Difference between revisions of "751.1 Preliminary Design"
(→751.1.3.4 Barrier or Railing Type, Height and Guidelines for Curb Blockouts: updated per RR3848) |
(→751.1.2.8 Box Culverts: updated per RR3954) |
||
(4 intermediate revisions by the same user not shown) | |||
Line 65: | Line 65: | ||
:Bridge numbers that were assigned to new structures that were never built are only reused if the proposed structure is at the same crossing location that the bridge number was originally assigned to. | :Bridge numbers that were assigned to new structures that were never built are only reused if the proposed structure is at the same crossing location that the bridge number was originally assigned to. | ||
− | :Bridge numbers that were assigned to rehabilitate or modify structures where the work was not completed may reuse the previous bridge number by adding the suffix | + | :Bridge numbers that were assigned to rehabilitate or modify structures where the work was not completed may reuse the previous bridge number by adding the suffix “_02” to the bridge number (i.e., bridge number A6545 had plans developed for deck repairs and was assigned the bridge number A65451, but the work was never completed. At a later date, bridge A6545 is set up to be redecked; the bridge number assigned to the redeck would be A65451_02). This suffix is only recorded in Bloodhound for tracking purposes and is not shown as part of the bridge number on file folders or final plans. |
Line 130: | Line 130: | ||
===751.1.1.5 New Regular Bridge Design Schedule (Nonseismic) (Nonrailway Crossing)=== | ===751.1.1.5 New Regular Bridge Design Schedule (Nonseismic) (Nonrailway Crossing)=== | ||
− | + | <center> | |
− | + | <gallery gallery mode=nolines widths=750px heights=500px " > | |
+ | File:751.1.1.5_01.png|left| | ||
+ | </gallery> | ||
+ | <div style="width: 700px; text-align: left;"> | ||
+ | <nowiki>*</nowiki>13 months minimum required for multi-span bridge design with seismic details or seismic details and abutment seismic design. 13 months minimum required for single-span bridge design with abutment seismic design or seismic details. 24 months minimum required for complete seismic analysis of multi-span bridge design. 24 months minimum required for Railway Crossing bridge design. | ||
+ | </div> | ||
+ | </center> | ||
==751.1.2 Bridges/Boxes== | ==751.1.2 Bridges/Boxes== | ||
Line 155: | Line 161: | ||
The purpose of wings is to contain and stabilize the abutment fill as the roadway transitions to the bridge. For stream crossings in particular, the wings also protect the abutment during extreme hydraulic events. | The purpose of wings is to contain and stabilize the abutment fill as the roadway transitions to the bridge. For stream crossings in particular, the wings also protect the abutment during extreme hydraulic events. | ||
− | The lengths of the wings at the end bents are to be determined prior to the issuance of the Bridge Memorandum. | + | The lengths of the wings at the end bents are to be determined prior to the issuance of the Bridge Memorandum. There are two reasons for this. First, the district will use these lengths to determine the placement of their guardrail (bridge anchor section). Second, if the lengths of the wings exceed 22 ft. for seismic design category A or 17 ft. for seismic design category B, C or D, they will have to be broken into a stub wing and a detached wing wall. If this happens, then you will need to include this extra cost in your Preliminary Cost Estimate and request soundings for the wall. The request for soundings for the wall should include a request for the determination of the allowable bearing of the soil (if in cut - assume piling if it is in fill) and the angle of internal friction for the material retained by the detached wing wall. Also include the bottom of wing footing elevation. |
In order to use a standard end section for Type D barrier on a short turned-back wing, consider increasing the wing length so that the barrier end section is at least 8 feet long. | In order to use a standard end section for Type D barrier on a short turned-back wing, consider increasing the wing length so that the barrier end section is at least 8 feet long. | ||
Line 251: | Line 257: | ||
===751.1.2.8 Box Culverts=== | ===751.1.2.8 Box Culverts=== | ||
− | Most districts prefer a box culvert to a bridge because of the lower maintenance costs; however, if a stream crossing is on the borderline between a box culvert and a bridge, each option should be explored and presented to the district. The presentation to the district should include the cost estimate for each option as well as a recommendation as to which option is preferred by the Bridge Division. | + | Most districts prefer a box culvert to a bridge because of the lower maintenance costs; however, if a stream crossing is on the borderline between a box culvert and a bridge, each option should be explored and presented to the district. The presentation to the district should include the cost estimate for each option as well as a recommendation as to which option is preferred by the Bridge Division. Multi-cell box culverts shall be avoided on streams with reported medium to heavy drift because the interior wall creates a snag point and drift will have difficulty passing through the box culvert resulting in clogging and likely undermining of the culvert. Single-cell box culverts may be used if the opening is sized to allow drift to pass. If the stream being crossed is a drainage ditch it is advisable to have the district contact the drainage district to see if they have any specific objections (i.e. drift etc.) to using a culvert at the proposed location. Approval of proposed structure layout by the drainage district may be required, see [[:Category:747 Bridge Reports and Layouts#747.3.4 Bridge Permits or Approvals by Other Agencies|EPG 747.3.4 Bridge Permits or Approvals by Other Agencies]]. |
====751.1.2.8.1 Hydraulic Design==== | ====751.1.2.8.1 Hydraulic Design==== | ||
Line 358: | Line 364: | ||
If the district decides to use staged construction, one important item to verify in this situation is that the new girders will clear the existing substructure. Another item to consider in setting up the staging is the placement and attachment requirements of the temporary concrete traffic barrier relative to the bridge deck and meeting horizontal distance requirements from the edge of the deck, which determines whether the temporary concrete traffic barrier is attached to the deck and how it is attached. | If the district decides to use staged construction, one important item to verify in this situation is that the new girders will clear the existing substructure. Another item to consider in setting up the staging is the placement and attachment requirements of the temporary concrete traffic barrier relative to the bridge deck and meeting horizontal distance requirements from the edge of the deck, which determines whether the temporary concrete traffic barrier is attached to the deck and how it is attached. | ||
+ | :* For staged bridge construction with MSE walls at the abutments, consider specifying location of temporary MSE walls on the plan details. The interior angle between MSE walls and temporary MSE walls should be greater than 70°. However, if unavoidable, then interior angle shall be absolute minimum 65°. Temporary MSE wall option for staged bridge construction shall not be used when bridge skew is greater than 25°. | ||
− | + | Sometimes due to limited space or to retain improved foundation material or to retain existing slope contractor may need to provide temporary shoring prior to constructing temporary MSE wall systems in staged construction, but only the temporary MSE wall should be indicated on the plans. For design requirements of MSE wall systems, see [[:Category:720_Mechanically_Stabilized_Earth_Wall_Systems#720.2_Design_Requirements|720 Mechanically Stabilized Earth Wall Systems]]. | |
===751.1.2.12 Temporary Barriers=== | ===751.1.2.12 Temporary Barriers=== | ||
Line 385: | Line 392: | ||
<center>'''Attached Temporary Barrier'''</center> | <center>'''Attached Temporary Barrier'''</center> | ||
− | ===751.1.2.13 Earthquake | + | ===751.1.2.13 Seismic (Earthquake) Design Category A, B, C and D Considerations=== |
− | See [[: | + | See [[:751.9_Bridge_Seismic_Design|EPG 751.9 Bridge Seismic Design]] for seismic design and detail requirements in accordance with SGS, and LRFD. Utilize provided flow charts. |
− | |||
− | |||
− | + | All new or replacement bridge/wall designs, either nonseismic (meaning a regular static design) or seismic design or detail, must meet Seismic Design Category (SDC) A requirements in accordance with SGS (Seismic Zone 1 of LRFD). Additionally, where applicable bridge seismic designs/details/analysis must meet requirements of the Seismic Design Category B, C, or D in accordance with [https://epg.modot.org/forms/general_files/BR/Bridge_Seismic_Design_Flowchart.pdf Bridge Seismic Design Flowchart]. | |
− | : | + | For laying out new or replacement bridges in SDC A, B, C or D (per SGS), the following is important. |
+ | :* Box culverts are preferable to bridges on stream crossings because they are exempt from seismic design unless crossing a known exposed fault. | ||
+ | :* Pile cap intermediate bents and drilled shafts are preferable to open column bents on footings because footings can grow quite large due to seismic forces. | ||
+ | :* Minimize the number of expansion joints in the deck because each of these locations may require earthquake restrainers which are very costly. | ||
+ | :* Make the superstructure as light as possible, which usually means use steel plate girders or wide flanges instead of prestressed concrete girders where possible. | ||
− | + | The new or replacement bridge design schedule for a complete seismic analysis requires 24 months minimum and bridge design schedule for seismic details and/or abutment seismic design requires 13 months minimum. Additional 2 - 3 months is required for review and letting process before the schedule letting. See [[751.1_Preliminary_Design#751.1.1.5_New_Regular_Bridge_Design_Schedule_.28Nonseismic.29_.28Nonrailway_Crossing.29|EPG 751.1.1.5 New Regular Bridge Design Schedule (Nonseismic) (Nonrailway Crossing)]]. | |
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
===751.1.2.14 Temporary Bridges=== | ===751.1.2.14 Temporary Bridges=== | ||
Line 444: | Line 447: | ||
===751.1.2.17 Preliminary Cost Estimate=== | ===751.1.2.17 Preliminary Cost Estimate=== | ||
+ | |||
+ | '''Box Culverts –''' A new or replaced box culvert is exempt from seismic design unless crossing a known exposed fault. Submit [https://epg.modot.org/forms/general_files/BR/Request_for_Final_Soundings_for_Structures_Form.xlsx “Request for soil properties Form A”] to Geotech Section and design as a SDC A. If box culvert is crossing a known exposed fault then discuss with Structural Project Manager (SPM) for alternate option. | ||
+ | |||
+ | '''Bridges and Retaining Walls –''' For a new or replaced retaining wall or bridge, review [https://epg.modot.org/forms/general_files/BR/Bridge_Seismic_Planning_Flowchart.pdf Bridge Seismic Planning Flowchart], [https://epg.modot.org/forms/general_files/BR/Bridge_Seismic_Design_Flowchart.pdf Bridge Seismic Design Flowchart], [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf preliminary seismic design map] and following information. | ||
+ | :* Seismic design of overpass should be considered when overpass bridge collapse would greatly impede emergency traffic for the main route. (i.e., No access ramps on a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf major route or a 1st or 2nd priority earthquake emergency route]). | ||
+ | :* For preliminary planning and cost estimate use the SDC values shown on [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf preliminary seismic design map]. SDC boundaries are shown for soil site class D. | ||
+ | :* Site class verification is not required for bridges located in regions SDC A1 or A2, so the preliminary SDC shall be used for plans reporting. | ||
+ | :* In the normal design schedule, the Geotechnical section will determine the site class and an accurate SDC, S<sub>D1</sub>, A<sub>s</sub> for bridges located in the regions encompassed by SDC B, C and D on the [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf preliminary seismic design map]. Typically, the SDC will remain the same as shown on the map or get dropped to a lower SDC (e.g., D to C, C to B, B to A2). | ||
+ | :* If a bridge gets downgraded to SDC A2 after Geotech analysis and carry a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf 1<sup>st</sup> or 2<sup>nd</sup> priority earthquake emergency route], the bridge shall receive seismic details similar to SDC B. If a bridge gets downgraded to SDC A2 after Geotech analysis and does not carry a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf 1<sup>st</sup> or 2<sup>nd</sup> priority route], it will not require seismic details. If a bridge gets downgraded to SDC A1 after Geotech analysis, it will not require seismic details. Typically, downgrades may result in a reduced project schedule and/or a reduced cost estimate for the bridge. | ||
+ | :* Geotechnical section will perform a liquefaction assessment for bridges with a final SDC of C or D and carry a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf major route or 1<sup>st</sup> or 2<sup>nd</sup> priority earthquake emergency route]. | ||
+ | |||
+ | Seismic design category (SDC) is divided in SDC A (S<sub>D1</sub> < 0.15), SDC B (0.15 ≤ S<sub>D1</sub> < 0.30), SDC C (0.30 ≤ S<sub>D1</sub> < 0.50) and SDC D (S<sub>D1</sub> ≥ 0.50). SDC A is subdivided into SDC A1 (S<sub>D1</sub> < 0.10) and SDC A2 (0.10 ≤ S<sub>D1</sub> < 0.15). Submit “Soil properties Form A” to Geotech Section for SDC A1 and SDC A2 area bridges, retaining walls and box culverts. Submit “Soil properties Form A” and “Soil properties Form B” to Geotech Section for SDC B, C and D area bridges and retaining walls. For soil properties form, see [[751.1_Preliminary_Design#751.1.2.19_Soundings_.28Borings.29|EPG 751.1.2.19 Soundings (Borings)]]. | ||
The Preliminary Cost Estimate should be neat, legible and dated since a copy of it is included with the Bridge Memo. It should also be rounded to the nearest thousand dollars. | The Preliminary Cost Estimate should be neat, legible and dated since a copy of it is included with the Bridge Memo. It should also be rounded to the nearest thousand dollars. | ||
Line 468: | Line 483: | ||
</center> | </center> | ||
− | The Preliminary Cost Estimate should be increased for the following items: Cost Estimate Guide for rural preliminary design (do not compound | + | The Preliminary Cost Estimate should be increased for the following items: Cost Estimate Guide for rural preliminary design (do not compound all increases using your judgment). |
− | ::: | + | {| class="wikitable" |
− | + | |- | |
− | |< | + | | style="width:300px; text-align: center; background-color:lightgray;" | '''Bridge in SDC boundaries on</br>[https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf preliminary seismic design map]''' |
+ | | style="width:125px; text-align: center; background-color:lightgray;" | '''% Cost Increase''' | ||
+ | | style="text-align: center; background-color:lightgray;" | '''Comments for final SDC''' | ||
