only marginally stable during the consolidation process and application of embankment loads must be carefully monitored and controlled. Use is often made of restricted loading rates, construction delays, embankment control stakes, pore pressure measurement devices, and flattened or bermed slopes. Where settlements are expected to be high and of very long-term duration, vertical sand or wick drains may be used to accelerate settlement but must be used with great care since they may contribute to stability problems. Separate paving and grading projects may be especially helpful in mitigating some of the settlement and stability problems associated with compressible foundations.
  
 
'''Transition Zones.''' Where subgrade support changes from a soil foundation to a solid rock foundation, special precaution is taken to guard against pavement failure. Transition zones of varying depth are feathered out in each direction longitudinally for a distance of approximately 30 to 40 ft. (9.0 to 12.0 m). The transition zone is backfilled with materials specified in the standard specifications for backfilling of undergraded areas. This eliminates or minimizes uneven stresses which may result in pavement failure. Approximate station limits of transition zones are shown on the plans.
 
'''Transition Zones.''' Where subgrade support changes from a soil foundation to a solid rock foundation, special precaution is taken to guard against pavement failure. Transition zones of varying depth are feathered out in each direction longitudinally for a distance of approximately 30 to 40 ft. (9.0 to 12.0 m). The transition zone is backfilled with materials specified in the standard specifications for backfilling of undergraded areas. This eliminates or minimizes uneven stresses which may result in pavement failure. Approximate station limits of transition zones are shown on the plans.
Line 175: Line 59:
  
 
==Temporary Connections and Bypasses==
 
==Temporary Connections and Bypasses==
A temporary bypass should normally be designed as an optional pavement. The thickness should be determined by the Pavement Section in the Construction and Materials Division, but for scoping purposes can be estimated at 8 inches for Hot Mix Asphalt (HMA) and 7 inches for Portland Cement Concrete (PCC). The optional HMA pavement design should consist of 1 ¾ inches of [[:Category:450 Bituminous Pavement Design|BP-1 mix with PG 64-22 binder]] on whatever the required remaining structural thickness is of PMBB PG 64-22. The optional PCC pavement design should be sawed at the tranverse joints, but not doweled. For a bypass duration less than one year the pavement should be placed directly on the subgrade, with the subgrade being compacted in accordance with [http://www.modot.state.mo.us/business/standards_and_specs/Sec0203.pdf Sec 203.4] of the standard specifications. If the bypass is to be used for more than one construction season, i.e., in place over winter months, the pavement may need to be placed on Type 1 aggregate base, compacted in accordance with Sec 203.4 of the standard specifications, over the compacted subgrade. In cases where the bypass pavement will be incorporated into a permanent roadway pavement, the bypass should be designed to the same thickness and alternate type as the proposed pavement. For truck traffic less than 10 a day and if dust can be tolerated, a 2 in. (50 mm) thickness of gravel, crushed stone, or chat may be used for the temporary bypass.
+
A temporary bypass should normally be designed as an optional pavement. The thickness should be determined by the Pavement Section in the Construction and Materials Division, but for scoping purposes can be estimated at 8 inches for Hot Mix Asphalt (HMA) and 7 inches for Portland Cement Concrete (PCC). The optional HMA pavement design should consist of 1 ¾ inches of [[:Category:450 Bituminous Pavement Design|BP-1 mix with PG 64-22 binder]] on whatever the required remaining structural thickness is of PMBB PG 64-22. The optional PCC pavement design should be sawed at the transverse joints, but not doweled. For a bypass duration less than one year the pavement should be placed directly on the subgrade, with the subgrade being compacted in accordance with [http://www.modot.org/business/standards_and_specs/SpecbookEPG.pdf#page=5 Sec 203.4] of the standard specifications. If the bypass is to be used for more than one construction season, i.e., in place over winter months, the pavement may need to be placed on Type 1 aggregate base, compacted in accordance with Sec 203.4 of the standard specifications, over the compacted subgrade. In cases where the bypass pavement will be incorporated into a permanent roadway pavement, the bypass should be designed to the same thickness and alternate type as the proposed pavement. For truck traffic less than 10 a day and if dust can be tolerated, a 2 in. (50 mm) thickness of gravel, crushed stone, or chat may be used for the temporary bypass.
  
