Difference between revisions of "Category talk:203 Roadway and Drainage Excavation, Embankment and Compaction"
Jump to navigation
Jump to search
(Question about borrow areas.) |
(address question.) |
||
Line 6: | Line 6: | ||
--[[User:Martik2|Martik2]] 13:06, 25 February 2009 (CST) | --[[User:Martik2|Martik2]] 13:06, 25 February 2009 (CST) | ||
+ | |||
+ | |||
+ | '''Sam Masters''': You are correct. Presently, the department normally specifies contractor furnished borrow. 203.2.3.1.2 will be corrected (as will the "Borrow and Excess Material" article) to reflect this information. |
Latest revision as of 14:26, 25 February 2009
203.2.3.1.2 Borrow or Excess Material States:
The plans shall designate commission furnished borrow areas for all projects where suitable borrow areas can be provided.
Is this correct? I thought the department had moved toward contractor furnished borrow.
--Martik2 13:06, 25 February 2009 (CST)
Sam Masters: You are correct. Presently, the department normally specifies contractor furnished borrow. 203.2.3.1.2 will be corrected (as will the "Borrow and Excess Material" article) to reflect this information.