[[104.3 Project Scoping|Project scoping]] can be defined as the set of design parameters that precisely satisfy the purpose and need of the project. A poorly identified scope that is broader than the purpose and need will result in an unnecessarily high project budget and lengthy schedule, while a scope that falls short will yield a project that accomplishes little of significance.  Further, a construction program based on poorly scoped projects will eventually fragment, whether by expanding the scope to meet the need during the design process or through field adjustment to correct errors and additional needs during construction.
 
[[104.3 Project Scoping|Project scoping]] can be defined as the set of design parameters that precisely satisfy the purpose and need of the project. A poorly identified scope that is broader than the purpose and need will result in an unnecessarily high project budget and lengthy schedule, while a scope that falls short will yield a project that accomplishes little of significance.  Further, a construction program based on poorly scoped projects will eventually fragment, whether by expanding the scope to meet the need during the design process or through field adjustment to correct errors and additional needs during construction.
  
When transportation needs arise, planning staff will prioritize them and present them to the project manager, marking the commencement of project development.  The project manager will then assemble the core team and begin to analyze the need in search of a solution.  As development proceeds, more and more aspects of the project will become apparent and the core [[104.2 Scoping Team|team]], acting through the project manager, will adjust the scope accordingly.
+
When transportation needs arise, planning staff will prioritize them and present them to the project manager, marking the commencement of project development.  The project manager will then assemble the core team and begin to analyze the need in search of a solution.  As development proceeds, more and more aspects of the project will become apparent and the core team, acting through the project manager, will adjust the scope accordingly.
  
 
The complete project scoping process involves determining the root causes of the need, developing a range of possible solutions to address the need, choosing the best solution, setting the physical limits of the project, accurately estimating the cost of the project, and forecasting the [[104.4 Timeline|timeline]] and delivery schedule of the project.  The core team will use available data, meetings, field checks and [[104.8 Public Involvement in Project Scoping|public input]] to accomplish these tasks.
 
The complete project scoping process involves determining the root causes of the need, developing a range of possible solutions to address the need, choosing the best solution, setting the physical limits of the project, accurately estimating the cost of the project, and forecasting the [[104.4 Timeline|timeline]] and delivery schedule of the project.  The core team will use available data, meetings, field checks and [[104.8 Public Involvement in Project Scoping|public input]] to accomplish these tasks.
Line 17: Line 17:
 
When the appropriate level of confidence in the scope has been reached there is a point of concurrence where the proposed scope is submitted for [[104.10 Management Concurrence|management concurrence]] as to whether or not it addresses the original need.  The level of concurrence sought is dependant upon the nature and complexity of the project.  Right of way and construction funds, as well as the delivery date, will only be publicly committed to a project subsequent to this approval and after having gone through the project prioritization process.
 
When the appropriate level of confidence in the scope has been reached there is a point of concurrence where the proposed scope is submitted for [[104.10 Management Concurrence|management concurrence]] as to whether or not it addresses the original need.  The level of concurrence sought is dependant upon the nature and complexity of the project.  Right of way and construction funds, as well as the delivery date, will only be publicly committed to a project subsequent to this approval and after having gone through the project prioritization process.
  
This article also provides guidelines for [[104.1 Scope of Work|scope of work]], [[104.5 Completion of Scoping|completion of scoping]], [[104.6 Items Required to be Considered and Addressed|items required to be considered and addressed]],  [[104.9 Environmental Considerations|environmental considerations]], [[104.11 Project Scoping Memorandum|project scoping memorandum]], [[104.12 Project Scoping Checklists|project scoping checklists]] and [[104.13 Scope Changes|scope changes]].
+
This article also provides guidelines for [[104.5 Completion of Scoping|completion of scoping]], [[104.6 Items Required to be Considered and Addressed|items required to be considered and addressed]],  [[104.9 Environmental Considerations|environmental considerations]], [[104.11 Project Scoping Memorandum|project scoping memorandum]], [[104.12 Project Scoping Checklists|project scoping checklists]] and [[104.13 Scope Changes|scope changes]].

Revision as of 15:21, 18 December 2006

Related Information
MoDOT's STIP website


This section covers the initial steps necessary to identify transportation needs, properly scope solutions to those needs and develop commitments for inclusion in the Statewide Transportation Improvement Program (STIP). Guidelines are also included for the preparation of appropriate project cost estimates at various milestones and the required documentation of those estimates.

Project scoping can be defined as the set of design parameters that precisely satisfy the purpose and need of the project. A poorly identified scope that is broader than the purpose and need will result in an unnecessarily high project budget and lengthy schedule, while a scope that falls short will yield a project that accomplishes little of significance. Further, a construction program based on poorly scoped projects will eventually fragment, whether by expanding the scope to meet the need during the design process or through field adjustment to correct errors and additional needs during construction.

When transportation needs arise, planning staff will prioritize them and present them to the project manager, marking the commencement of project development. The project manager will then assemble the core team and begin to analyze the need in search of a solution. As development proceeds, more and more aspects of the project will become apparent and the core team, acting through the project manager, will adjust the scope accordingly.

The complete project scoping process involves determining the root causes of the need, developing a range of possible solutions to address the need, choosing the best solution, setting the physical limits of the project, accurately estimating the cost of the project, and forecasting the timeline and delivery schedule of the project. The core team will use available data, meetings, field checks and public input to accomplish these tasks.

When the appropriate level of confidence in the scope has been reached there is a point of concurrence where the proposed scope is submitted for management concurrence as to whether or not it addresses the original need. The level of concurrence sought is dependant upon the nature and complexity of the project. Right of way and construction funds, as well as the delivery date, will only be publicly committed to a project subsequent to this approval and after having gone through the project prioritization process.

This article also provides guidelines for completion of scoping, items required to be considered and addressed, environmental considerations, project scoping memorandum, project scoping checklists and scope changes.