+ | |- | ||
+ | | SDC A1 </br> SDC A2 (nonseismic) </br> SDC A2 (seismic details) | ||
+ | | style="text-align: center;" | 0 </br> 0 </br> 10 | ||
+ | | No cost increase for SDC A1 area bridges and most of the bridges in SDC A2 area. </br> If a bridge carry a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf 1<sup>st</sup> or 2<sup>nd</sup> priority earthquake emergency route] and located in SDC A2 area, it will receive seismic details similar to SDC B (i.e. 10% increase). | ||
|- | |- | ||
− | | | + | | SDC B (single span, seismic details) </br> SDC B (single span, abutment seismic design) </br> SDC B (multi-span) |
+ | | style="text-align: center;" | 0 </br> 5 </br> 10 | ||
+ | | Cost increase is for seismic details in accordance with the 2023 AASHTO Guide Specifications for LRFD Seismic Bridge Design. If bridge receives a final SDC B and carries a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf major route or 1st or 2nd priority earthquake emergency route] then abutments will be designed for mass inertial forces per [https://www.modot.org/media/47034 SEG 24-02]. (i.e. 0 to 5% increase for single span bridges). If a bridge gets downgraded to SDC A2 and does not carry a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf 1st or 2nd priority route], it will not require seismic details. If a bridge gets downgraded to SDC A1 after Geotech analysis, it will not require seismic details (i.e. no cost increase). | ||
|- | |- | ||
− | | | + | |SDC C (single span, seismic details) </br> SDC C (single span, abutment seismic design) </br> SDC C (multi-span, seismic details) </br> SDC C (multi-span, complete seismic analysis) |
+ | | style="text-align: center;" | 0 </br> 5 </br> 10 </br> 25 | ||
+ | | 25% cost increase is for complete seismic analysis. All bridges receiving a final SDC C and not carrying a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf major route or 1st or 2nd priority earthquake emergency route] will only receive seismic details (i.e. 10% increase). If a bridge carries a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf major route or 1st or 2nd priority earthquake emergency route], gets downgraded to SDC B, it will only receive seismic details and abutments will be designed for mass inertial forces per [https://www.modot.org/media/47034 SEG 24-02] (i.e. 10% increase).If single span bridge receives a final SDC C and carries a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf major route or 1st or 2nd priority earthquake emergency route] then abutments will be designed for mass inertial forces per [https://www.modot.org/media/47034 SEG 24-02] (i.e. 0 to 5% increase). | ||
|- | |- | ||
− | | | + | | SDC D (single span, seismic details) </br> SDC D (single span, abutment seismic design) </br> SDC D (multi-span, seismic details) </br> SDC D (multi-span, complete seismic analysis) |
+ | | style="text-align: center;" | 0 </br> 10 </br> 10 </br> 40 | ||
+ | | 40 % cost increase is for complete seismic analysis. All bridges receiving a final SDC D after Geotech analysis and do not carry a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf major route or 1st or 2nd priority earthquake emergency route] will only receive seismic details (i.e. 10% increase). If a bridge carries a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf major route or 1st or 2nd priority earthquake emergency route], gets downgraded to SDC B, it will only receive seismic details and abutments will be designed for mass inertial forces per [https://www.modot.org/media/47034 SEG 24-02] (i.e. 10% increase). If a bridge carries a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf major route or 1st or 2nd priority earthquake emergency route], gets downgraded to SDC C, it will receive a complete seismic analysis (i.e. 25% increase). If single span bridge receives a final SDC C or D and carries a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf major route or 1st or 2nd priority earthquake emergency route] then abutments will be designed for mass inertial forces per [https://www.modot.org/media/47034 SEG 24-02] (i.e. 5 to 10% increase). | ||
+ | |} | ||
+ | |||
+ | :::{|border="0" | ||
+ | | <u>Item</u> || <u>% Cost increase</u> | ||
|- | |- | ||
− | | | + | | width="200" | Staged Construction (SDC A) ||align="center" | 10 |
|- | |- | ||
− | | | + | | Horizontally Curved (SDC A) || align="center" | 5 |
|- | |- | ||
− | |Tight Site/Limited Access||align="center"|3 | + | | Tight Site/Limited Access || align="center" | 3 |
|} | |} | ||
− | + | The following are guidelines for estimating the cost of the removal of existing bridges: | |
− | |||
− | |||
− | |||
− | |||
:::{|border="0" | :::{|border="0" | ||
− | + | | <u>Type of Bridge Removal</u> || <u>Cost per Square Foot</u> | |
− | |<u>Type of Bridge Removal</u>||<u>Cost per Square Foot</u> | ||
|- | |- | ||
− | |Simple Structures Over Streams||align="center"|** | + | | Simple Structures Over Streams || align="center" | ** |
|- | |- | ||
− | |Girder Structures Over Roads||align="center"|** | + | | Girder Structures Over Roads || align="center" | ** |
|- | |- | ||
− | |Conc. Slab Structures Over Interstates||align="center"|** | + | | Conc. Slab Structures Over Interstates || align="center" | ** |
|- | |- | ||
− | | ( | + | | (Quick opening of lanes to traffic) |
|} | |} | ||
− | + | <math>**</math> Consult Bid Tabs for an analysis of the latest bridge removal costs. Bridge Division staff may consult the Pay Item Spreadsheet maintained by the Structural Review Engineer or see [[751.6_General_Quantities#751.6.1_Index_of_Quantities|EPG 751.6.1 Index of Quantities]]. | |
− | |||
===751.1.2.18 Bridge Memorandums=== | ===751.1.2.18 Bridge Memorandums=== | ||
Line 541: | Line 566: | ||
Sample listing of what to include on the Bridge Memorandum: | Sample listing of what to include on the Bridge Memorandum: | ||
− | 1. Identify the following classifications if applicable: (''[ | + | 1. Identify the following classifications if applicable: (''[https://epg.modot.org/forms/general_files/BR/751-1-2-18-2_Design_Implications.docx Design Implications]'') |
::• All routes involved shall be classified as either: | ::• All routes involved shall be classified as either: | ||
− | :::o ([ | + | :::o ([https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf major]), as shown in link. |
:::o (minor), not a major route and ADT ≥ 400. | :::o (minor), not a major route and ADT ≥ 400. | ||
:::o (low volume), not a major route and ADT < 400. | :::o (low volume), not a major route and ADT < 400. | ||
::• Major bridges with a total length ≥ 1000 feet shall be classified by specifying “(major)” behind the specified bridge number. | ::• Major bridges with a total length ≥ 1000 feet shall be classified by specifying “(major)” behind the specified bridge number. | ||
− | ::• Priority 1 or 2 | + | ::• [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf Priority 1 or 2 earthquake emergency routes] shall be classified by specifying “(priority <u>1</u> <u>2</u> EQ)” behind the route classification. |
2. Identify type of structure, span lengths, skew, loading, roadway width, wing lengths and special end fill considerations. For curved structures, specify how the design span lengths are to be measured i.e., “measured along the CL of Roadway”. If plate girder or wide flange beam, further identify them as either weathering or painted steel. | 2. Identify type of structure, span lengths, skew, loading, roadway width, wing lengths and special end fill considerations. For curved structures, specify how the design span lengths are to be measured i.e., “measured along the CL of Roadway”. If plate girder or wide flange beam, further identify them as either weathering or painted steel. | ||
Line 594: | Line 619: | ||
21. Identify the bridge end drainage provisions as determined by district Design. For example, note when concrete aprons at each wing wall will be required (Rdwy. Item). Note when concrete approach pavement (Rdwy. Item) with or without drain basins (Rdwy. Item) will be required, or note when rock blanket will be required that extends up to full length of bridge approach slabs, or when drain flumes (Rdwy. Item) will be required. | 21. Identify the bridge end drainage provisions as determined by district Design. For example, note when concrete aprons at each wing wall will be required (Rdwy. Item). Note when concrete approach pavement (Rdwy. Item) with or without drain basins (Rdwy. Item) will be required, or note when rock blanket will be required that extends up to full length of bridge approach slabs, or when drain flumes (Rdwy. Item) will be required. | ||
− | + | ||
22. For redecks or in other cases where the rock blanket elevations are not shown on the bridge plans and the top of the rock blanket is required to be flush to the existing ground line in accordance with the Memorandum of Agreement with SEMA, include the following note: | 22. For redecks or in other cases where the rock blanket elevations are not shown on the bridge plans and the top of the rock blanket is required to be flush to the existing ground line in accordance with the Memorandum of Agreement with SEMA, include the following note: | ||
: The top of rock blanket shall be flush to the ground line as directed by the engineer. (Roadway Item.) | : The top of rock blanket shall be flush to the ground line as directed by the engineer. (Roadway Item.) | ||
Line 600: | Line 625: | ||
23. For retaining walls, indicate any aesthetic treatments such as concrete staining and form liner requirements. Be specific regarding names, types and colors of staining, and names and types of form liner. | 23. For retaining walls, indicate any aesthetic treatments such as concrete staining and form liner requirements. Be specific regarding names, types and colors of staining, and names and types of form liner. | ||
− | 24. Form liners are standard for MSE | + | 24. Form liners are standard for MSE precast modular panel wall systems. Be specific regarding names, types and colors of staining, and names and types of form liner. See [https://www.modot.org/bridge-standard-drawings Bridge Standard Drawings → MSE Wall - MSEW]. |
− | 25. For MSE wall | + | 25. For MSE wall supporting abutment fill: Identify gutter type, fencing, lower longitudinal and lateral drain pipe sizes (type and sizes to be determined by district Design division). (Lateral drain pipes are only required as determined by district Design division.) |
− | 26. OPTIONAL Seismic Information for new bridge or wall on Memo: Note “Preliminary Seismic Description: Site Class _, Seismic Design Category _, A<sub>s</sub> = __, S<sub>D1</sub> = | + | 26. OPTIONAL Seismic Information for new bridge or wall on Memo: Note “Preliminary Seismic Description: Site Class _, Seismic Design Category _, A<sub>s</sub> = __, S<sub>D1</sub> = _, _____”. The last blank should be filled with “non-seismic”, “seismic details”, “abutment seismic design”, “seismic details with abutment seismic design” or “complete seismic analysis”. The provided information is subject to change after Geotechnical Report is released. See [https://epg.modot.org/forms/general_files/BR/Bridge_Seismic_Planning_Flowchart.pdf Bridge Seismic Planning Flowchart]. (This is similar to item no. 9 under [[751.1_Preliminary_Design#751.1.2.31_Finishing_Up_Design_Layout|EPG 751.1.2.31 Finishing Up Design Layout]].) |
− | 27. For rehabs, redecks, widenings, recoatings and new replacement structures, see [[#751.1.3. | + | 27. For rehabs, redecks, widenings, recoatings and new replacement structures, see [[751.1_Preliminary_Design#751.1.3.9_Environmental_Considerations:_Asbestos_and_Lead|EPG 751.1.3.9 Environmental Considerations: Asbestos and Lead]] for notes to include. |
====751.1.2.18.3 Supporting Documents==== | ====751.1.2.18.3 Supporting Documents==== | ||
Line 644: | Line 669: | ||
|'''Additional Information''' | |'''Additional Information''' | ||
|- | |- | ||
− | | [https://epg.modot.org/forms/general_files/BR/ | + | | [https://epg.modot.org/forms/general_files/BR/Request_for_Final_Soundings_for_Structures_Form.xlsx Request for Final Soundings for Structures Form] |
|- | |- | ||
| [https://epg.modot.org/forms/general_files/BR/Guidance_for_Request_for_Final_Soundings_for_Structures_Form.xlsx Guidance for Request for Final Soundings for Structures Form] | | [https://epg.modot.org/forms/general_files/BR/Guidance_for_Request_for_Final_Soundings_for_Structures_Form.xlsx Guidance for Request for Final Soundings for Structures Form] | ||
Line 673: | Line 698: | ||
'''Plan and Elevation Sheet(s) of Existing Bridge.''' When applicable. | '''Plan and Elevation Sheet(s) of Existing Bridge.''' When applicable. | ||
− | '''[https://epg.modot.org/forms/general_files/BR/ | + | '''[https://epg.modot.org/forms/general_files/BR/Request_for_Final_Soundings_for_Structures_Form.xlsx Request for Final Soundings for Structures Form].''' The [https://epg.modot.org/forms/general_files/BR/Guidance_for_Request_for_Final_Soundings_for_Structures_Form.xlsx Guidance for Request for Final Soundings for Structures Form] is available. |
Instructions to Soundings Party included on the form should be similar to the following: | Instructions to Soundings Party included on the form should be similar to the following: | ||
Line 683: | Line 708: | ||
:'''Retaining Walls -''' Request that soundings be taken every 25 ft. along the wall alignment. Soundings shall be made to rock or to a point which is 20 ft. below the bottom of the wall, whichever is higher. | :'''Retaining Walls -''' Request that soundings be taken every 25 ft. along the wall alignment. Soundings shall be made to rock or to a point which is 20 ft. below the bottom of the wall, whichever is higher. | ||
− | '''Request for Soil Properties –''' The request for soil properties is located on a separate tab in the Request for Final Soundings for Structures form. | + | '''Request for Soil Properties –''' The request for soil properties is located on a separate tab in the [https://epg.modot.org/forms/general_files/BR/Request_for_Final_Soundings_for_Structures_Form.xlsx Request for Final Soundings for Structures form]. |
:'''Bridges –''' If there is a possibility that drilled shafts will be used, request borings based on using drilled shafts so the appropriate lab work can be done the first time. | :'''Bridges –''' If there is a possibility that drilled shafts will be used, request borings based on using drilled shafts so the appropriate lab work can be done the first time. | ||
− | :'''MSE Walls –''' The request for soundings for MSE walls should include requests for the angle of internal frictions (Ø) for both the foundation and the retained material. | + | :'''MSE Walls –''' The request for soundings for MSE walls should include requests for the angle of internal frictions (Ø) for both the foundation (improved and unimproved) and the retained material. |
'''Due Date –''' Use the following guidelines when setting a due date: | '''Due Date –''' Use the following guidelines when setting a due date: | ||
Line 705: | Line 730: | ||
====751.1.2.19.4 Submittal==== | ====751.1.2.19.4 Submittal==== | ||
− | The completed Request for Final Soundings | + | The completed [https://epg.modot.org/forms/general_files/BR/Request_for_Final_Soundings_for_Structures_Form.xlsx Request for Final Soundings for Structures Form] and the other supporting documents listed above should be stored in the project's corresponding eProjects folder. (Consultants should contact the Structural Liaison Engineer). |
