User:Hoskir/Revision Request 4213

From Engineering Policy Guide
Jump to navigation Jump to search

REVISION REQUEST 4213

copy only 109.12

The primary purpose of a change order is to document a supplemental change to the contract. The official definition, as stated in Sec 101, is as follows:

Change Order - A written order from the engineer to the contractor, as authorized by the contract, directing changes in the work as made necessary or desirable by unforeseen conditions or events discovered or occurring during the progress of the work.

The second most primary purpose of the change order process is to ensure proper authority has been granted before proceeding with revisions in quantities or changes in scope of work, design concept, time or specifications. Changes in scope should be limited to the original intent, purpose and limits (length and width) of the job. In instances where proposed changes in scope go beyond these original job parameters, the change order shall be considered a major change order (Sequence 4). Significant scope changes require the State Construction and Materials Engineer to discuss the requested changes with the Asst. Chief Engineer prior to granting approval.

Change orders must have approval at all required levels before the work proceeds. Exceptions are granted for routine or minor changes, or emergency revisions for which verbal approval has been granted. In rare cases it may be necessary to proceed with emergency measures without prior approval. In such cases, verbal approval should be sought as soon as practicable. Indicate in the DWR remarks the name of the individual who provided verbal approval. For change orders that provide payment for additional work, all attempts should be made to complete the process promptly so that the contractor can be compensated at the end of the pay period in which the work was performed.

Design Changes - When the change order is a result of a design change, all appropriate design criteria should be reviewed in coordination with the Transportation Project Manager. If the design criteria cannot be met, a Design Exception is required. See EPG 131.1.4.

Environmental Change Orders - Any design changes that include disturbance of new areas on the project, or that include any other unplanned environmental impacts, should be reviewed by the Project Manager to determine if a request for environmental services is necessary prior to implementation.

Job Order Contract Change Orders - Job Order Contracts have unique contract terms that limit spending to a budgeted amount and often include pre-approved time extensions. Reference EPG 147.3.9 Change Order Approvals for additional guidance on administration of change orders for Job Order Contracts.




Copy all of 131.1

131.1.1 When to Complete a Design Exception

Forms
Design Exception Information Form
Vertical Clearance Design Exception Coordination with SDDCTEA

A design exception documents design elements of an improvement that vary from general guidance on engineering policy. In most cases, the need for an exception results from an inability to reasonably meet the design criteria. The determination to approve a project design that does not conform to the minimum criteria is to be made only after due consideration is given to all project conditions such as maximum service and safety benefits for the dollar invested, compatibility with adjacent sections of roadway and the probable time before reconstruction of the section due to increased traffic demands or changed conditions.

An approved exception documents the engineering-based determination that variance from MoDOT’s published engineering policy is necessary and appropriate. It is the primary tool to detail not only the decision itself but also what was considered when the decision was made.

When there is doubt whether a design exception is required, the Assistant State Design Engineers, Assistant State Bridge Engineer, Structural Liaison Engineer (SLE), or the Design Liaison Engineer (DLE) for the district should be consulted.

A design exception is encouraged whenever it is feasibly or technically impossible to reasonably meet the minimum design criteria or wherever there is potential for additional value outside of written engineering policy. Design exceptions should not be considered breaches of policy as much as opportunities to add practicality or value to the design.

An approved exception is not a request for permission; rather, it simply documents deliberate variances from general engineering policy.

The Federal Highway Administration (FHWA) Design Decision Documentation and Mitigation Strategies for Design Exceptions may be used in the development of the design exception.

131.1.2 The 10 Controlling Criteria

There are 10 controlling criteria that the FHWA has identified as the most important or critical elements for the design of projects on the National Highway System (NHS). FHWA only approves design exceptions for the controlling criteria listed in Table 131.1.2 when it has determined that a project is a Project of Division Interest (PODI) with Design Exception selected.

The controlling criteria, which vary based upon the type of route and design speed, are described below:

Table 131.1.2 Controlling Criteria
NHS with Design Speed > 50 mph NHS with Design Speed < 50 mph Non-NHS
Design Speed Design Speed (No Controlling Criteria)
Design Loading Structural Capacity Design Loading Structural Capacity
Lane Width
Shoulder Width
Horizontal Curve Radius
Superelevation Rate
Stopping Sight Distance
Maximum Profile Grade
Cross Slope
Vertical Clearance

A design exception approved only by MoDOT is required for all other non-complying design elements on projects which are designated for federal involvement for design exceptions and for all non-complying design elements on all other projects not designated for federal involvement for design exceptions.