 
==Thickness Determination==
 
==Thickness Determination==
 +
[[image:thickness determination asphalt.jpg|right|250px]]
 +
 +
===Major Roads===
 +
 +
The Construction and Materials Division will determine the pavement thickness for all projects on major roads.
 +
 +
===Minor Roads===
 
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="right"  
 
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="right"  
 
|-   
 
|-   
 
|'''Forms'''
 
|'''Forms'''
 
|-
 
|-
|[http://wwwi/intranet/cm/materials/documents/PTSSubmittalForm_000.doc Pavement Type Selection Submittal Information]
+
|[https://epg.modot.org/forms/CM/Pavement_Type_Selection_Submittal.pdf Pavement Type Selection Submittal Information]
 
|}
 
|}
 +
For spot improvements, such as widening for turning lanes or for short realignments, a pavement thickness design by Construction and Materials is not always required.  The Optional Pavement Design chart below should be used to determine whether or not a pavement design is required.  If no pavement design is required, optional pavement choices should still be provided unless there is a valid reason for an exception.
  
===Major Roads===
+
The chart includes minimum pavement thicknesses for approaches within 500 ft. of a bridge since that portion of pavement usually will not receive the benefit of future resurfacings. 
 +
 
 +
The first 20 ft. of pavement on-grade adjacent to a bridge abutment is always reserved as a bridge design feature.  See [[:Category:503 Bridge Approach Slabs|EPG 503 Bridge Approach Slab]] for more information. The contractor will be given the option of selecting the material type for the  Bridge Approach Slab (Minor) which shall be either an optional concrete bridge approach slab (Min. 12” reinforced PCC) or an optional asphalt (Min. 12” HMA) thickened slab consisting of either bituminous pavement (BP) or Superpave (SP) mix, as determined appropriate for the roadway truck volume.
  
[[image:thickness determination asphalt.jpg|right|250px]]
+
Optional pavement details (pavement type and all lift thicknesses) should be included on the typical section plan sheets.
The Construction and Materials Division will determine the pavement thickness for all projects on major roads. During early scoping, pavement thicknesses for conceptual design and estimating purposes may be obtained from the [[#Pavement Design for Scoping|ME (Mechanistic-Empirical) Design Table for Project Scoping]].
 
  
===Minor Roads===
+
====Optional Pavement Design for Minor Roads====
  
On minor roads, for spot improvements, such as pavement replacement less than 0.5 miles in length adjacent to bridge replacements, widening for turning lanes for a turning movement that has less than 1000 vehicles per day or for short realignments, a pavement thickness determination by Construction and Materials is not required. The new pavement thickness is to be equivalent to the existing pavement thickness on 4 in. of aggregate base or 5 ¾ in. on 4 in. of aggregate base, whichever is greater. For these projects, the new pavement is to consist of asphalt (cold mix or hot mix) or concrete pavement, at the contractor’s option. If the AADT is between 1000 and 2000, the cold mix may be eliminated. If the AADT is greater than 2000, cold mix is not allowed.
+
All selections below should include a 4” Type 1 aggregate base.
  