− | A request for soundings should be sent by email to the Construction and Materials Division. The email shall be addressed to the Geotechnical Engineer and copied to the Geotechnical Director and the Structural Project Manager (or the Structural Liaison Engineer). It should include at a minimum, a link to the SharePoint folder that contains the completed Request for Final Soundings | + | A request for soundings should be sent by email to the Construction and Materials Division. The email shall be addressed to the Geotechnical Engineer and copied to the Geotechnical Director and the Structural Project Manager (or the Structural Liaison Engineer). It should include at a minimum, a link to the SharePoint folder that contains the completed [https://epg.modot.org/forms/general_files/BR/Request_for_Final_Soundings_for_Structures_Form.xlsx Request for Final Soundings for Structures Form] and supporting documents. In addition to the link, any relevant information that may aid the Geotechnical Section in providing the requested borings should be included. |
The request for soundings is typically done at the same time that the Bridge Memorandum is sent to the district. | The request for soundings is typically done at the same time that the Bridge Memorandum is sent to the district. | ||
+ | |||
+ | ====751.1.2.19.4.1 Sounding Information for Seismic Category A, B, C and D==== | ||
+ | |||
+ | For all new or replacement bridges or walls or structure modification for widening submit [https://epg.modot.org/forms/general_files/BR/Request_for_Final_Soundings_for_Structures_Form.xlsx Request for Final Soundings for Structures Form] (Soil Properties Form A and AASHTO LRFD (SGS) Form B) for LRFD projects. Based on following procedure Geotechnical Section will determine SDC for structures located in SDC B, C and D on [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf Preliminary Seismic Design Map]. For all new or replacement box culverts on rock submit [https://epg.modot.org/forms/general_files/BR/Request_for_Final_Soundings_for_Structures_Form.xlsx Request for Final Soundings for Structures Form] (Soil Properties Form A). | ||
+ | |||
+ | :Geotechnical Section will determine S<sub>D1</sub> = , A<sub>S</sub> = , and SDC = ____ using [https://earthquake.usgs.gov/ws/designmaps/aashto-2023/ NSHMP Static Data Services (usgs.gov)] website. The risk-targeted design spectra returned by this web service are derived from the USGS 2018 National Seismic Hazard Model for the conterminous United States. Designer should use same procedure to create response spectra for bridge seismic design or verifying SDC using Geotechnical section reported site class. | ||
+ | |||
+ | :For example see: [https://epg.modot.org/forms/general_files/BR/Example-1_SDC_Response_Spectra.docx Example 1_SDC_Response_Spectra] | ||
===751.1.2.20 Substructure Type=== | ===751.1.2.20 Substructure Type=== | ||
Line 908: | Line 941: | ||
{|border="0" | {|border="0" | ||
|- | |- | ||
− | |1.)||colspan="2"|General Information | + | | 1.) || colspan="2" | General Information |
|- | |- | ||
− | | ||a.||Route and structure classifications | + | | || a. || [[751.1_Preliminary_Design#751.1.2.18.2_Content|Route and structure classifications]] |
|- | |- | ||
− | | ||b.||Live load designation | + | | || b. || Live load designation |
|- | |- | ||
− | | ||c.||Traffic counts for the design year (AADT and AADTT). | + | | || c. || Traffic counts for the design year (AADT and AADTT). |
|- | |- | ||
− | | ||d.||Tie station (if applicable). | + | | ||d. || Tie station (if applicable). |
|- | |- | ||
− | | ||e.||Beginning station. | + | | || e. || Beginning station. |
|- | |- | ||
− | | ||f.||Horizontal curve data. | + | | || f. || Horizontal curve data. |
|- | |- | ||
− | | ||g.||Profile grade information (including offset from CL of roadway or median). | + | | || g. || Profile grade information (including offset from CL of roadway or median). |
|- | |- | ||
− | | ||h.||Excavation datum. | + | | || h. || Excavation datum. |
|- | |- | ||
− | |2.)||colspan="2"|Superstructure | + | | 2.) || colspan="2" | Superstructure |
|- | |- | ||
− | | ||a.||Type and span lengths. | + | | || a. || Type and span lengths. |
|- | |- | ||
− | | ||b.||Roadway widths and type of barrier or railing. | + | | || b. || Roadway widths and type of barrier or railing. |
|- | |- | ||
− | |3.)||colspan="2"|Substructure | + | | 3.) || colspan="2" | Substructure |
|- | |- | ||
− | | ||a.||Skew(s) of all bents. | + | | || a. || Skew(s) of all bents. |
|- | |- | ||
− | | ||b.||Types of all bents. | + | | || b. || Types of all bents. |
|- | |- | ||
− | | ||c.||Type and locations of sway bracing for concrete pile cap intermediate bent with HP pile. | + | | || c. || Type and locations of sway bracing for concrete pile cap intermediate bent with HP pile. |
|- | |- | ||
− | | ||d.||Locations and top of wall elevations for collision walls. | + | | || d. || Locations and top of wall elevations for collision walls. |
|- | |- | ||
− | | ||e.||Embedment of encasement for encased pile cap bent. | + | | || e. || Embedment of encasement for encased pile cap bent. |
|- | |- | ||
− | | ||f.||Location of tie beam. | + | | || f. || Location of tie beam. |
|- | |- | ||
− | | ||g.||Bottom elevations of web beam. | + | | || g. || Bottom elevations of web beam. |
|- | |- | ||
− | |4.)||colspan="2"|End Bents (Abutments) | + | | 4.) || colspan="2" | End Bents (Abutments) |
|- | |- | ||
− | | ||a.||Type of end fill and maximum slope. | + | | || a. || Type of end fill and maximum slope. Include earth plugs for piling in rock fill. |
|- | |- | ||
− | | ||b.||Berm elevations. | + | | || b. || Berm elevations. |
|- | |- | ||
− | | ||c.||Type and extent of spill and side slope protection (permanent erosion control geotextile fabric is required). | + | | || c. || Type and extent of spill and side slope protection (permanent erosion control geotextile fabric is required). |
|- | |- | ||
− | | ||d.||Bridge end drainage provisions per district (drain basins<sup>'''1'''</sup>, rock blanket, drain flumes) (Rdwy. Item) | + | | || d. || Bridge end drainage provisions per district (drain basins<sup>'''1'''</sup>, rock blanket, drain flumes) (Rdwy. Item) |
|- | |- | ||
− | | ||e.||Angle of internal friction to be used for deadman anchors. | + | | || e. || Angle of internal friction to be used for deadman anchors. |
|- | |- | ||
− | |5.)||colspan="2"|Foundations | + | | 5.) || colspan="2" | Foundations |
|- | |- | ||
− | | ||a.||Type and lengths of all piling. | + | | || a. || Type and lengths of all piling. |
|- | |- | ||
− | | ||b.||Minimum galvanized penetration (elevation) | + | | ||b. || Minimum galvanized penetration (elevation) |
|- | |- | ||
− | | ||c.||Minimum tip elevations for all piles. | + | | || c. || Minimum tip elevations for all piles. |
|- | |- | ||
− | | ||d.||Location and elevation for any preboring. | + | | || d. || Location and elevation for any preboring. |
− | |-style="vertical-align:top;" | + | |- style="vertical-align:top;" |
− | | ||e.||Pile point reinforcement (shoes) required for all structural steel HP piles. When Geotechnical Section indicates pile point reinforcement needed and show pile point type on boring log for CIP pile, then recommended pile point reinforcement type shall be shown on Design Layout. | + | | ||e. || Pile point reinforcement (shoes) required for all structural steel HP piles. When Geotechnical Section indicates pile point reinforcement needed and show pile point type on boring log for CIP pile, then recommended pile point reinforcement type shall be shown on Design Layout. |
|- | |- | ||
− | | ||f.||For end bearing pile when Geotechnical Section recommends dynamic pile testing (PDA) for pile driving verification method then reflect that on Design Layout. | + | | || f. || For end bearing pile when Geotechnical Section recommends dynamic pile testing (PDA) for pile driving verification method then reflect that on Design Layout. |
|- | |- | ||
− | | ||g.||Types of footings, their elevations and allowable bearing (if applicable). | + | | || g. || Types of footings, their elevations and allowable bearing (if applicable). |
|- | |- | ||
− | | ||h.||Location of any cofferdams and/or seal courses. | + | | || h. || Location of any cofferdams and/or seal courses. |
|- | |- | ||
− | | ||i.||End bearing and side bearing capacity for any drilled shafts. | + | | || i. || End bearing and side bearing capacity for any drilled shafts. |
|- | |- | ||
− | | ||j.||Top of Rock Socket elevations and their minimum lengths. | + | | || j. || Top of Rock Socket elevations and their minimum lengths. |
|- | |- | ||
− | | ||k.||Estimated Maximum Scour Depth (Elev.)<sup>'''2'''</sup> | + | | || k. || Estimated Maximum Scour Depth (Elev.)<sup>'''2'''</sup> |
|- | |- | ||
− | | ||l.||Minimum pile cleanout penetration (Elev.)<sup>'''3'''</sup> | + | | || l. || Minimum pile cleanout penetration (Elev.)<sup>'''3'''</sup> |
|- | |- | ||
− | |6.)||colspan="2"|Traffic Handling | + | | 6.) || colspan="2" | Traffic Handling |
|- | |- | ||
− | | ||a.||How will traffic be handled (bypass, road closure, staging, other) | + | | || a. || How will traffic be handled (bypass, road closure, staging, other) |
|- | |- | ||
− | | ||b.||Include a sketch of any staging. | + | | || b. || Include a sketch of any staging. |
|- | |- | ||
− | |7.)||colspan="2"|Disposition of Existing Structure | + | | 7.) || colspan="2" | Disposition of Existing Structure |
|- | |- | ||
− | | ||a.||Bridge No(s). of structures slated for removal. | + | | || a. || Bridge No(s). of structures slated for removal. |
|- | |- | ||
− | | ||b.||Estimate cost of removal and indicate that this cost is included in the total. | + | | || b. || Estimate cost of removal and indicate that this cost is included in the total. |
|- | |- | ||
− | |8.)||colspan="2"|Hydraulic Information | + | | 8.) || colspan="2" |Hydraulic Information |
|- | |- | ||
− | | ||a.||Drainage area and terrain description. | + | | || a. || Drainage area and terrain description. |
|- | |- | ||
− | | ||b.||Design frequency. | + | | || b. || Design frequency. |
|- | |- | ||
− | | ||c.||Design discharge. | + | | || c. || Design discharge. |
|- | |- | ||
− | | ||d.||Design high water elevation. | + | | || d. || Design high water elevation. |
|- | |- | ||
− | | ||e.||Estimated backwater. | + | | || e. || Estimated backwater. |
|- | |- | ||
− | | ||f.||Overtopping frequency and discharge if less than 500 yr. | + | | || f. || Overtopping frequency and discharge if less than 500 yr. |
+ | |- style="vertical-align:top;" | ||
+ | | 9.) || colspan="2" | Seismic Information (New or Replacement Bridge, substructure widening or Wall) (Applies to both seismic and nonseismic designs): | ||
+ | |- style="vertical-align:top;" | ||
+ | | || a. || Provide Site Class, Seismic Design Category, A<sub>s</sub> and S<sub>D1</sub> for SDC B, C and D bridge/wall, and Liquefaction Potential information for SDC C and D (All available information from Geotechnical report). When A<sub>s</sub> is greater than 0.75 then show A<sub>s</sub> = 0.75. For SDC A area bridge/wall indicate SDC A, S<sub>D1</sub> < 0.15 and A<sub>s</sub> = N/A. Use N/A if not reported in Geotech report. | ||
+ | |- style="vertical-align:top;" | ||
+ | | || b. || Indicate either “Nonseismic”, "Seismic Details", “Abutment Seismic Design”, “Seismic Details plus Abutment Seismic Design” or “Complete Seismic Analysis” for a bridge structure based on Geotechnical Section provided SDC and [https://epg.modot.org/forms/general_files/BR/Bridge_Seismic_Design_Flowchart.pdf Bridge Seismic Design Flowchart] ([[751.9_LFD_Seismic#751.9.1_Seismic_Analysis_.26_Design_Specifications|EPG 751.9.1 Seismic Analysis and Design Specifications]]). | ||
+ | :* For final SDC A2 from Geotechnical report, indicate “Seismic Details” if bridge carries a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf 1st or 2nd priority earthquake emergency route]. For final SDC A2 bridge indicate SDC A on design layout. | ||
+ | :* For final SDC B from Geotechnical report, indicate “Seismic Details plus Abutment Seismic Design” if bridge carries a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf major or 1st or 2nd priority earthquake emergency route] otherwise indicate “Seismic details”. | ||
+ | :* For final SDC C or D from Geotechnical report, indicate “Complete seismic analysis” if multi-span bridge carries a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf major or 1st or 2nd priority earthquake emergency route] otherwise indicate “Seismic details”. For final SDC C or D from Geotechnical report, indicate “Abutment Seismic Design” if single-span bridge carry a [https://epg.modot.org/forms/general_files/BR/Preliminary_Seismic_Design_Map.pdf major or 1st or 2nd priority earthquake emergency route] otherwise indicate “Seismic details”. | ||
+ | |- style="vertical-align:top;" | ||
+ | | || c. || For a wall structure in SDC B, or C seismic analysis provisions shall not be ignored for walls that support another structure (i.e. abutment fill or building) in accordance with LRFD 11.5.4.2. Based on wall supporting information and Geotech report indicate “seismic analysis not required” or “seismic analysis required”. SDC D retaining walls shall be designed for seismic load. | ||
+ | |- style="vertical-align:top;" | ||
+ | | || d. || All new or replacement bridge/wall designs, either nonseismic (meaning a regular static design) or seismic design or detail, must meet Seismic Design Category (SDC) A requirements in accordance with SGS (Seismic Zone 1 of LRFD). Additionally, bridge/wall seismic designs/details must meet requirements of the Seismic Design Category B, C, or D where applicable. See [[751.1_Preliminary_Design#751.1.2.13_Seismic_.28Earthquake.29_Design_Category_A.2C_B.2C_C_and_D_Considerations|EPG 751.1.2.13 Seismic (Earthquake) Design Category A, B, C and D Considerations.]] | ||
|- | |- | ||
− | | | + | | 10.) || colspan="2" | Miscellaneous |
|- | |- | ||
− | | ||a.|| | + | | || a. || Locations of Bridge Approach Slabs. |
|- | |- | ||
− | | ||b.|| | + | | || b. || Call out slab drain requirements if other than the standard procedure. |
|- | |- | ||
− | | ||c. | + | | || c. || The location of the stationing reference line (CL roadway, CL median, other). |
|- | |- | ||
− | | | + | | || d. || Station equations. |
|- | |- | ||
− | | || | + | | || e. || Minimum final and construction clearances (vertical and horizontal). |
|- | |- | ||
− | | || | + | | || f. || Use of weathering steel or color of paint (steel girders). |
|- | |- | ||
− | | || | + | | || g. || Name and phone number of district contact. |
|- | |- | ||
− | | || | + | | || h. || Preliminary Cost Estimate. |
|- | |- | ||
− | | || | + | | || i. || Details of any utilities to be attached to the bridge. |
|- | |- | ||
− | | || | + | | || j. || Details of any conduit, light supports or any other unusual attachments. |
|- | |- | ||
− | | || | + | | || k. || Channel change requirements. |
|- | |- | ||
− | | || | + | | || l. || Temporary shoring requirements and whether it is a Bridge or Roadway Item. |
|- | |- | ||
− | | || | + | | || m. || Temporary MSE wall systems. (If determined during layout process for staged bridge construction). |
|- | |- | ||
