Difference between revisions of "Category:170 Maintenance Activity Planning Guidelines"
m (updating links to pdfs) |
m (→Index of Printable Planning Guides: updating links to planning guides) |
||
Line 148: | Line 148: | ||
| rowspan="5" | '''R319 Pipe Culvert Repairs (LF)''' || <div id="R319 Pipe Culvert Repairs (LF)"></div> '''Clean & Repair Pipe & Box Culverts''' | | rowspan="5" | '''R319 Pipe Culvert Repairs (LF)''' || <div id="R319 Pipe Culvert Repairs (LF)"></div> '''Clean & Repair Pipe & Box Culverts''' | ||
|- | |- | ||
− | |[ | + | |[https://epg.modot.org/forms/general_files/MT/R319_update-install_pipe_liners.pdf Install Pipe Liners (LF)] |
|- | |- | ||
− | | [ | + | | [https://epg.modot.org/forms/general_files/MT/R319_update-clean_and_repair_pipe_culverts.pdf|Pipe Culverts] (Also See [[:Category:773 Pipe, Box Culvert and Miscellaneous Drainage Maintenance|Pipe, Box Culvert and Miscellaneous Drainage Maintenance]]) |
|- | |- | ||
− | | [ | + | | [https://epg.modot.org/forms/general_files/MT/R319_update-clean_and_repair_box_culverts.pdf Box Culverts] (Also See [[:Category:773 Pipe, Box Culvert and Miscellaneous Drainage Maintenance|Pipe, Box Culvert and Miscellaneous Drainage Maintenance]]) |
|- | |- | ||
− | | [ | + | | [https://epg.modot.org/forms/general_files/MT/R319_update-replace_pipe_and_box_culverts.pdf Replace Pipe & Box Culverts (LF)] (Also See [[:Category:773 Pipe, Box Culvert and Miscellaneous Drainage Maintenance|Pipe, Box Culvert and Miscellaneous Drainage Maintenance]]) |
|- | |- | ||
− | | '''R31B Sweeping (LM)''' || [ | + | | '''R31B Sweeping (LM)''' || [https://epg.modot.org/forms/general_files/MT/R31B_update-sweeping.pdf Sweeping (LM)] (For routine flushing of bridge decks see [[771.2 Bridge Cleaning and Flushing|Bridge Cleaning and Flushing]]) |
|- | |- | ||
| rowspan="3" | '''R31C Chip Sealing (LM)''' || '''Chip Sealing''' | | rowspan="3" | '''R31C Chip Sealing (LM)''' || '''Chip Sealing''' |
Revision as of 16:53, 27 February 2024
Contents
Introduction
Safety Video |
Safety is My Story |
Patching Roads |
Additional Information |
Safe Lifting |
The original Maintenance Planning Guide was developed and published in 1989. The purpose of that manual was to provide maintenance managers with a quick reference for performing most maintenance functions. It included scheduling forms, traffic control guidelines, function codes, commodity codes and a sample crew report. Since the original publication the guide has been updated to meet the needs of MoDOT.
This article provides each manager with a list of recommended equipment and materials to use for each function as well as a recommended procedure for that function. The guidelines also have safety reminders and schedules to help managers plan for the best time of year to perform each function.
This article is intended to be an accurate source of information and a tool that maintenance managers will use to better organize, plan and be more productive leaders.
Reference the Missouri Standard Plans and Missouri Standard Specifications for Highway Construction for performance details on many of the maintenance function planning guidelines. It is the intent of the department to provide as good of a finished product with Maintenance forces as it does by contract methods.
Recommended materials: When purchasing recommended material, refer to guidance for maintenance materials. Guidance for these materials also refers to the Current General Services Specifications (MGS) by Subject for each of the various maintenance materials.
The Highway Maintenance Tables in the appendix were provided to MoDOT through the Local Technical Assistance Program of the Michigan Tech Transportation Institute at Michigan Technological University in Houghton, Michigan.
Rainy Day Activities
Printable Version |
Rainy Day Activities |
- Check roadway surface drainage
- Check bridge surface for ponding
- Check bridges and box culverts for drift and erosion
- Flush bridge decks
- Check culverts and culvert pipes
- Check drain basins on bridges
- Check high water locations
- Check, clean and repair equipment
- Clean and repair buildings and grounds
- Blade driveways, entrances, shoulders and mailbox turnouts
- Check signs
- Work on special projects
- Clean abutment caps on bridges
- Cut and treat brush and vines under bridges
- Conduct equipment and safety trainings
Work Scheduling Guidelines
Printable Version |
Work Scheduling Guide |
Index of Printable Planning Guides
Highway Maintenance Tables and Conversion Factors
The Highway Maintenance Tables and Conversion Factors contain helpful tables and conversion factors that aid in volumetric and weight measurements needed in maintenance activities.