On minor roads, for improvements greater than 0.5 miles in length or for widening for turning lanes for a turning movement with more than 1000 vehicles per day, the Construction and Materials Division will make a pavement thickness determination. During early scoping, pavement thicknesses for conceptual design and estimating purposes may be obtained from the [[#Pavement Design for Scoping|ME (Mechanistic-Empirical) Design Table for Project Scoping]].
+
{| border="1" class="wikitable" style="margin: 1em auto 1em auto" style="text-align:left"
 +
|+
 +
!style="background:#BEBEBE" | !!style="background:#BEBEBE" |Minor Roads ≤ 1000 AADT!! style="background:#BEBEBE" |Minor Roads > 1000 AADT
 +
|-
 +
| ||colspan="2" align="center"| '''Roadways'''
 +
|-
 +
| ≤ 0.5 mile|| 7” HMA / 7” JPCP|| Pavement design determined by Const & Mtrls Division
 +
|-
 +
|> 0.5 mile|| Pavement design determined by Const. & Mtrls. Division|| Pavement design determined by Const & Mtrls Division
 +
|-
 +
| ||colspan="2" align="center"| '''Bridge Approaches'''
 +
|-
 +
|From fill face to 20’|| Bridge Approach Slab (Minor)<br/>12” Min. HMA or Reinf. PCC ||Bridge Approach Slab (Minor)<br/>12” Min. HMA or Reinf. PCC
 +
|-
 +
|From 20’ to 500’ ||10” HMA / 8” JPCP ||10” HMA / 8” PCCP or pavement design, whichever is greater
 +
|-
 +
|Beyond 500’|| Use roadway design above|| Use roadway design above
 +
|}
  
 
===Aggregate Surfaces===
 
===Aggregate Surfaces===
Line 202: Line 112:
 
===Pavement Thickness Request===
 
===Pavement Thickness Request===
 
[[image:thickness determination concrete.jpg|right|250px]]
 
[[image:thickness determination concrete.jpg|right|250px]]
A completed [http://wwwi/intranet/cm/materials/documents/PTSSubmittalForm_000.doc Pavement Type Selection Submittal Information] form is submitted to the Pavement Section in the Construction and Materials Division, with a copy to the Design Division, during preliminary design. The pavement thickness determination will include the aggregate base and underdrainage design. The pavement thickness request is to include the following information:
+
A completed [https://epg.modot.org/forms/CM/Pavement_Type_Selection_Submittal.pdf Pavement Type Selection Submittal Information] form is submitted to the Pavement Section in the Construction and Materials Division, with a copy to the Design Division, during preliminary design. The pavement thickness determination will include the aggregate base and underdrainage design. The pavement thickness request is to include the following information:
  
 
*A description of the existing and proposed design template for the mainline, ramps and any other roadways associated with the project (appurtenances) requiring a pavement structural design
 
*A description of the existing and proposed design template for the mainline, ramps and any other roadways associated with the project (appurtenances) requiring a pavement structural design
Line 216: Line 126:
 
Although final decisions regarding pavement thickness are made by the Construction and Materials Division, the districts may make specific recommendations regarding the principal roadway, outer roadway, service road, or temporary bypass pavement thickness.
 
Although final decisions regarding pavement thickness are made by the Construction and Materials Division, the districts may make specific recommendations regarding the principal roadway, outer roadway, service road, or temporary bypass pavement thickness.
  
===Pavement Design for Scoping===
 
 
During project scoping for conceptual estimates only, a pavement thickness from the following table may be used.  This table is not used for preliminary or final design.
 
 
[[Image:METable for Scoping.gif|680 px|center]]
 
  
  

Latest revision as of 08:57, 22 October 2021

Alternate and Optional Pavement

Refer to EPG 242 Optional and Alternate Pavement Designs.

Approaches and Driveways

Refer to EPG 233.2.10 Driveway and Approach Pavement Design Criteria.

Asphalt Over Rubblized Pavement

Refer to EPG 450.8 Asphalt Over Rubblized Pavement.

Shoulder Surface

Shoulder Surface Photo.jpg

Paved shoulders and aggregate stabilized shoulders provide a secure surface to accommodate vehicles for emergencies and other uses. Paved shoulders are an integral part of the pavement structure and are considered as part of the pavement design configuration. See Shoulder Width for additional information

Additional Information
EPG 350 Design for Bases and Aggregate Surfaces

Shoulders on urban roadways with access control (major or minor) are to be paved. In no case will a paved or aggregate surface be used directly behind a mountable curb along the outer edge of a roadway. A curb and gutter will only be used with a posted speed less than 50 mph.