− | | || | + | | || n. || Location of Maint. facility contractor is to use for delivery of MoDOT retained items. |
|- | |- | ||
− | + | | || o. || All DGN files should be stored in the project folder (Preliminary subfolder). | |
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | | ||o.||All DGN files should be stored in the project folder (Preliminary subfolder). | ||
|} | |} | ||
{| style="margin: 1em auto 1em auto" | {| style="margin: 1em auto 1em auto" | ||
− | |- | + | |- style="vertical-align:top;" |
− | |width=" | + | | width="40" | || '''1''' || colspan="2" align="left" | Drain basins can be included with concrete approach pavement per district. (Rdwy. Item) |
− | |- | + | |- style="vertical-align:top;" |
− | | ||colspan="2" align="left"| | + | | || '''2''' || colspan="2" align="left" | Show maximum of total scour depths estimated for multiple return periods in years from Preliminary design which should be given on the Design Layout. Show the controlling return period (e.g. 100, 200, 500) in Foundation Data. If return periods are different for different bents, add a new line in Foundation Data.<br/>On the plans report note EPG 751.50 E2.22 for CIP pile. |
− | + | |- style="vertical-align:top;" | |
− | + | | || '''3''' || colspan="2" align="left" | Show for open ended CIP piles. For scour condition, minimum cleanout elevation shall be at least 3 feet below maximum estimated scour depth. For non scour condition, minimum cleanout elevation shall be at least 10 feet below natural ground line. | |
− | |- | ||
− | | ||colspan="2" align="left"| | ||
|} | |} | ||
− | |||
Once the Preliminary Detailer and Designer are in agreement on these items, the entire layout folder should be submitted to the SPM for their review. The SPM will then request a Design Layout Conference with the Assistant State Bridge Engineer and the Structural Resource Manager. | Once the Preliminary Detailer and Designer are in agreement on these items, the entire layout folder should be submitted to the SPM for their review. The SPM will then request a Design Layout Conference with the Assistant State Bridge Engineer and the Structural Resource Manager. | ||
Line 1,178: | Line 1,213: | ||
:* MASH (2016) TL-4 (Type C and D barrier, 38-inch two tube railing) | :* MASH (2016) TL-4 (Type C and D barrier, 38-inch two tube railing) | ||
:* MASH TL-3 (Type H barrier, Type A and B barrier, culvert guardrail) | :* MASH TL-3 (Type H barrier, Type A and B barrier, culvert guardrail) | ||
− | :* NCHRP 350 TL-4 (32-inch two tube railing | + | :* NCHRP 350 TL-4 (32-inch two tube railing) |
− | :* NCHRP 350 TL-3 (thrie beam railing). | + | :* NCHRP 350 TL-3 (12” x 29” vertical barrier, thrie beam railing). |
Type C and D barrier shall be used on all redecks, rehabs and widenings where the full length of barrier is being replaced with exceptions for the following: | Type C and D barrier shall be used on all redecks, rehabs and widenings where the full length of barrier is being replaced with exceptions for the following: | ||
Line 1,202: | Line 1,237: | ||
'''W-beam Railing (Culvert Guardrail)''' | '''W-beam Railing (Culvert Guardrail)''' | ||
− | The MASH TL-3 standard for guardrail attachment is covered in [[751.12_Barriers,_Railings,_Curbs_and_Fences#751.12.6_Culvert_Guardrail_(Top_Mounted)|EPG 751.12.6 Culvert Guardrail (Top Mounted)]]. Existing guardrail or thrie beam attachments likely do not have an adequate base plate design, railing height or headwall clearance to be considered MASH TL-3 compliant. Existing attachments most closely fit NCHRP 350 TL-3 or MASH TL-2. Existing guardrail attachments shall be treated in the same manner as free-standing guardrail when determining if the system can be used in place ( | + | The MASH TL-3 standard for guardrail attachment is covered in [[751.12_Barriers,_Railings,_Curbs_and_Fences#751.12.6_Culvert_Guardrail_(Top_Mounted)|EPG 751.12.6 Culvert Guardrail (Top Mounted)]]. Existing guardrail or thrie beam attachments likely do not have an adequate base plate design, railing height or headwall clearance to be considered MASH TL-3 compliant. Existing attachments most closely fit NCHRP 350 TL-3 or MASH TL-2. Existing guardrail attachments shall be treated in the same manner as free-standing guardrail when determining if the system can be used in place ([[606.1_Guardrail#606.1.3.1_Guardrail_Selection_and_Placement|see EPG 606.1.3.1 Guardrail Selection and Placement]]). If Midwest Guardrail System (MGS) is required and space is available for headwall clearance, 2’-10” minimum between headwall and roadway face of guardrail, the MASH TL-3 standard for guardrail attachment shall be used. |
If there is less than 2’-10” of space between headwall and roadway face of guardrail, a thrie beam shall be used and it is preferrable to top mount the headwall instead of pushing the slab mount closer to headwall. The condition of the headwall should be considered before choosing the headwall mount option. | If there is less than 2’-10” of space between headwall and roadway face of guardrail, a thrie beam shall be used and it is preferrable to top mount the headwall instead of pushing the slab mount closer to headwall. The condition of the headwall should be considered before choosing the headwall mount option. | ||
Line 1,292: | Line 1,327: | ||
|'''38-inch Two Tube Rail'''<br/> (Photo not available) || [[image:751.1.3.4-MASH2016 tl-4.png|130px]]<br/>(MASH 2016 TL-4) || Up to 2” || Use in place.|| (3)<br/>Not for use with turned-back abutment wings less than 18” thick. | |'''38-inch Two Tube Rail'''<br/> (Photo not available) || [[image:751.1.3.4-MASH2016 tl-4.png|130px]]<br/>(MASH 2016 TL-4) || Up to 2” || Use in place.|| (3)<br/>Not for use with turned-back abutment wings less than 18” thick. | ||
|- | |- | ||
− | |'''12” x 29” Vertical Barrier'''<br/> [[image:751.1.3.4 vertical.jpg|130px]] || [[image:751.1.3.4 vertical section.jpg|130px]] <br/>(NCHRP 350 TL- | + | |'''12” x 29” Vertical Barrier'''<br/> [[image:751.1.3.4 vertical.jpg|130px]] || [[image:751.1.3.4 vertical section.jpg|130px]] <br/>(NCHRP 350 TL-3) || Up to 2” ||End of barrier modification for new guardrail attachment.|| (1) |
|- | |- | ||
− | | '''Culvert Guardrail''' || [[image:751.1.3.4-NCHRP 350 TL-3.png|150px]]<br/>(NCHRP 350 TL-3 Thrie Beam or W-Beam) || | + | | '''Culvert Guardrail''' || [[image:751.1.3.4-NCHRP 350 TL-3.png|150px]]<br/>(NCHRP 350 TL-3 Thrie Beam or W-Beam) || [[606.1_Guardrail#606.1.3.1_Guardrail_Selection_and_Placement|See EPG 606.1.3.1 Guardrail Selection and Placement]] || Use in place. || If MGS is required for the approach, the MASH TL-3 standard shall be installed if space allows. |
|- | |- | ||
|colspan=5 align="left" width="750"|(1) Shall not be used for redecks, widenings, and railing or cantilever full length replacements.<br/>(2) Typically specified for redecks, and railing or cantilever full length replacements. Shall not be used for widenings.<br/>(3) Typically specified for redecks, widenings, and railing or cantilever full length replacements.<br/>(4) Shall not be used on major routes with design speeds greater than 45 mph or on minor and low volume routes with design speeds greater than 55 mph or AADT ≥ 1700. May be used for all other major, minor, and low volume routes. | |colspan=5 align="left" width="750"|(1) Shall not be used for redecks, widenings, and railing or cantilever full length replacements.<br/>(2) Typically specified for redecks, and railing or cantilever full length replacements. Shall not be used for widenings.<br/>(3) Typically specified for redecks, widenings, and railing or cantilever full length replacements.<br/>(4) Shall not be used on major routes with design speeds greater than 45 mph or on minor and low volume routes with design speeds greater than 55 mph or AADT ≥ 1700. May be used for all other major, minor, and low volume routes. | ||
Line 1,454: | Line 1,489: | ||
:Shortening of bottom reinforcement layers to less than 0.7H to minimize excavation requirements, provided the wall is bearing on rock or very competent foundation soil. | :Shortening of bottom reinforcement layers to less than 0.7H to minimize excavation requirements, provided the wall is bearing on rock or very competent foundation soil. | ||
− | For walls on rock or very competent foundation soil, e.i., SPT > 50, the Bottom reinforcements may be shortened to a | + | For walls on rock or very competent foundation soil, e.i., SPT > 50, the Bottom reinforcements may be shortened to a greater of 0.4H or 5 ft with the Upper reinforcements lengthened to compensate for external stability issues in lieu of removing rock or competent soil for construction. Design Guidelines for this case are provided in FHWA Publications No. FHWA-NHI-10-024. |
For conditions of marginal stability, consideration must be given to ground improvement techniques to improve foundation stability, or to lengthening of reinforcement. | For conditions of marginal stability, consideration must be given to ground improvement techniques to improve foundation stability, or to lengthening of reinforcement. | ||
− | MSE walls are pre-qualified and listed on the internet in | + | MSE walls are pre-qualified and listed on the internet in three categories: |
− | * | + | * Drycast modular block wall (DMBW-MSE) systems |
− | * | + | * Wetcast modular block wall (WMBW-MSE) systems |
+ | * Precast modular panel wall (PMPW-MSE) systems | ||
− | + | Drycast modular block wall systems are battered walls with a maximum height of 10 feet. Drycast modular block wall systems have five major components: Dry cast modular blocks, pre-approved geogrid soil reinforcements, select granular backfill, unit fill and nonreinforced concrete leveling pad. | |
− | + | Wetcast modular block wall systems are battered walls with a maximum height of 15 feet. Wetcast modular block wall systems have five major components: Wetcast modular blocks, pre-approved geogrid soil reinforcements, select granular backfill, unit fill and nonreinforced concrete leveling pad. | |
− | + | Precast modular panel wall systems are vertical walls with heights that may exceed 10 feet. Precast modular panel wall systems have five major components: Precast modular panels, pre-approved soil reinforcements, anchorage devices, select granular backfill, and nonreinforced concrete leveling pad. | |
− | |||
− | Aesthetic enhancements may be used for either CIP or MSE walls. If [[#751.1.2.33 Aesthetic Enhancements | + | Aesthetic enhancements may be used for either CIP or MSE walls. If [[751.1_Preliminary_Design#751.1.2.33_Aesthetic_Enhancements|EPG 751.1.2.33 Aesthetic Enhancements]] are required by the district, form liners and concrete stains are encouraged rather than actual brickwork and stonework since form liners and concrete stains typically need less maintenance, less loading, less detailing, less detailing, no extra support ledge and produce no risk of delamination or falling work. However, for MSE precast modular panel wall systems only, form liners are required for all panels. For additional information, see [[751.24_LFD_Retaining_Walls#751.24.2_Mechanically_Stabilized_Earth_.28MSE.29_Walls|EPG 751.24.2 Mechanically Stabilized Earth (MSE) Walls]]. |
Any deviation from the criteria listed shall be discussed with Structural Project Manager. | Any deviation from the criteria listed shall be discussed with Structural Project Manager. | ||
Line 1,476: | Line 1,511: | ||
===751.1.4.3 MSE Walls=== | ===751.1.4.3 MSE Walls=== | ||
− | Generally, both the horizontal alignment and the top of wall elevations are supplied by the district in the Bridge Survey. You do need to check the top of wall elevations to make sure the district accounted for any concrete gutters placed behind the top of the wall (Gutters are necessary if the slope of the fill can direct water towards the top of the wall, i.e. positive sloping and flat backfills). The district should decide whether to use Type A or Type B gutters ([https://www.modot.org/media/16880 Standard Plan 609.00]), or Modified Type A or Modified Type B gutters ([https://www.modot.org/media/16871 Standard Plan 607.11]) if fencing is required, and where they should drain (to be shown on roadway plans). For general guidelines, see [[751.24 LFD Retaining Walls#751.24.2 Mechanically Stabilized Earth (MSE) Walls|EPG 751.24.2 Mechanically Stabilized Earth (MSE) Walls]]. | + | Generally, both the horizontal alignment and the top of wall elevations are supplied by the district in the Bridge Survey. You do need to check the top of wall elevations to make sure the district accounted for any concrete gutters placed behind the top of the wall (Gutters are necessary if the slope of the fill can direct water towards the top of the wall, i.e., positive sloping and flat backfills). The district should decide whether to use Type A or Type B gutters ([https://www.modot.org/media/16880 Standard Plan 609.00]), or Modified Type A or Modified Type B gutters ([https://www.modot.org/media/16871 Standard Plan 607.11]) if fencing is required, and where they should drain (to be shown on roadway plans). For general guidelines, see [[751.24 LFD Retaining Walls#751.24.2 Mechanically Stabilized Earth (MSE) Walls|EPG 751.24.2 Mechanically Stabilized Earth (MSE) Walls]]. |
− | You will also need to set the elevations for the top of the leveling pad. | + | You will also need to set the elevations for the top of the leveling pad. The minimum embedment depth of MSEW, which is the distance between the finished ground line and the top of the leveling pad, is based on this table: (FHWA-NHI-10-024, Table 2-1 and LRFD 11.10.2.2) |
− | {|border="1" cellspacing="0" cellpadding="5" align="center" style="text-align:center" | + | {| border="1" cellspacing="0" cellpadding="5" align="center" style="text-align:center" |
− | + | | width="250" | '''Slope in Front of Wall''' || width="250" | '''Minimum Embedment Depth to Top of Leveling Pad''' | |
− | |width="250"|'''Slope in Front of Wall'''||width="250"|'''Minimum Embedment''' | + | |- |
+ | | All Geometries || 2 ft minimum | ||
+ | |- | ||
+ | | Horizontal (walls) || H/20 | ||
+ | |- | ||
+ | | Horizontal (abutments) || H/10 | ||
|- | |- | ||
− | | | + | | 3H:1V || H/10 |
|- | |- | ||
− | | | + | | 2H:1V || H/7 |
|- | |- | ||
− | | | + | | 1.5H:1V || H/5 |
|} | |} | ||
− | The absolute minimum embedment is 2 ft. | + | Where, |
+ | |||
+ | H:V = Horizontal to vertical slope in the front of the wall | ||
+ | |||
+ | H = Height of the wall as measured from the top of the leveling pad to the top of the wall | ||
+ | |||
+ | The absolute minimum embedment is 2 ft except when rock is found near surface. When the soundings are returned from the Geotechnical Director, they will include a minimum embedment depth to the top of leveling pad, minimum soil reinforcement length necessary for global stability, bearing resistance and settlement requirements. If rock is encountered during excavation then the contractor shall immediately cease excavating and notify the engineer and contact Geotechnical Section to perform global stability and suggest a required minimum embedment depth to the top of leveling pad and required minimum soil reinforcement length. | ||