131.1.3 Approval Requirements

Table 131.1.3 Design Exception Required Approvals
Category PODI Designated Controlling Criteria* FHWA MoDOT
NHS Yes Yes
No
No Yes or No
Non-NHS Yes or No N/A
* Applicable Controlling Criteria as indicated in EPG 131.1.2.

131.1.3.1 Projects of Division Interest (PODI)

See EPG 123.1.1 FHWA Oversight - National Highway System for information on federal involvement on projects and for the PODI matrix.

131.1.4 The Design Exception Process

Requests for design exceptions are submitted when the need first arises; however, they may be submitted at any time and specifically along with the conceptual study, preliminary plan, right of way certification, or final plans. All design exceptions should be approved prior to and submitted with the plans, specifications, and estimate (PS&E). In general, it is best to identify, consider, and execute the design exception as early as practical in the design process. When a design change is required during construction, the Resident Engineer should contact the Transportation Project Manager (TPM). If that design change has elements that do not meet design standards, a design exception is required. The normal design exception process is followed.

When the need for a design exception has been identified, the TPM, Structural Project Manager (SPM), or consultant representative is responsible for completing the standard Design Exception Information Form. The form must include a detailed description of the rationale for the change and the appropriate supporting documentation to satisfactorily justify the decision and document any mitigation efforts associated with varying from the engineering policy. Previous approval of an item should not be considered approval of the item on any future project. Approval for future projects must be sought on a case-by-case basis.

Project managers (consultant, transportation or structural) and their design staff should recognize the importance of an open and transparent decision making process while considering the suitability and appropriateness of a given design element that is not consistent with current policies. Since engineering policy is established through a collaborative effort, it is critical to engage all appropriate staff when making the decision not to meet policy. While completing the form, communication with the appropriate staff, including the DLE, a representative of any affected MoDOT division and FHWA (when applicable), is critical to ensure efficient and effective review and approval. For efficient processing and to avoid delays, this communication should occur prior to the formal submittal. Depending upon the item being excepted and the type of project, the appropriate review staff and signatory parties will vary.

Central Office staff should be consulted and provide review of the draft design exception prior to district approval. Design exceptions involving safety related items (see EPG 131.1.5) should be reviewed by the District Traffic Engineer and/or Highway Safety and Traffic Division prior to district approval. For design-bid-build projects, a final copy of the design exception is saved in eProjects using the appropriate content type: DE Design Exceptions, with all necessary checkboxes for Type of Exception checked. Staff should include any pertinent information in the Comments Section within the eProjects metadata. For design-build projects, approved design exceptions incorporated into the project are saved in the design-build projects SharePoint site in an Approved Design Exceptions folder.

PODI design exceptions are processed through the DLE for the State Design Engineer and FHWA signatures of approval. The DLE provides the electronic copy of the fully approved design exception back to the TPM for placement in eProjects.

FHWA reserves the right to audit the design exceptions of any federal aid project regardless of level of oversight.

131.1.4.1 The Development, Concurrence and Approval Process

In addition to the applicable process requirements described below, vertical clearance design exceptions on the interstate must also follow the additional requirement described in EPG 131.1.7 Deficient Vertical Clearances on Interstates.

131.1.4.1.1 Roadway Design Exceptions

Upon the core team's determination that a design exception is warranted, the following process should be used for design exception submittals relating to roadway items only:

Conceptual Approval:

  1. The TPM working with the Consultant Project Manager, if applicable, submits the design exception information form and supporting information to the DLE, the District Design Engineer (DDE), FHWA (if applicable) and any other pertinent district and division staff.
  2. The contacted division and district representatives will respond with any necessary comments or concerns, request additional information if necessary or will request an opportunity to meet and discuss the issue.
  3. The TPM works with staff to appropriately address or resolve comments, concerns or objections and finalizes the design exception.
  4. The TPM submits the design exception including all supporting documentation in a single pdf file for signature according to the flowchart below.