Currently shoulder designs for new roadway construction are categorized as Type A1, A2 and A3. The Type A1, A2 and A3 designations should not be used when adding shoulders to existing pavements, (see EPG 231.4.3 Shoulder Widening Projects).

Type A1 shoulder design is comprised of asphalt or concrete on a prepared aggregate subgrade placed the same thickness as the mainline pavement. This shoulder type is to be used sparingly, in instances that can be justified such as where there is an imminent need for use of the shoulder as a lane.

Type A2 shoulder design consists of asphalt, concrete or roller compacted concrete on a prepared aggregate subgrade with the final surface placed 5 ¾ in. thick. Type A2 shoulders are used on all interstate routes and for major roadways with significant traffic.

Type A3 shoulder design consists of asphalt, concrete, or roller compacted concrete on a prepared aggregate subgrade with the final surface placed either 3 ¾ in. thick (asphalt) or 4 in. thick (concrete or roller compacted concrete). This shoulder type is used on major routes (non-interstate only) with relatively lower traffic volumes and on minor routes where a paved shoulder will be provided.

For new construction, a paved shoulder is provided on major routes, the full thickness of the travel way pavement should be extended laterally to a longitudinal joint either 1 ft. or 2 ft. outside the travel way. This widening is to extend 2 ft. for interstate and 1 ft. for all other locations. In instances where short segments of pavement are placed, butted at each end by pavement that is not widened, approval may be obtained to omit the widening.

For resurfacing projects on roadways with shoulders 4 feet or narrower, when shoulder improvements are also anticipated as part of the scope of work, the same asphalt surface mix used on the travelway should be extended the entire shoulder width. This will allow for a single monolithic pavement operation for the shoulder, reducing additional lane drops and construction time. All shoulders wider than 4 feet should have the same asphalt surface mix used on the travelway extended onto the shoulder a minimum of 18 inches. An alternate mix type may be specified beyond 18 inches when the shoulder is wider than 4 feet. This will provide a continuous surface mix for placing rumble strips/stripes. (See EPG 626 Rumble Strips.)

Ramp shoulders should be consistent with the mainline. For ramps with integral curbs, the shoulder material and thickness will be specified in the pavement thickness determination.

Minor road shoulders should be aggregate stabilized except when maintenance or safety concerns (e.g., edge drop off, high run-off road occurrence) justify an alternate treatment. When conditions warrant, a 1 or 2 ft. lateral extension of the mainline pavement should be considered as an initial option. If paving the remaining width of shoulder is justified, the shoulder should consist of the Type A3 shoulder design.

Soil Characteristics

Soil Characteristics.JPG

Since the performance and durability of pavement primarily depends upon the support provided by the underlying subgrade materials, it might be said that soil is the most important of all materials used in highway construction. The achievement of an adequate pavement structure requires a close coordination of soil survey, design, and construction to produce the best possible combination of the most economically available materials. The engineering properties of soil, probably more than any other factor, except drainage, influence the service and performance of all types of roads.

Soil Surveys. In order that all pertinent soils information be made available for proper design use, soil surveys and cut classification investigations are made by district soils and geology technologists for most projects. Basic soils information which can easily be understood and used by those who have not specialized in soil science is furnished by the Construction and Materials Division.

Specific recommendations for cut, fill, and bridge spill fill slopes are contained in soil survey reports. For those projects on which soil survey reports have not been made, such reports with specific slope recommendations are requested from the district construction and materials engineer.

Effects of Soils on Pavement Designs. For flexible types of pavement, bases and subbases provide uniformity of support and strength and serve to distribute the load to the underlying soil over an area greater than the contact area of the tire. The weaker or more unstable the underlying soil, the greater the required area of load distribution and, consequently, the greater the required pavement thickness. For rigid pavements, bases provide uniformity of support and a means of preventing pumping.