− | Preliminary cost estimating MSE walls is based on the unit price bid history and on the square footage of the area of the face of the wall. | + | Preliminary cost estimating MSE walls is based on the unit price bid history and on the square footage of the area of the face of the wall. The unit price per square foot of wall includes wall elements, leveling pad and backfill. Excavation and retained fill are not included. |
If soundings indicate weak material exist, then the designer should investigate that sufficient right of way limits exist to address the required length for the soil reinforcement. | If soundings indicate weak material exist, then the designer should investigate that sufficient right of way limits exist to address the required length for the soil reinforcement. | ||
Line 1,511: | Line 1,557: | ||
French drains will be used to relieve water pressure behind the CIP wall as a default. If you expect to encounter springs or swampy conditions, then check with the district contact on calling for an underdrain. If the decision is made to use an underdrain, the porous backfill and pipes are Roadway Items and this must be noted on the Bridge Memorandum and Design Layout. | French drains will be used to relieve water pressure behind the CIP wall as a default. If you expect to encounter springs or swampy conditions, then check with the district contact on calling for an underdrain. If the decision is made to use an underdrain, the porous backfill and pipes are Roadway Items and this must be noted on the Bridge Memorandum and Design Layout. | ||
− | For details on requesting soundings, see [[#751.1.2. | + | For details on requesting soundings, see [[751.1_Preliminary_Design#751.1.2.19_Soundings_.28Borings.29|EPG 751.1.2.19 Soundings (Borings)]]. |
− | If you have indications that the foundation material is very poor in quality (less than 1 ton per sq. ft. allowable bearing), consider piling and include in the Preliminary Cost Estimate. Preliminary cost estimating should follow [[751. | + | If you have indications that the foundation material is very poor in quality (less than 1 ton per sq. ft. allowable bearing), consider piling and include in the Preliminary Cost Estimate. Preliminary cost estimating should follow [[751.1_Preliminary_Design#751.1.2.17_Preliminary_Cost_Estimate|EPG 751.1.2.17 Preliminary Cost Estimate]] and be based upon unit price bid history. More refined cost estimating should follow cost-basing estimating. |
===751.1.4.5 Obstructions=== | ===751.1.4.5 Obstructions=== |
Latest revision as of 09:17, 21 November 2024
Contents
- 1 751.1.1 Overview
- 2 751.1.2 Bridges/Boxes
- 2.1 751.1.2.1 End Slopes/Spill Fills
- 2.2 751.1.2.2 Wing Lengths
- 2.3 751.1.2.3 Live Load Determination
- 2.4 751.1.2.4 Skew Angle
- 2.5 751.1.2.5 Bridge Width
- 2.6 751.1.2.6 Vertical and Horizontal Clearances
- 2.7 751.1.2.7 Structure Type Selection
- 2.8 751.1.2.8 Box Culverts
- 2.9 751.1.2.9 Girder Type Selection
- 2.10 751.1.2.10 Longer Bridges
- 2.11 751.1.2.11 Staged Construction
- 2.12 751.1.2.12 Temporary Barriers
- 2.13 751.1.2.13 Seismic (Earthquake) Design Category A, B, C and D Considerations
- 2.14 751.1.2.14 Temporary Bridges
- 2.15 751.1.2.15 Bridges Over Railroads
- 2.16 751.1.2.16 Historical Bridge Considerations
- 2.17 751.1.2.17 Preliminary Cost Estimate
- 2.18 751.1.2.18 Bridge Memorandums
- 2.19 751.1.2.19 Soundings (Borings)
- 2.20 751.1.2.20 Substructure Type
- 2.21 751.1.2.21 Type of Footings
- 2.22 751.1.2.22 Types of Piling
- 2.23 751.1.2.23 Estimating the Lengths of Piles
- 2.24 751.1.2.24 Drilled Shafts
- 2.25 751.1.2.25 Excavation Datum
- 2.26 751.1.2.26 Seal Courses
- 2.27 751.1.2.27 Cofferdams
- 2.28 751.1.2.28 Webs
- 2.29 751.1.2.29 Protection of Spill Slopes and Side Slopes
- 2.30 751.1.2.30 Design Exceptions
- 2.31 751.1.2.31 Finishing Up Design Layout
- 2.32 751.1.2.32 FHWA Submittal
- 2.33 751.1.2.33 Aesthetic Enhancements
- 2.34 751.1.2.34 Blast Loading Considerations
- 2.35 751.1.2.35 Bridge Approach Slabs
- 2.36 751.1.2.36 Bridge End Drainage
- 3 751.1.3 Wearing Surfaces/Rehabs/Redecks/Widenings
- 3.1 751.1.3.1 Overview
- 3.2 751.1.3.2 Documentation
- 3.3 751.1.3.3 Bridges on Resurfacing Projects
- 3.4 751.1.3.4 Barrier or Railing Type, Height and Guidelines for Curb Blockouts
- 3.5 751.1.3.5 Deck Repairs
- 3.6 751.1.3.6 Deck Treatment
- 3.7 751.1.3.7 Bridge Approach Slabs
- 3.8 751.1.3.8 Bridge End Drainage
- 3.9 751.1.3.9 Environmental Considerations: Asbestos and Lead
- 4 751.1.4 Retaining Walls
Forms |
Structural Rehabilitation Checklist |
751.1.1 Overview
751.1.1.1 Introduction
The Preliminary Design of a structure begins with the district submitting a Bridge Survey indicating their need for a structure, and ends with the completion of the Substructure Layout or TS&L submittal (type, size and location). This article is intended to be a guide for those individuals assigned the task of performing the Preliminary Design or “laying out” of a structure.
The types of structures can be broken into five categories:
- 1.) Bridge over Water
- 2.) Bridge over Roadway or Railroad
- 3.) Box Culvert over Water
- 4.) Retaining Wall (CIP walls taller than 5 ft., MSE walls adjacent to bridge end bents)
- 5.) Rehabilitation or Modification of Existing Structure
In addition to the following information, the Preliminary Design shall consider hydraulic issues where applicable.
751.1.1.2 Bridge Survey Processing and Bridge Numbering
The Preliminary Design process starts with the receipt of the Bridge Survey. The following is a list of steps that are taken by the Bridge Survey Processor.
Assign a Bridge Number to the Structure
The Bridge Division assigns bridge numbers in Bloodhound to all new, rehabilitated or modified structures (i.e., bridges, box culverts (see EPG 750.7.4.3 Summary of Responsibilities), CIP retaining walls over 5 ft. tall and MSE walls adjacent to bridge end bents).
Enter the Bridge Number, survey received date and feature crossed in the Bloodhound database.
New Structures:
- New structures are numbered in ascending order using the next available bridge number. Numbering for new structures (except timber structures) start at A0001 thru A9999 and will be followed by B1000 thru B9999. (Note: B0001 thru B0581 were used for the Safe and Sound Bridge Replacement Program.)
- New timber bridges are numbered in the same manner using the letter “T” instead of the letter “A”.
Temporary Structures:
- Temporary bridges use the same number as the new bridge with the letter “T” added to the end (i.e., the temporary bridge for A8650 would be A8650T).
Rehabilitated or Modified Structures (Except when rehabilitation is only for structural steel coating):
- Single Structures (Includes twin structures with individual bridge numbers):
- Structures without a suffix letter on the existing bridge number will be numbered using the existing bridge number and a suffix number added that corresponds to the number of rehabilitations or modifications to the structure (i.e., bridge number A0455 becomes A04551 upon its first rehabilitation or modification and A04552 upon its second).
- Single Structures with the Suffix “R”:
- Structures that have the suffix “R” on the bridge number are usually bridges that have been rehabilitated or modified in the past, but in some cases bridges were given the suffix “R” to denote it as a replacement for a bridge with the same number. Review the existing bridge plans to determine if the “R” was for a rehabilitation or replacement. Structures that have been previously rehabilitated should replace the “R” with a suffix number corresponding to the total number of rehabilitations to the structure (i.e., bridge number A0444R would become A04442 (second rehab. or mod.), bridge number A0055R2 would become A00553 (third rehab. or mod.), etc.). For structures where the “R” denotes it as a replacement, the suffix number corresponds to the number of rehabilitations or modifications and the “R” is dropped (i.e., bridge number L0428R becomes L04281 for the first rehabilitation). If the “R” suffix was removed in a previous rehabilitation, the next suffix number is used regardless if the original structure was a rehabilitation or replacement.
- Twin Structures with the Same Bridge Number:
- Twin structures with the same bridge number will use a different suffix number for each structure. The numbering is similar to a single structure with the lower suffix number being used on the eastbound or southbound structure and the next suffix number being used on the westbound or northbound structure (i.e., bridge number A0144 would become A01441 for the eastbound bridge and A01442 for the westbound bridge. A future rehabilitation would become A01443 for the eastbound bridge and A01444 for the westbound bridge). Twin bridges with an “R” suffix on the bridge number would receive the suffix numbers using the same rules, but with the same consideration given to the “R” as it is for a single structure.
Structural Steel Coating (Use when all bridge pay items are related to structural steel coatings):
- Rehabilitations that consist only of structural steel coatings use the existing bridge number plus the suffix “-Paint” (i.e., bridge number A2100 would become A2100-Paint and bridge number A150010 (multiple rehabilitations) would become A150010-Paint). A future rehabilitation consisting of only structural steel coatings would use the suffix “-Paint2” only if no other rehabilitations have been completed since the previous coating rehabilitation.
Removal of Existing Bridge Structures:
- When a bridge structure is removed and not replaced by a new bridge structure or is removed under a separate contract, the suffix “-Remove” should be added to the latest bridge number (i.e., bridge number T0415 would become T0415-Remove and bridge number K01651 would become K01651-Remove).
Re-using Bridge Numbers:
- Bridge numbers that were assigned to new structures that were never built are only reused if the proposed structure is at the same crossing location that the bridge number was originally assigned to.
- Bridge numbers that were assigned to rehabilitate or modify structures where the work was not completed may reuse the previous bridge number by adding the suffix “_02” to the bridge number (i.e., bridge number A6545 had plans developed for deck repairs and was assigned the bridge number A65451, but the work was never completed. At a later date, bridge A6545 is set up to be redecked; the bridge number assigned to the redeck would be A65451_02). This suffix is only recorded in Bloodhound for tracking purposes and is not shown as part of the bridge number on file folders or final plans.
Create Job Folders
Check to see if a Correspondence File has been created. If the Correspondence File has been created, record the Bridge Number(s) in Bloodhound and make a Preliminary Design File for each structure received. If the Correspondence File has not been created, make a Correspondence File, an outer folder and a Preliminary Design File for each structure received. Here is the information for each type of folder/file:
Folder Type | Required Information on Folder | |
Outer (pink label) | County, Route and Job No. | |
Correspondence | County, Route and Job No. | |
Preliminary Design | County, Route, Bridge No., Location and Job No. |
Also, be sure to notify by email the Structural Resource Manager and the appropriate Structural Project Manager or Structural Liaison Engineer, if known, when a new Correspondence File is created. The email subject line should include the Job No., County, Route and Bridge No. Include the name of the Bridge Division contact in the email, either the Structural Project Manager or the Structural Liaison Engineer.
Calculate Drainage Information
For structures over streams or waterways, calculate the drainage area and length of stream. Generate a drainage summary and include this information along with a map showing the drainage area for the structure and the area surrounding it in the Preliminary Design folder. If the drainage area is less than 1.5 sq. miles, consult the Structural Resource Manager to determine if preliminary design by the Bridge Division is necessary. The accuracy of the drainage area should be to the nearest 0.1 sq. mile for drainage areas less than 10 sq. miles and to the nearest 1 sq. mile for drainage areas greater than or equal to 10 sq. miles. When another stream intersects the subject stream near the downstream side of the proposed structure, create a separate drainage summary for the intersecting stream and include it in the Preliminary Design folder.
Process Electronic Files
When the electronic files listed in EPG 747.1.2 Bridge Survey Submittals are received, verify that the drawing scales are correct and that the necessary reference files are included. Also, review all Bridge Survey Sheets and the Bridge Survey Checklist for accuracy and completeness. The Bridge Survey Processor may have to work with the district to correct any discrepancies and/or omissions.
Add the newly assigned bridge number to the files and place a hard copy in the layout folder.
Final Step for Bridge Survey Processor
Once all of these steps are completed, the Bridge Survey Processor should deliver the Correspondence File, outer folder and the Preliminary Design Folder(s) to the Structural Resource Manager. An acknowledgement email is sent to the district contact(s) informing them that the Bridge Division has received the Bridge Survey. The email subject line should include the Job No., County and Route. Include the Bridge No(s). and the name of the Bridge Division contact in the email.
Once the survey is found to be complete and accurate, the Survey Complete date should be entered into Bloodhound. This date should match the Surv Rec date if no changes were made. If the survey is not complete or contains inaccuracies as submitted, we need to work with the district to fill in the blanks. If the omissions affect the timeline for completing the preliminary design, the Survey Complete date should reflect the date when we have all the information needed for the preliminary design to move forward without delay. If there is a delay in the bridge division review of the survey, this time should not count against the district in the survey complete date. The Bridge Survey Processor should work closely with the preliminary designer and SPM to determine the proper Survey Complete date in this case. For example, a bridge survey is received on 9/16/2016. Initial review by the bridge survey processor shows a complete survey. The job sits for five weeks while a preliminary resource comes available. Review by the preliminary designer shows a profile grade that is unusable and the preliminary design cannot progress until the grade situation is corrected. It takes four weeks for the grade to get worked out. The Survey Complete date should be four weeks after the Surv Rec date (10/14/2016). The district would not be penalized for our five week delay in reviewing the survey. This date is important because it will help us track when bridge surveys are turned in relative to when they are complete and when the project is due to Design.
751.1.1.3 Beginning Preliminary Design
The Preliminary Designer should meet with the Structural Project Manager to go over the Correspondence and Preliminary Design files to see if anything out of the ordinary has come up at Core Team Meetings prior to that date. It is important to include any correspondence or calculations used in the laying out of the structure in the bound portion of the Preliminary Design Folder.