Formal Approval:

Signatures for approval should be obtained in accordance with the following flowchart:

alt=Flowchart Start - Need for design exception (DE) identified - Go to Process 1 Process 1 MoDOT TPM (and consultant PM, if applicable) obtain conceptual approval of DE – confer with District, Divisions, and FHWA (if applicable) - Go to Process 2 Process 2 - DE revised based on conceptual approval comments - Go to process 3 Process 3 - DE reviewed by DLE - Go to Decision 1 Decision 1 - Is the project designed by a consultant? - If yes, go to Process 4, If no, go to Process 5 Process 4 - Consultant PM signs DE - Go to Process 5 Process 5 - TPM signs DE - Go to Process 6 Process 6 - DLE signs DE - Go to Process 7 Process 7 - TPM obtains District Engineer Signature - Go to Decision 2 Decision 2 - Is FHWA approval required by EPG 131.1.4? If yes, go to Process 8. If no, go to End. Process 8 - TPM sends DE to DLE - Go to Process 11 Process 9 - DLE obtains State Design Engineer signature - Go to Process 10 Process 10 - DLE obtains FHWA signature - Go to Process 10 Process 11 - DLE returns DE to TPM - Go to End End - TPM stores DE in eProjects
alt=Flowchart Start - Need for design exception (DE) identified - Go to Process 1 Process 1 MoDOT TPM (and consultant PM, if applicable) obtain conceptual approval of DE – confer with District, Divisions, and FHWA (if applicable) - Go to Process 2 Process 2 - DE revised based on conceptual approval comments - Go to process 3 Process 3 - DE reviewed by DLE - Go to Decision 1 Decision 1 - Is the project designed by a consultant? - If yes, go to Process 4, If no, go to Process 5 Process 4 - Consultant PM signs DE - Go to Process 5 Process 5 - TPM signs DE - Go to Process 6 Process 6 - DLE signs DE - Go to Process 7 Process 7 - TPM obtains District Engineer Signature - Go to Decision 2 Decision 2 - Is FHWA approval required by EPG 131.1.4? If yes, go to Process 8. If no, go to End. Process 8 - TPM sends DE to DLE - Go to Process 11 Process 9 - DLE obtains State Design Engineer signature - Go to Process 10 Process 10 - DLE obtains FHWA signature - Go to Process 10 Process 11 - DLE returns DE to TPM - Go to End End - TPM stores DE in eProjects


131.1.4.1.2 Bridge Design Exceptions

The following process should be used for design exception submittals relating to bridge items:

Conceptual Approval:

  1. The SPM, or the SLE working with the Consultant Project Manager submits the design exception form to the Assistant State Bridge Engineer, the DLE, the Transportation Project Manager, FHWA (if applicable) and any other pertinent district and division staff.
  2. The contacted division and district representatives will respond with any necessary comments or concerns, request additional information if necessary or will request an opportunity to meet and discuss the issue (if significant objection is determined).
  3. The SPM/SLE works with staff to appropriately address or resolve comments, concerns or objections and finalizes the design exception.
  4. The SPM/SLE submits the design exception including all supporting documentation in a single pdf file for signature according to the flowchart below.

Formal Approval:

Signatures for approval should be obtained in accordance with the following flowchart:

alt=Flowchart Start - Need for design exception (DE) identified - Go to Process 1 Process 1 MoDOT TPM (and consultant PM, if applicable) obtain conceptual approval of DE – confer with District, Divisions, and FHWA (if applicable) - Go to Process 2 Process 2 - DE revised based on conceptual approval comments - Go to process 3 Process 3 - DE reviewed by DLE - Go to Decision 1 Decision 1 - Is the project designed by a consultant? - If yes, go to Process 4. If no, go to Process 5 Process 4 - Consultant PM signs DE - Go to Process 5 Process 5 - TPM signs DE - Go to Process 6 Process 6 - DLE signs DE - Go to Process 7 Process 7 - SLE/SPM signs DE - Go to Process 8 Process 8 - State Bridge Engineer signs DE - Go to Process 9 Process 9 - TPM obtains District Engineer Signature - Go to Decision 2 Decision 2 - Is FHWA approval required by EPG 131.1.4? If yes, go to Process 10. If no, go to End. Process 10 - TPM sends DE to DLE - Go to Process 11 Process 11 - DLE obtains State Design Engineer signature - Go to Process 12 Process 12 - DLE obtains FHWA signature - Go to Process 13 Process 13 - DLE returns DE to TPM - Go to End End - TPM stores DE in eProjects
alt=Flowchart Start - Need for design exception (DE) identified - Go to Process 1 Process 1 MoDOT TPM (and consultant PM, if applicable) obtain conceptual approval of DE – confer with District, Divisions, and FHWA (if applicable) - Go to Process 2 Process 2 - DE revised based on conceptual approval comments - Go to process 3 Process 3 - DE reviewed by DLE - Go to Decision 1 Decision 1 - Is the project designed by a consultant? - If yes, go to Process 4. If no, go to Process 5 Process 4 - Consultant PM signs DE - Go to Process 5 Process 5 - TPM signs DE - Go to Process 6 Process 6 - DLE signs DE - Go to Process 7 Process 7 - SLE/SPM signs DE - Go to Process 8 Process 8 - State Bridge Engineer signs DE - Go to Process 9 Process 9 - TPM obtains District Engineer Signature - Go to Decision 2 Decision 2 - Is FHWA approval required by EPG 131.1.4? If yes, go to Process 10. If no, go to End. Process 10 - TPM sends DE to DLE - Go to Process 11 Process 11 - DLE obtains State Design Engineer signature - Go to Process 12 Process 12 - DLE obtains FHWA signature - Go to Process 13 Process 13 - DLE returns DE to TPM - Go to End End - TPM stores DE in eProjects

131.1.4.1.3 Both Roadway and Bridge Item Related Design Exceptions

Occasionally, both roadway and bridge items will need to be included. In these instances, the TPM and the SLE/SPM should agree to a single point of contact for the review, concurrence and approval of the design exception and will ensure that the appropriate staff members are properly engaged throughout the process.

131.1.4.2 Issue Resolution

The review and concurrence process is intended to avoid any significant objections, questions or concerns during the approval process, however, occasionally these issues may arise. In this instance, the design exception approval process may be put on hold until the issue can be resolved by the appropriate staff members. The TPM or SLE/SPM will remain the primary contact to address any request for additional information or consideration.

131.1.5 Completing the Design Exception Information Form

Whenever engineering policy cannot be met, data for only those non-standard items is listed on the form. This data includes a brief description of the project and the improvement goals that are being attempted. This information is required since the context of the project often helps in deciding if approval of the exception is appropriate. Additionally, the data should include the details related to the location (limits) associated with the solution, the existing condition (if applicable), the standard design criteria for that feature, and the proposed design solution. The column shown for the existing condition is not applicable to new construction. The appropriate values for desired design criteria are shown in the third column. The design criteria for new construction on rural and urban highways are stated in individual articles pertaining to each geometric element discussed in the EPG 200 Geometrics articles. Design criteria for 3R and 4R projects are discussed in EPG 128 Conceptual Studies. The criteria for proper access management can be found in EPG 940 Access Management.

All design exceptions must suitably explain the justification for the exception. It is imperative that this justification be sufficiently complete to clearly reflect that the designer exercised reasonable care in the selection of a particular highway design. Design exceptions often arise because it is impractical or impossible to reasonably meet engineering policy. The justification may include appropriate economic analysis, discussion of applicable accident location and type or discussion of avoidance of Section 4(f) or Section 6(f) lands. The justification supports the concept that maximum service and safety benefits were realized for the cost invested. Engineering judgment is used when balancing the economic and engineering reasons for the justification. A design exception is based on sound engineering judgment rather than being solely an attempt to save cost.

In general all design exceptions should include the following:

  • Specific design criteria that will not be met.
  • Existing roadway characteristics.
  • Alternatives considered.
  • Comparison of the safety and operational performance of the roadway and other impacts such as right-of-way, community, environmental, cost, and usability by all modes of transportation.
  • Proposed mitigation measures.
  • Compatibility with adjacent sections of roadway.

Note: The level of analysis should be commensurate with the complexity of the project.

In addition to the information above, exceptions for the Design Speed and Design Loading Structural Capacity criteria should include the following information;

Design Speed exceptions:
  • Length of section with reduced design speed compared to overall length of project
  • Measures used in transitions to adjacent sections with higher or lower design or operating speeds.
Design Loading Structural Capacity exceptions:
  • Verification of safe load-carrying capacity (load rating) for all state unrestricted legal loads or routine permit loads, and in the case of bridges and tunnels on the interstate, all federal legal loads.