Unsuitable Soils. Unsuitable soils are those which have unstable, non-uniform or otherwise undesirable subgrade support characteristics. Highly plastic clays may have detrimental volume change characteristics (shrink-swell) from removal of overburden or changes in moisture content. This may be a particular problem when encountered in pockets, in varying thicknesses and when transitioning from cuts to fills. Silts are susceptible to rutting and pumping if compacted wet or in proximity to available moisture and may remain susceptible to pumping and frost heave from capillary action after paving. Particular problem materials include the "underclays" found beneath coal beds in Pennsylvanian age strata and gleys or gumbotils often found associated with glacial tills. Differential settlement, rutting and fatigue cracking in pavements is common when these materials are left in the subgrade.

The minimum standard treatment of clay soils of moderate plasticity and average volume change potential includes cut compaction and compaction at moisture contents in excess of the optimum in the upper part of the subgrade. Silty soils should be compacted at moisture contents below the optimum. The standard specifications provide for both these measures.

Consideration may be given to various forms of subgrade stabilization using chemical (lime, flyash, lime kiln dust, or other) or geosynthetic materials. However, extremely bad materials, such as underclay, gley or pockets of high plasticity clay, should be replaced with select material after being undergraded and wasted or buried in non-critical areas.

Importance of Uniformity. Since one key to satisfactory pavement performance is uniformity of underlying support, it is important that subgrades be composed of materials of reasonably uniform characteristics. To achieve uniformity of subgrade support, selection of borrow areas, earthwork balancing, and cross hauling are items which are given consideration including use of contract furnished borrow (embankment in place).

Compressible Foundations. Compressible foundations, often encountered in stream bottoms, are normally detected during the soil survey and are referred to the Construction and Materials Division for detailed investigation. This investigation will usually include undisturbed foundation soil sampling, testing and analyses to determine settlement and strength properties. Compressible foundations may be unstable or only marginally stable during the consolidation process and application of embankment loads must be carefully monitored and controlled. Use is often made of restricted loading rates, construction delays, embankment control stakes, pore pressure measurement devices, and flattened or bermed slopes. Where settlements are expected to be high and of very long-term duration, vertical sand or wick drains may be used to accelerate settlement but must be used with great care since they may contribute to stability problems. Separate paving and grading projects may be especially helpful in mitigating some of the settlement and stability problems associated with compressible foundations.

Transition Zones. Where subgrade support changes from a soil foundation to a solid rock foundation, special precaution is taken to guard against pavement failure. Transition zones of varying depth are feathered out in each direction longitudinally for a distance of approximately 30 to 40 ft. (9.0 to 12.0 m). The transition zone is backfilled with materials specified in the standard specifications for backfilling of undergraded areas. This eliminates or minimizes uneven stresses which may result in pavement failure. Approximate station limits of transition zones are shown on the plans.

Pockets of Unsuitable Material. Where pockets of heavy plastic clay or other unsuitable materials are encountered between pinnacles of solid rock, the unsuitable material is removed to required depth and backfilled with the material specified in the Standard Specification for backfilling of undergraded areas. If it is anticipated that such conditions will be encountered, approximate quantities for removal and backfill are shown on the plans. In areas known to have pinnacles of rock, it is extremely important to study the cut classification information in order to avoid large overruns of Class C excavation during construction.

Temporary Connections and Bypasses

A temporary bypass should normally be designed as an optional pavement. The thickness should be determined by the Pavement Section in the Construction and Materials Division, but for scoping purposes can be estimated at 8 inches for Hot Mix Asphalt (HMA) and 7 inches for Portland Cement Concrete (PCC). The optional HMA pavement design should consist of 1 ¾ inches of BP-1 mix with PG 64-22 binder on whatever the required remaining structural thickness is of PMBB PG 64-22. The optional PCC pavement design should be sawed at the transverse joints, but not doweled. For a bypass duration less than one year the pavement should be placed directly on the subgrade, with the subgrade being compacted in accordance with Sec 203.4 of the standard specifications. If the bypass is to be used for more than one construction season, i.e., in place over winter months, the pavement may need to be placed on Type 1 aggregate base, compacted in accordance with Sec 203.4 of the standard specifications, over the compacted subgrade. In cases where the bypass pavement will be incorporated into a permanent roadway pavement, the bypass should be designed to the same thickness and alternate type as the proposed pavement. For truck traffic less than 10 a day and if dust can be tolerated, a 2 in. (50 mm) thickness of gravel, crushed stone, or chat may be used for the temporary bypass.