The Preliminary Designer should then examine the Bridge Survey closely for any errors or omissions. Consult EPG 747 Bridge Reports and Layouts. Pay special attention to the scales used. Make sure the district's submittal includes photographs and details of staging and/or bypasses, if applicable. Verify that the proposed roadway width meets the NBI criteria for minimum bridge roadway width to avoid building a deficient bridge. Contact the district to resolve any discrepancies or questions.
A visit to the bridge site by the Preliminary Designer may be warranted to help determine Manning’s “n” values, examine adjacent properties, etc. If you decide to make this trip, advise the Structural Project Manager and the district contact since they may also want to attend.
Vertical Alignment and Bridge Deck Drainage
Laying out a bridge should consider deck drainage concerns for bridges on flat grades and sagging vertical curves and other vertical alignment issues as given in EPG 230.2 Vertical Alignment and EPG 230.2.10 Bridge Considerations.
751.1.1.4 Coordination, Permits, and Approvals
The interests of other agencies must be considered in the evaluation of a proposed stream-crossing system; cooperation and coordination with these agencies must be undertaken. Coordination with the State Emergency Management Agency (SEMA), the U.S. Coast Guard, the U.S. Army Corps of Engineers, and the Department of Natural Resources is required.
Required permits include:
- U.S. Coast Guard permits for construction of bridges over navigable waterways.
- Section 404 permits for fills within waterways of the United States from the U.S. Army Corps of Engineers.
- Section 401 Water Quality Certification permits from the Missouri Department of Natural Resources.
- Floodplain development permits for work in special flood hazard areas from the State Emergency Management Agency (SEMA).
Section 404 and Section 401 permits are obtained by the Design Division. U.S. Coast Guard permits are obtained by the Bridge Division. The Bridge Division will obtain floodplain development permits for projects that include structures in a regulated floodplain. The Design Division will obtain floodplain development permits for other projects involving roadway fill in a regulated floodplain.
Copies of approved U.S. Coast Guard permits and floodplain development permit/applications are sent to the district, with a copy to the Design Division.
See MoDOT and the Environment for more information on the required permits.
751.1.1.5 New Regular Bridge Design Schedule (Nonseismic) (Nonrailway Crossing)
*13 months minimum required for multi-span bridge design with seismic details or seismic details and abutment seismic design. 13 months minimum required for single-span bridge design with abutment seismic design or seismic details. 24 months minimum required for complete seismic analysis of multi-span bridge design. 24 months minimum required for Railway Crossing bridge design.
751.1.2 Bridges/Boxes
751.1.2.1 End Slopes/Spill Fills
The end slopes are determined by the Construction and Materials Division and are supplied to the Bridge Division by way of the Preliminary Geotechnical Report. If this report is not in the Correspondence file, contact the district to get a copy of it. The Bridge Division has made a commitment to the districts that we will have the bridge plans, specials and estimate completed 12 months after the date the Bridge Survey and Preliminary Geotechnical Report are received. The "12 month clock" does not start ticking until both the Bridge Survey and the Preliminary Geotechnical Report are in the Bridge Division.
When laying out a skewed structure, adjust the end slope for the skew angle. On higher skews, this will have a significant effect on the lengths of the spans. Often the slope of the spill fills will be steeper than the roadway side slopes. On a skewed structure, this makes it necessary to "warp" the slopes.
Whenever there will be a berm under any of the spans, its elevation should be such that there is a minimum of 4 feet clear between the ground line and the bottom of the girder as shown below.
If a rock cut is encountered in the spill slope, a slope of 1:1 may be used to the top of the rock.
751.1.2.2 Wing Lengths
The purpose of wings is to contain and stabilize the abutment fill as the roadway transitions to the bridge. For stream crossings in particular, the wings also protect the abutment during extreme hydraulic events.
The lengths of the wings at the end bents are to be determined prior to the issuance of the Bridge Memorandum. There are two reasons for this. First, the district will use these lengths to determine the placement of their guardrail (bridge anchor section). Second, if the lengths of the wings exceed 22 ft. for seismic design category A or 17 ft. for seismic design category B, C or D, they will have to be broken into a stub wing and a detached wing wall. If this happens, then you will need to include this extra cost in your Preliminary Cost Estimate and request soundings for the wall. The request for soundings for the wall should include a request for the determination of the allowable bearing of the soil (if in cut - assume piling if it is in fill) and the angle of internal friction for the material retained by the detached wing wall. Also include the bottom of wing footing elevation.
In order to use a standard end section for Type D barrier on a short turned-back wing, consider increasing the wing length so that the barrier end section is at least 8 feet long.
Unequal Wing Lengths
Wing lengths at each end of a bridge could be unequal because of several factors: grade of roadway under, superelevation of bridge, skew of the bridge, and/or other ramps/roads/slopes adjacent to the bridge structure, e.g., stream access roads or unusual geomorphic conditions.
Set/determine the wing lengths using the control points, as shown in Embankment at Bridge Ends, which may be used for both grade separations and stream crossings. This is done after the end bent location is determined. If estimated wing lengths are within 3 ft., they should be made equal and based on the longer wing length. Make sure no slope is steeper than that recommended in the geotechnical preliminary report. Slightly flatter slopes are acceptable. The contractor will warp the slopes to fit the wing tip locations.
Equal wing lengths are preferable at stream crossings to mitigate scour, improve erosion control and improve/mitigate parallel water flow along wing and side embankment. Also, since wing lengths are reported to districts for use in estimating rock slope protection limits, unequal lengths (especially on the upstream side) could mistakenly lead to the unfavorable condition of allowing for less than adequate rock side slope protection.
Judgement is required since no two estimated wing lengths at a bridge end will be exactly equal. More often equal wing lengths are used.
On divided highway bridges with high skews and shallow end slopes, the wing lengths on the median side of the bridge may be less than the other side due to the difference in sideslope between the median and the outside.
751.1.2.3 Live Load Determination
The live load requirements for a structure shall be HL-93
On box culverts, the actual live load applied to the structure is dependent upon the amount of fill on top of the box; however, see Structural Project Manager for the live load that goes on the Bridge Memorandum.
751.1.2.4 Skew Angle
Determining the most appropriate skew angle for the structure involves some judgement. On bridges over streams, pick the angle that will allow floodwater to pass through the bridge opening with the least amount of interference from intermediate bent columns. Another consideration on meandering streams is to avoid a skew which will cause the spill fill – side slope transition from blocking the stream. Often a trip to the field may be justified just for determining the angle (you can even ask the district to stake some different skews for you to observe in the field).
On stream crossings, avoid skews between zero and five degrees and try to use five-degree increments. On grade separations, often the skew must be accurate to the nearest second to maintain minimum horizontal clearances.
Keep all bents on a bridge parallel whenever possible and avoid skews over 55 degrees (30 degrees for adjacent prestressed concrete beams). Also keep in mind that the higher the skew, the higher the Preliminary Cost Estimate due to the beam caps and wings being longer.
751.1.2.5 Bridge Width
For bridge width requirements, see EPG 231.8 Bridge Width.
751.1.2.6 Vertical and Horizontal Clearances
751.1.2.6.1 Grade Separations
Minimum Design Clearances for New Bridges | ||
---|---|---|
Facility Under Bridge | Vertical Clearance under Superstructure1 | Horizontal Clearance |
Interstate and Principal Arterial Routes | 16’-6” over roadway including auxiliary lanes and shoulders | Clear zone clearances from the edge of the traveled way (includes shoulders and auxiliary lanes) are obtained from the District Design Division. The vertical clearance is required for the full width of the clear zone. Barrier is required if unable to locate obstacles outside clear zone (columns, beams, walls, coping, 3:1 [1V:3H] slopes or steeper). If a barrier is required the minimum distance to the barrier shall be specified on the Bridge Memorandum as the horizontal clearance otherwise the clear zone clearance shall be used. See EPG 751.2.2.6 Other Loads and Standard Plans 606.01, 606.51 and 617.10 for typical barrier and railing options. |
Other State Routes with Volumes ≥ 1700 vpd | 16’-6” over roadway including auxiliary lanes and shoulders | |
Other State Routes with Volumes < 1700 vpd | 15’-6” over the roadway including auxiliary lanes and shoulders2 | |
Other Streets and Roads | 14’-6” (15’-6” commercial zones) over the roadway including auxiliary lanes and shoulders2 | |
Railroads | 23’-0” inside 18’-0” opening or as required by railroad (23’-4” for UPRR, 23’-6” for BNSF)3 | 14’-0” and 22’-0” from centerline4,5 (25’-0” eliminates collision walls) |
1 Roadway vertical clearances are based upon AASHTO minimums with an additional 6 inches to accommodate future resurfacing of the roadway. An additional 1 ft. is required for pedestrian overpass facilities over roadways. Vertical clearances shown are also applicable when the facility under the bridge is being carried by a bridge. 2 To provide continuity of travel for taller vehicles exceptions can be made both rural and urban for any routes connecting to the systems where taller vehicles are allowed but not to exceed 16.5 feet. 3 Clearance is measured from the top of rails (from top of high rail on superelevated track). The required 18-ft. opening centered on the track shall be increased on each side of centerline 1.5 inches per each degree of curvature for any track crossed. 4 Fourteen feet is a preferred minimum. The absolute minimum is 9 ft. from the centerline plus 1.5 inches per each degree of any track curvature. 5 The minimum clearance of 22 ft. to be provided on one side of the track(s) is for off-track maintenance. If it is not obvious on which side of the track(s) this clearance is provided, a decision should be obtained from railroad's local representative. Assistance from Multimodal Operations may be required in some situations. |
Clearance over Traffic During Construction (New and Existing Structures) |
---|
Roadways: Consult with the structural project manager or the structural liaison engineer and the district contact for minimum allowable vertical and horizontal clearance. Vertically this is usually 12 to 18 inches below the final minimum vertical clearance. Horizontally this is usually a minimum number of lanes or minimum size of opening required during the project while specifying the locality of the opening (e.g. centered on existing lanes, two 12-ft. lanes minimum in each direction, etc.). These clearances shall be specified on the Bridge Memorandum to be used in the note required on the final plans. For note see EPG 751.50 A3. All Structures. |
Railroads: If feasible, 15 ft. horizontally from centerline of track and 21.5 ft. vertically from tops of tracks (from top of high rail on superelevated track). If either of these clearances is not feasible then obtain acceptable clearances from the railroad projects manager. For the detail required on the final plans showing minimum clearances during construction over railroads, see EPG 751.5.2.1.2.7 Features Crossed. |
Deficient Vertical Clearances on Interstates |
---|
Refer to EPG 131.1.7 Deficient Vertical Clearances on Interstates for information about coordinating minimum vertical clearance for grade separation structures with the Defense Department. |
751.1.2.6.2 Stream Crossings
For vertical clearance on stream crossings, see EPG 748.3 Freeboard.
751.1.2.7 Structure Type Selection
Both steel and prestressed concrete girders shall be considered on all structure type selections. As the required span length of the structure increases to bridge the obstruction, deeper girder sections will be required. As a general rule of thumb, span to superstructure depth ratios (S/D) will be on the order of 20 to 30 with the higher numbers being slender, flexible structures.
Preliminary designers should consider these structure types as the span length increases with the top of the list providing the least amount of span capability. Economic consideration should be given to the selection of steel or concrete superstructures. Recent and relevant bid history for each structure type should be reviewed during the preliminary design phase.
- Concrete Box Culvert (single, double or triple cell)
- Prestressed or Reinforced Concrete Slab
- Adjacent Prestressed Concrete Box or Voided Slab Beams (with approval of Structural Project Manager)
- Shallow Depth Girder Sections: Wide Flange Steel Beams, Spread Prestressed Concrete Beams (Box or Voided Slab), Prestressed I-Girders (Type 2, 3, 4 or 6), or Prestressed NU-Girders (PSNU-35 or PSNU-43)
- Intermediate Depth Girder Sections: Plate Girder, Prestressed Bulb-Tee Girder (63.5” or 72.5") or Prestressed NU Girder (PSNU-53, 63, 70 or 78)
- Deep Girder Sections: Plate Girder (greater than 78” web depth)
Voided slab beams are currently only produced by one manufacturer and therefore a long transport may need to be considered in the bridge memo estimate.
Often site conditions warrant the use of shallower depth girder sections to maximize vertical clearance over roads or railroads or to maximize freeboard over streams. When contemplating these situations, the preliminary designer should work with the district highway designer to provide several structure depth options with corresponding roadway profile grade raises. It may be that a more expensive bridge structure results in an overall minimized project cost. High strength concrete or high-performance steel grades may allow the preliminary designer to span longer distances with shallower structures. These higher strength materials may also be used to eliminate girder lines as roadway width increases.
On multi-span structures, it is generally more efficient to have a balanced span arrangement where the end spans are approximately 10 percent shorter than the intermediate spans. This type of arrangement balances the positive moment demand at the midspans with the negative moment demand at the intermediate bents and allows optimization of the structural cross section. For example, a span layout of (67’ - 76’ - 67’) is structurally more efficient than (70’-70’-70’).
751.1.2.8 Box Culverts
Most districts prefer a box culvert to a bridge because of the lower maintenance costs; however, if a stream crossing is on the borderline between a box culvert and a bridge, each option should be explored and presented to the district. The presentation to the district should include the cost estimate for each option as well as a recommendation as to which option is preferred by the Bridge Division. Multi-cell box culverts shall be avoided on streams with reported medium to heavy drift because the interior wall creates a snag point and drift will have difficulty passing through the box culvert resulting in clogging and likely undermining of the culvert. Single-cell box culverts may be used if the opening is sized to allow drift to pass. If the stream being crossed is a drainage ditch it is advisable to have the district contact the drainage district to see if they have any specific objections (i.e. drift etc.) to using a culvert at the proposed location. Approval of proposed structure layout by the drainage district may be required, see EPG 747.3.4 Bridge Permits or Approvals by Other Agencies.
751.1.2.8.1 Hydraulic Design
A general rule of thumb for the use of a culvert is that it can handle about 1,000 cfs per cell with 3 cells being the usual maximum. This can vary if the slope of the streambed is unusually flat or steep. Another rule of thumb is that the water from a drainage area of less than 5 square miles can usually be handled by a concrete box culvert. Curves or bends should be avoided when possible. See EPG 750.2.3.2.2 Head Loss Due to Bends when curves or bends will be used.
For details of hydraulic design, see EPG 750.2 Culverts.
Hydraulic designs and plans for some small box culverts are handled by the district. See EPG 750.7.4.3 Summary of Responsibilities for responsibility for analysis, design and final plans preparation.