For design exceptions related to existing conditions, a review of the existing condition crash history is required. The review should focus on crash types to which the design element may relate with a special consideration to fatal and injury crashes. A summary report of the crash information is acceptable if the volume of the data is excessive. Specific attention should be paid to design elements that have a direct impact on safety. Examples of such design elements include, but are not limited to, the following: design speed, stopping sight distance, passing sight distance, lane width, shoulder width, shoulder type, rumble strips, turn lanes, access management requirements, bridge approach rail, horizontal alignment, vertical alignment, grade, horizontal clearance, vertical clearance, guardrail, etc.

In addition, if the design exception request involves safety related features that are adequately addressed in the AASHTO Highway Safety Manual, then documentation of the exception should include a safety analysis as described in the manual. Typically, this process will involve two primary determinations:

  • Calculate the expected change in crashes from existing conditions to standard design conditions.
  • Calculate the expected change in crashes from existing conditions to the proposed design.

The proposed design should take into account any design exceptions as well as any additional safety features above and beyond the standard design.

By making these two determinations, a quantitative safety comparison can be made between existing conditions, the standard design, and the proposed design. This information, along with other project considerations, can be used to help determine the best design alternative. A list of features currently addressed by the manual include: lane width, shoulder width, shoulder type, center line rumble strips, horizontal alignment (length, radius), grade, roadside hazard rating, fixed objects, driveway density, median width, sideslope, lighting, intersection skew angle and turn lanes. Not all features in the manual are addressed for every facility type. If a feature is not addressed in the manual, a statement should be included on the design exception stating that fact. For features not addressed in the HSM, a qualitative discussion may be included.

131.1.6 Revising an Approved Design Exception

Changes in project scope or design criteria can result in changes to design exceptions that have previously been approved. In these cases, a revised design exception must be completed and approved (as described above). The reasoning on revised design exceptions should address the changes and an explanation of the circumstances leading to the revision. The original design exception should accompany the revised information in order to illustrate the changes.

131.1.7 Deficient Vertical Clearances on Interstates

Maintaining the integrity of interstates for national defense purposes has long been recognized. Interstates are intended to be constructed and maintained to meet AASHTO Policy as stated in A Policy on Design Standards - Interstate System, which is incorporated by reference in 23 CFR 625. Maintaining standard vertical clearances to the extent possible for defense mobilization is considered particularly important and is a focus at the national level. As a result, the FHWA has agreed that all exceptions to a 16 foot (16') vertical clearance standard for the rural Interstate routes or on a single routhe through urban areas must be coordinated with the Surface Deployment and Distribution Command Transportation Engineering Agency (SDDCTEA) of the Department of Defense. This coordination applies whether it is a new construction project, a project that does not provide for the correction of an existing substandard condition, or a project that creates a substandard condition at an existing structure. The steps involved are:

  1. For a vertical clearance over any interstate highway that will be less than 16 ft. meeting the above criteria, the district submits to the Design Division a completed SDDCTEA Interstate Vertical Clearance Coordination Form along with a Design Exception for vertical clearance.
  2. The DLE emails the Bridge Inventory Analysts and requests the Structure NBI number for box 2 on the Vertical Clearance Design Exception Coordination with SDDCTEA Form.
  3. Concurrent with the submission or routing of the Design Exception, the DLE submits the SDDCTEA Form to the SDDCTEA and copies FHWA. This may be done electronically using the contact information on the Vertical Clearance Design Exception Coordination with SDDCTEA.
  4. A response from SDDCTEA should occur within 10 working days following receipt of the coordination request. Receipt of the request can be verified with SDDCTEA via telephone, fax, or email. If there is no response after 10 working days following receipt, it can be determined that SDDCTEA does not have any concerns about the proposed exception.
  5. The DLE informs FHWA as to the final outcome of the SDDCTEA request.

Create Category link to 131 Other General Procedures




UPDATING LINKS!!!!

Forms Box EPG 139 form d1 https://epg.modot.mo.org/forms/general_files/DE/DB-202a_Design_Exception_Summary.xlsx form d2 https://epg.modot.mo.org/forms/general_files/DE/DB-202b_Design_Exception_Form.docx

Forms Box EPG 136.7.2.7 Design Exception Information form [https://epg.modot.mo.org/forms/general_files/DE/DesignExceptionInformationForm.docx