Thickness Determination

Thickness determination asphalt.jpg

Major Roads

The Construction and Materials Division will determine the pavement thickness for all projects on major roads.

Minor Roads

Forms
Pavement Type Selection Submittal Information

For spot improvements, such as widening for turning lanes or for short realignments, a pavement thickness design by Construction and Materials is not always required. The Optional Pavement Design chart below should be used to determine whether or not a pavement design is required. If no pavement design is required, optional pavement choices should still be provided unless there is a valid reason for an exception.

The chart includes minimum pavement thicknesses for approaches within 500 ft. of a bridge since that portion of pavement usually will not receive the benefit of future resurfacings.

The first 20 ft. of pavement on-grade adjacent to a bridge abutment is always reserved as a bridge design feature. See EPG 503 Bridge Approach Slab for more information. The contractor will be given the option of selecting the material type for the Bridge Approach Slab (Minor) which shall be either an optional concrete bridge approach slab (Min. 12” reinforced PCC) or an optional asphalt (Min. 12” HMA) thickened slab consisting of either bituminous pavement (BP) or Superpave (SP) mix, as determined appropriate for the roadway truck volume.

Optional pavement details (pavement type and all lift thicknesses) should be included on the typical section plan sheets.

Optional Pavement Design for Minor Roads

All selections below should include a 4” Type 1 aggregate base.

Minor Roads ≤ 1000 AADT Minor Roads > 1000 AADT
Roadways
≤ 0.5 mile 7” HMA / 7” JPCP Pavement design determined by Const & Mtrls Division
> 0.5 mile Pavement design determined by Const. & Mtrls. Division Pavement design determined by Const & Mtrls Division
Bridge Approaches
From fill face to 20’ Bridge Approach Slab (Minor)
12” Min. HMA or Reinf. PCC
Bridge Approach Slab (Minor)
12” Min. HMA or Reinf. PCC
From 20’ to 500’ 10” HMA / 8” JPCP 10” HMA / 8” PCCP or pavement design, whichever is greater
Beyond 500’ Use roadway design above Use roadway design above

Aggregate Surfaces

Aggregate surfaces will not be used except on very low volume or dead end road applications, such as outer roads, temporary bypasses and roadways to be turned over to another agency. In these circumstances an aggregate surface may be appropriate if dust can be tolerated. For these situations a minimum 2 in. thickness of gravel, crushed stone, or chat may be used.

Pavement Thickness Request

Thickness determination concrete.jpg

A completed Pavement Type Selection Submittal Information form is submitted to the Pavement Section in the Construction and Materials Division, with a copy to the Design Division, during preliminary design. The pavement thickness determination will include the aggregate base and underdrainage design. The pavement thickness request is to include the following information:

  • A description of the existing and proposed design template for the mainline, ramps and any other roadways associated with the project (appurtenances) requiring a pavement structural design
  • The existing pavement structure on each end of the new pavement
  • Special conditions prevalent within the project area that may affect design consideration.
  • Due date the pavement thickness determination is needed to maintain the project development schedule.
  • Traffic data (construction year AADT, truck percentage, truck classification distribution (if available), and annual growth rate).
  • Soils survey, including data for P.I., gradation, and depth of water table.
  • Location sketch and length of each new pavement to be designed, including log mile reference and exceptions

The district is to request a review of the study for project changes, including (1) delays beyond the anticipated construction, (2) traffic changes, (3) section expansion or reduction, or (4) a revised typical section or other standards revisions, etc.

Although final decisions regarding pavement thickness are made by the Construction and Materials Division, the districts may make specific recommendations regarding the principal roadway, outer roadway, service road, or temporary bypass pavement thickness.