751.1.2.8.2 Environmental Requirements
See EPG 750.7.3 Environmental Requirements for details of embedment, velocity and conveyance requirements.
751.1.2.8.3 Layout
751.1.2.8.3.1 Size
When sizing the proposed concrete box culvert, use Standard Box Culvert Sizes whenever possible. For information on standard box culverts sizes, see EPG 750.7.4.1 Standard Plans. For additional information on culvert size, see EPG 750.7.4.4 Size.
751.1.2.8.3.2 Length
The inside face of the headwall is located at the intersection of the roadway fill slope and the top of the top slab of culvert. Typically, the longest barrel is produced considering this intersection point upgrade. Flared inlets, varying roadway widths, clear zones and guardrail placement are possible exceptions to this rule.
When clear zones are provided, locate the inside face of the headwalls of the culvert at or beyond the edge of the roadway clear zone. In situations of very low fill, contact the district to determine if the use of guardrail is preferred to placing the headwalls beyond the edge of the clear zone. When clear zones are not provided the district will determine the need for guardrail on a case by case basis. Typically when guardrail is to be used over a culvert the typical section will show a 3’-5” shoulder widening as shown in Standard Plan 606.00. Consult the district if it is unclear whether adequate clear zones are provided or if guardrail is to be used over a box culvert. If the fill over the culvert is shallow, guardrail attachment may need to be provided. It may be advisable to lengthen culverts with shallow fill slightly to provide room for future guardrail attachments if guardrail over the box culvert is not provided.
751.1.2.8.3.3 Roadway Fill
Minimum roadway fill height is determined at the outside shoulder line and is the greater of 1 ft. or the thickness of the pavement and base material specified in EPG 750.7.11.1 Minimum Fill Heights. Pavement and shoulder widths and thicknesses are determined on a project by project basis. Pavement and shoulder details (i.e., width, thickness, alternate pavement options) can be obtained from the district if needed, but based on maximum pavement thicknesses and minimum shoulder widths, fill heights at the outside of the shoulder of 20 ½” or greater on major routes or 14 ½” or greater on minor routes will not require pavement or shoulder details. For more information on pavement and shoulder widths and thicknesses see Other Aspects of Pavement Design and EPG 231 Typical Section Elements of Roadways.
Roadway fill outside of the shoulders shall be warped (in the past this was referred to as the fill being “rolled up and over”) to provide a minimum of 12 in. of cover where the top of the culvert could be exposed. A standard note should be shown on the Bridge Memorandums (Memos) regarding warping the roadway fill. Cases where this could occur are:
- 1. Culvert ends with shallow fill and headwalls located outside of the clear zone.
- 2. Median of a divided highway with shallow fill.
- 3. Flared Inlets
- 4. Auxiliary lane or outer road with skews different than that of the mainline
- 5. Steep grade with a wide or skewed culvert.
For additional information of roadway fill, see EPG 750.7.11 Overfill Heights.
751.1.2.8.3.4 Fill Settlement
Check the Preliminary Geotechnical Report for recommendations concerning fill settlements and the use of collar beams on longer box culverts. Cambering of the culvert should also be considered when fill settlements are appreciable. For more information, see EPG 750.7.9 Camber in Culverts.
751.1.2.8.4 Precast Box Culvert Sections
If the use of precast box culvert sections will not be allowed to be substituted for cast-in-place construction or if precasting is required it should be noted on the bridge memorandum and on the bridge plans.
Precast option for box culvert extensions will be permitted using a cast-in-place connection where the centerline of new cells is not laterally displaced more than 15° (maximum) from the centerline of existing cells for each cell extension.
751.1.2.8.5 Abrasion
If a culvert requires design for abrasion it should be noted on the bridge memorandum. For more information see EPG 750.7.4.2 Abrasion of Interior Surfaces.
751.1.2.9 Girder Type Selection
Once it has been determined that the structure will have girders, the types of girders to be used must be identified. To check the vertical clearance or freeboard, the maximum span length of each type of girder must be known. See EPG 751.22 P/S Concrete I Girders or EPG 751.14 Steel Superstructure. Adjustments will need to be made if the span ratios become greater than 1.25.
If it is determined that the roadway profile grade will need to be raised (or lowered) to provide additional vertical clearance or freeboard, the preliminary designer should notify the district contact as soon as possible. It is best to provide the district with several options of varying profile grade elevation increase with varying structural depth. Larger grade elevation increases typically result in longer bridges as spill slopes dictate bridge length. The preliminary designer and district contact should work together to minimize the overall project cost even if the bridge cost is slightly more expensive. Consider the various structure types listed in EPG 751.1.2.7 Structural Type Selection when selecting the girder type. Also consider that adding girder lines or using higher strength material (concrete or steel) may allow longer or shallower spans for a given girder cross section. As a last resort, request a design exception for the substandard item.
751.1.2.9.1 Concrete Girder Options
Prestressed girder selection should use the following order for trial sizing and spanning:
- Prestressed or reinforced concrete slab beams
- Prestressed Concrete Box Beams
- MoDOT Standard Prestressed Girders Type 2, 3, 4 and 6
- NU Standard Prestressed Girders Type 35, 43, 53, 63, 70 and 78
- MoDOT Bulb-Tees Type 7 and 8
For span lengths longer than 125 feet for prestressed concrete, the girders become very heavy and are difficult to transport to the site and often require two or more large cranes to place on the supports. The preliminary designer should discuss this with the district, and have it documented on the Constructability Questionnaire noted in EPG 751.1.2.18.3 Supporting Documents.
751.1.2.9.2 Steel Girder Options
When considering steel structures, the preliminary designer must decide if the girders should be painted or fabricated from weathering steel. If site-specific conditions allow, the use of unpainted weathering steel (ASTM A709 Grades 50W and HPS70W) should be considered and is MoDOT’s preferred system for routine steel I-girder type bridges due to its performance, economic and environmental benefits. Cost savings are realized because of the elimination of the initial paint system as well as the need for periodic renewal of the paint system over the life of the structure.
Weathering steels provide significant environmental and worker safety benefits as well. Since they do not require initial and periodic repainting of the whole bridge, emissions of volatile organic compounds (VOC) are reduced. Also, they generally do not require coating removal or disposal of contaminated blast debris over the service life of the structure. By eliminating the need for periodic repainting, the closing of traffic lanes can be prevented as well as the associated hazards to painters, maintenance workers, and the travelling public.
Partial coating of weathering steel is required near expansion joints. See EPG 751.14.5.8. Periodic recoating or overcoating will be required, however, on a much smaller scale than the whole bridge with the effect that lane closures and associated hazards are greatly reduced compared to painted steel.
Although weathering steel is MoDOT’s preferred system for routine I-girder bridges with proper detailing, it should not be used for box girders, trusses or other structure types where details may tend to trap moisture or debris. There are also some situations where the use of weathering steel may not be advisable due to unique environmental circumstances of the site. Generally, these types of structures would receive high deposits of salt along with humidity, or long-term wet conditions and individually each circumstance could be considered critical.
The FHWA Technical Advisory T5140.22 October 1989 should be used as guidance when determining the acceptability of weathering steel. Due to the large amounts of deicing salts used on our highways which ultimately causes salt spray on bridge girders, the flowchart below should be used as guidance for grade separations. The flowchart, Fig. 751.1.2.9, below, is general guidance but is not all inclusive. There may be cases based on the circumstances of the bridge site where the use of weathering steel is acceptable even though the flowchart may indicate otherwise. In these cases, follow MoDOT’s design exception process.
Weathering steel may be used for stream crossings where 1) the base flood elevation is lower than the bottom of girder elevation and 2) the difference between the normal water surface and bottom of girder elevations is greater than 10 ft. for stagnant and 8 ft. for moving bodies of water. Where the difference in elevations is less than noted, weathering steel may be used upon approval of the Assistant State Bridge Engineer.
Additional documents that can be referenced to aid in identifying the site-specific locations and details that should be avoided when the use of weathering steel is being considered include:
- 1. Transporation Research Board. (1989). Guidelines for the use of Weathering Steel in Bridges, (NCHRP Report 314). Washington, DC: Albrecht, et al.
- 2. American Iron and Steel Institute. (1995). Performance of Weathering Steel in Highway Bridges, Third Phase Report. Nickerson, R.L.
- 3. American Institute of Steel Construction. (2022). Uncoated Weathering Steel Reference Guide. NSBA
- 4. MoDOT. (1996). Missouri Highway and Transportation Department Task Force Report on Weathering Steel for Bridges. Jefferson City, MO: Porter, P., et al.
The final brown rust appearance could be an aesthetic concern. When determining the use of weathering steel, aesthetics and other concerns should be discussed by the Core Team members, with input from Bridge Division and Maintenance Division.
If weathering steel cannot be used, the girders should be painted gray (Federal Standard #26373). If the district doesn’t want gray, they can choose brown (Federal Standard #30045). If the district or the local municipality wants a color other than gray or brown, they must meet the requirements of EPG 1045.5 Policy on Color of Structural Steel Paint. System G paint is the preferred system on all steel plate girders. See EPG 751.6.2.11, EPG 751.6.2.12 and EPG 751.14.5.8 for further guidance on paint systems.
751.1.2.10 Longer Bridges
For bridges that are longer than normal (more than 6 spans being a general rule of thumb), other items must be considered. If the feature you are crossing allows flexibility in bent placement, the most cost-efficient span length is one that will result in the cost of one span's superstructure being equal to the cost of one bent. For example, calculate the cost of one intermediate bent, and then adjust the length of the span until the cost of the girders, slab and curb equal the cost of the bent. The use of higher strength concrete in Prestressed I-Girders or high performance steel in plate girders can allow spans to be increased approximately 20% as a means to eliminate intermediate bents.
Another item to consider is the placement of expansion devices. Be sure to include the costs of the expansion devices and deadman anchors (if applicable) in your Preliminary Cost Estimate.
751.1.2.11 Staged Construction
If the new structure being laid out replaces an existing structure on the same alignment, the default method of handling traffic during construction is to close the road and detour traffic. The new substructure should be spaced to avoid the existing substructure units if at all possible.
If the district determines the road cannot be closed, the options for handling traffic include staged construction or using a temporary bypass. If a temporary bypass is used, determine whether the district can size some drainage-diversion pipes for the bypass. If the district decides pipes cannot be used, then a temporary bridge is necessary, and a separate Bridge Survey/Memo/Bridge No. is required.
If the district decides to use staged construction, one important item to verify in this situation is that the new girders will clear the existing substructure. Another item to consider in setting up the staging is the placement and attachment requirements of the temporary concrete traffic barrier relative to the bridge deck and meeting horizontal distance requirements from the edge of the deck, which determines whether the temporary concrete traffic barrier is attached to the deck and how it is attached.
- For staged bridge construction with MSE walls at the abutments, consider specifying location of temporary MSE walls on the plan details. The interior angle between MSE walls and temporary MSE walls should be greater than 70°. However, if unavoidable, then interior angle shall be absolute minimum 65°. Temporary MSE wall option for staged bridge construction shall not be used when bridge skew is greater than 25°.
Sometimes due to limited space or to retain improved foundation material or to retain existing slope contractor may need to provide temporary shoring prior to constructing temporary MSE wall systems in staged construction, but only the temporary MSE wall should be indicated on the plans. For design requirements of MSE wall systems, see 720 Mechanically Stabilized Earth Wall Systems.
751.1.2.12 Temporary Barriers
Bridge Plans must note whether temporary concrete traffic barrier is attached or freestanding, and if attached, whether they are attached with tie-down straps or bolt through deck attachment. Coordination is required with district Design. See EPG 617.1 Temporary Traffic Barriers for more guidance.
- a. Where sufficient distance is available to accommodate lateral deflection of barriers: No attachment is required. Note on plans as “Freestanding” or “No attachment required”.
- b. Where sufficient distance is not available to accommodate lateral deflection of barriers: Tie-down strap system is required. (Refer to Standard Plan 617.20.) Coordinate with district Design to provide a minimum of four connected temporary concrete traffic barrier sections on approach slab roadway.
- c. Where lateral deflection cannot be tolerated: Bolt through deck system is required. (To be used only on existing decks that will be removed and that have sufficient strength.) (Refer to Standard Plan 617.20.) Coordinate with district Design division for required transition barrier attachments that may be used on any deck, existing or new, where lateral deflection is not permitted with approval of the Structural Project Manager or Structural Liaison Engineer.
For all other applications of a freestanding temporary concrete traffic barrier, the preferred installation method requires a 2 ft. buffer area behind the barrier to allow for lateral deflection in both work areas and lane separation situations.
Regardless of deflection distance (buffer area) available, if the bridge deck is super elevated or has a large roadway slope, a freestanding temporary concrete traffic barrier should not be used because the barrier has the potential for movement (“walking”) due to gravity forces and vibrations acting on the barrier.
When a temporary concrete traffic barrier is adequately attached to a bridge deck (refer to Standard Plan 617.20) a minimum distance of 6 in. shall be provided from the edge of the bridge deck to the face of the barrier.
751.1.2.13 Seismic (Earthquake) Design Category A, B, C and D Considerations
See EPG 751.9 Bridge Seismic Design for seismic design and detail requirements in accordance with SGS, and LRFD. Utilize provided flow charts.
All new or replacement bridge/wall designs, either nonseismic (meaning a regular static design) or seismic design or detail, must meet Seismic Design Category (SDC) A requirements in accordance with SGS (Seismic Zone 1 of LRFD). Additionally, where applicable bridge seismic designs/details/analysis must meet requirements of the Seismic Design Category B, C, or D in accordance with Bridge Seismic Design Flowchart.
For laying out new or replacement bridges in SDC A, B, C or D (per SGS), the following is important.
- Box culverts are preferable to bridges on stream crossings because they are exempt from seismic design unless crossing a known exposed fault.
- Pile cap intermediate bents and drilled shafts are preferable to open column bents on footings because footings can grow quite large due to seismic forces.
- Minimize the number of expansion joints in the deck because each of these locations may require earthquake restrainers which are very costly.
- Make the superstructure as light as possible, which usually means use steel plate girders or wide flanges instead of prestressed concrete girders where possible.
The new or replacement bridge design schedule for a complete seismic analysis requires 24 months minimum and bridge design schedule for seismic details and/or abutment seismic design requires 13 months minimum. Additional 2 - 3 months is required for review and letting process before the schedule letting. See EPG 751.1.1.5 New Regular Bridge Design Schedule (Nonseismic) (Nonrailway Crossing).
751.1.2.14 Temporary Bridges
If the district will be using a bypass on stream crossings, a temporary bridge may be necessary. The district should first consider using large drainage-diversion pipes to carry the water under the bypass, if the district determines this is not practical, they should submit a Bridge Survey for a temporary bridge on the bypass. Check with the Structural Project Manager for hydraulic design frequency.
Once the number of 40’ spans has been determined, the district should be contacted so they can locate the pieces necessary for the construction of the bridge. Make sure the pieces the district intends to use have the “new” beam caps that take 14” H-pile. The district should provide you with the location of where the pieces are coming from and where they should be taken by the contractor at the end of the project. If the district is unable to find the pieces, then they will need to be contractor furnished. This has a big impact on costs. See Preliminary Cost Estimate.
751.1.2.15 Bridges Over Railroads
Consult the AREMA (American Railway Engineering and Maintenance-of-Way Association) Manual for Railway Engineering located in the Bridge Division’s Development Section for more detailed information. Here are some basic points to keep in mind:
- Railroads often raise their tracks so provide some cushion in your vertical clearance.
- Absolute minimum horizontal clearance shall be 9 feet on each side of track centerline plus 1 1/2 inches per each degree of track curvature. (railroad projects manager of the Multimodal Operations Division will obtain the degree of curvature from the railroad)
- Will the railroad want room for an extra track or maintenance roadway?
- Keep the ballast free drained.
- Drainage needs to be designed for 100-year storm.
- Slope protection shall consist of Type 2, 18-inch thick rock blanket placed on top of permanent erosion control geotextile. Some railroads may require changes to this; however, this will be determined on a case-by-case basis.
- Some railroads also now require the barrier and slab overhangs to be designed to accommodate fences that may be added in the future.
If the face of the columns of an intermediate bent is within 25 ft. of the centerline of the railroad track, a collision wall is required. If the face of the columns of an intermediate bent is within 12 ft. of the centerline the top of the collision wall shall be set at 12 ft. above top of rail otherwise the top of the collision wall shall be set at 6 ft. above top of rail.
The railroad projects manager in the Multimodal Operations Division is a very good resource for answering questions at any stage of the layout. It typically takes a very long time to receive approval of a layout from the railroad. The railroad must approve both the preliminary design and the final plans.
When making a submittal to the railroad project manager for approval of the preliminary design, include three sets of half-sized plat and profile sheets, as well as a copy of the Design Layout.
The new bridge design schedule for a railway crossing bridge requires 24 months minimum. See EPG 751.1.1.5 New Regular Bridge Design Schedule.
751.1.2.16 Historical Bridge Considerations
You also need to check with the Historical Bridge Coordinator in the Design Division when replacing a bridge. There is not a magic age for a bridge for it to become "historical". Age does not matter. All "Bridge Resources" that will be impacted by MoDOT need to be cleared through the Department of Natural Resources (DNR) Historic Preservation Program (HPP) before they can be replaced, demolished, extensively rehabilitated or deeded to a new owner (county, city, etc.). The following is a definition of "Bridge Resources":
- "Bridge Resources are both public and privately owned highway, railroad and pedestrian bridges, viaducts and culverts. This does not include metal and plastic pipes, unless they are encased in an older concrete, stone or brick structure."
The following is the information on this topic supplied to the district (FYI):
- "Bridge Resources on any given job or location study need to be checked out and cleared just like historic buildings (architecture) and archaeological sites. Standard size color photographs can be submitted to the Historic Bridge Coordinator directly and/or attached to the Request for Environmental Assessment (RES) or Questionnaire to Determine Need for Cultural Resources Assessment. The Historic Bridge Coordinator will then determine and execute procedures for clearance, if required."
Bridges that are older than 50 years stand a better chance of being evaluated as eligible for the National Register of Historic Places (NRHP) in Clayton Fraser's 1996 draft Missouri Historic Bridge Inventory. This is a study that was undertaken under STURAA (Surface Transportation and Uniform Relocation Assistance Act of 1987) in order to inventory all potentially NRHP eligible historic bridges in the state. Any of these that are determined NRHP eligible by the HPP will require special mitigation (or avoidance) if they are to be affected by project activities. For this reason, it is important that all bridge resources be identified early in the process.
Usually, bridge resources do not stand in the way of right of way acquisition (A-dates) because they are generally located on roadways that the state already owns; however, there are cases in which bridge resources are privately owned and located on private property. In these rare cases, bridge resources would need to be checked out prior to our right of way acquisition approval.
751.1.2.17 Preliminary Cost Estimate
Box Culverts – A new or replaced box culvert is exempt from seismic design unless crossing a known exposed fault. Submit “Request for soil properties Form A” to Geotech Section and design as a SDC A. If box culvert is crossing a known exposed fault then discuss with Structural Project Manager (SPM) for alternate option.
Bridges and Retaining Walls – For a new or replaced retaining wall or bridge, review Bridge Seismic Planning Flowchart, Bridge Seismic Design Flowchart, preliminary seismic design map and following information.
- Seismic design of overpass should be considered when overpass bridge collapse would greatly impede emergency traffic for the main route. (i.e., No access ramps on a major route or a 1st or 2nd priority earthquake emergency route).
- For preliminary planning and cost estimate use the SDC values shown on preliminary seismic design map. SDC boundaries are shown for soil site class D.
- Site class verification is not required for bridges located in regions SDC A1 or A2, so the preliminary SDC shall be used for plans reporting.
- In the normal design schedule, the Geotechnical section will determine the site class and an accurate SDC, SD1, As for bridges located in the regions encompassed by SDC B, C and D on the preliminary seismic design map. Typically, the SDC will remain the same as shown on the map or get dropped to a lower SDC (e.g., D to C, C to B, B to A2).
- If a bridge gets downgraded to SDC A2 after Geotech analysis and carry a 1st or 2nd priority earthquake emergency route, the bridge shall receive seismic details similar to SDC B. If a bridge gets downgraded to SDC A2 after Geotech analysis and does not carry a 1st or 2nd priority route, it will not require seismic details. If a bridge gets downgraded to SDC A1 after Geotech analysis, it will not require seismic details. Typically, downgrades may result in a reduced project schedule and/or a reduced cost estimate for the bridge.
- Geotechnical section will perform a liquefaction assessment for bridges with a final SDC of C or D and carry a major route or 1st or 2nd priority earthquake emergency route.
Seismic design category (SDC) is divided in SDC A (SD1 < 0.15), SDC B (0.15 ≤ SD1 < 0.30), SDC C (0.30 ≤ SD1 < 0.50) and SDC D (SD1 ≥ 0.50). SDC A is subdivided into SDC A1 (SD1 < 0.10) and SDC A2 (0.10 ≤ SD1 < 0.15). Submit “Soil properties Form A” to Geotech Section for SDC A1 and SDC A2 area bridges, retaining walls and box culverts. Submit “Soil properties Form A” and “Soil properties Form B” to Geotech Section for SDC B, C and D area bridges and retaining walls. For soil properties form, see EPG 751.1.2.19 Soundings (Borings).
The Preliminary Cost Estimate should be neat, legible and dated since a copy of it is included with the Bridge Memo. It should also be rounded to the nearest thousand dollars.
The accepted method of calculating the Preliminary Cost Estimate is to calculate some approximate quantities for the bridge and then multiply them by the unit prices supplied by the Bridge Division Preliminary and Review Section. A spreadsheet should be used to calculate these quantities. To estimate the pounds of reinforcing steel in a structure, multiply the number of cubic yards of concrete in the structure by 125 for bridges. See table below for Box Culverts.
Table 751.1.2.17, Box Culvert Reinforcing Steel (lbs.) Estimate | |
---|---|
Design Fill (ft.) | Concrete (lbs/cy) Multiplier |
2.00 | 225 |
6.00 | 168 |
10.00 | 116 |
25.00 | 96 |
32.00 | 84 |
The Preliminary Cost Estimate should be increased for the following items: Cost Estimate Guide for rural preliminary design (do not compound all increases using your judgment).
Bridge in SDC boundaries on preliminary seismic design map |
% Cost Increase | Comments for final SDC |
SDC A1 SDC A2 (nonseismic) SDC A2 (seismic details) |
0 0 10 |
No cost increase for SDC A1 area bridges and most of the bridges in SDC A2 area. If a bridge carry a 1st or 2nd priority earthquake emergency route and located in SDC A2 area, it will receive seismic details similar to SDC B (i.e. 10% increase). |
SDC B (single span, seismic details) SDC B (single span, abutment seismic design) SDC B (multi-span) |
0 5 10 |
Cost increase is for seismic details in accordance with the 2023 AASHTO Guide Specifications for LRFD Seismic Bridge Design. If bridge receives a final SDC B and carries a major route or 1st or 2nd priority earthquake emergency route then abutments will be designed for mass inertial forces per SEG 24-02. (i.e. 0 to 5% increase for single span bridges). If a bridge gets downgraded to SDC A2 and does not carry a 1st or 2nd priority route, it will not require seismic details. If a bridge gets downgraded to SDC A1 after Geotech analysis, it will not require seismic details (i.e. no cost increase). |
SDC C (single span, seismic details) SDC C (single span, abutment seismic design) SDC C (multi-span, seismic details) SDC C (multi-span, complete seismic analysis) |
0 5 10 25 |
25% cost increase is for complete seismic analysis. All bridges receiving a final SDC C and not carrying a major route or 1st or 2nd priority earthquake emergency route will only receive seismic details (i.e. 10% increase). If a bridge carries a major route or 1st or 2nd priority earthquake emergency route, gets downgraded to SDC B, it will only receive seismic details and abutments will be designed for mass inertial forces per SEG 24-02 (i.e. 10% increase).If single span bridge receives a final SDC C and carries a major route or 1st or 2nd priority earthquake emergency route then abutments will be designed for mass inertial forces per SEG 24-02 (i.e. 0 to 5% increase). |
SDC D (single span, seismic details) SDC D (single span, abutment seismic design) SDC D (multi-span, seismic details) SDC D (multi-span, complete seismic analysis) |
0 10 10 40 |
40 % cost increase is for complete seismic analysis. All bridges receiving a final SDC D after Geotech analysis and do not carry a major route or 1st or 2nd priority earthquake emergency route will only receive seismic details (i.e. 10% increase). If a bridge carries a major route or 1st or 2nd priority earthquake emergency route, gets downgraded to SDC B, it will only receive seismic details and abutments will be designed for mass inertial forces per SEG 24-02 (i.e. 10% increase). If a bridge carries a major route or 1st or 2nd priority earthquake emergency route, gets downgraded to SDC C, it will receive a complete seismic analysis (i.e. 25% increase). If single span bridge receives a final SDC C or D and carries a major route or 1st or 2nd priority earthquake emergency route then abutments will be designed for mass inertial forces per SEG 24-02 (i.e. 5 to 10% increase). |
Item % Cost increase Staged Construction (SDC A) 10 Horizontally Curved (SDC A) 5 Tight Site/Limited Access 3
The following are guidelines for estimating the cost of the removal of existing bridges:
Type of Bridge Removal Cost per Square Foot Simple Structures Over Streams ** Girder Structures Over Roads ** Conc. Slab Structures Over Interstates ** (Quick opening of lanes to traffic)
Consult Bid Tabs for an analysis of the latest bridge removal costs. Bridge Division staff may consult the Pay Item Spreadsheet maintained by the Structural Review Engineer or see EPG 751.6.1 Index of Quantities.
751.1.2.18 Bridge Memorandums
Bridge Memorandums are generated for new and rehabilitated bridge structures including retaining walls. Formal correspondence will not be required for special structural work or miscellaneous structures like high mast tower lighting (HMTL) or small retaining walls equal to or shorter than 5 feet; however, documentation such as a Bridge Memorandum may be a good idea in order to effectively communicate the understanding and agreement to the level of design work proposed and associated construction costs with districts.
751.1.2.18.1 Purpose
The Bridge Memorandum is the instrument which coordinates bridge plan and roadway plan preparation. It is sent to the district to inform them where we plan to put the bridge, what kind of structure it will be, what the Preliminary Cost Estimate is and any other pertinent information. More information is required on more complicated structures. If you are not sure if the district needs to have a certain piece of information concerning the structure, include it on the Bridge Memorandum to be safe. Too much information is better than too little.
An electronic copy of the bridge memorandum and supporting documents are sent to the district for review and signature. If, during the design process, revision to the bridge memorandum by either the district or the Bridge Division becomes necessary, all parties to the memorandum are to be notified immediately. The proposed revisions must be agreed to by all parties that signed the original bridge memorandum.
The Bridge Memorandum also serves as a design layout for structures where the latter is not required, see EPG 751.1.2.31 Finishing Up Design Layout.
751.1.2.18.2 Content
Sample listing of what to include on the Bridge Memorandum:
1. Identify the following classifications if applicable: (Design Implications)
- • All routes involved shall be classified as either:
- o (major), as shown in link.
- o (minor), not a major route and ADT ≥ 400.
- o (low volume), not a major route and ADT < 400.
- • Major bridges with a total length ≥ 1000 feet shall be classified by specifying “(major)” behind the specified bridge number.
- • Priority 1 or 2 earthquake emergency routes shall be classified by specifying “(priority 1 2 EQ)” behind the route classification.
- • All routes involved shall be classified as either:
2. Identify type of structure, span lengths, skew, loading, roadway width, wing lengths and special end fill considerations. For curved structures, specify how the design span lengths are to be measured i.e., “measured along the CL of Roadway”. If plate girder or wide flange beam, further identify them as either weathering or painted steel.
3. Indicate all pertinent profile grade, alignment and superelevation transition information.
4. Identify the fill exception stations or ends of the bridge. The district uses this to coordinate the bridge with their roadway design features such as guardrail. For PSI-Girder bridges, take into account the layout length when calculating these stations.
5. Identify slopes at end bents.
6. Indicate elevation of any berms to be constructed at the end bents.
7. If applicable, call for old roadway fill to be removed to natural ground line.
8. For box culverts, indicate the location of the headwalls and the type of wings to be provided (flared or straight). Also include the upper and lower flow line elevations along the CL of the box.
9. Identify any bridge related items that the district will need to address in their plans or special provisions as a “Roadway Item”.
10. Include the cost estimate for construction (Preliminary Cost Estimate).
11. Include the method of traffic handling while construction is underway. Attach sketches for staged construction when appropriate.
12. For stream crossings, show all pertinent hydrologic data used for the layout of the structure. See EPG 751.5.2.1.5.3 Hydraulic Data for Hydraulic Data tables.
13. For roadway and railroad grade separations, include all minimum vertical and horizontal clearances (final and construction) and include the opening (horizontal limits) of the minimum vertical clearance. The minimum horizontal clearance shall be specified from the edge of the traveled way(s).
14. Quite often, the district will add items to a bridge late in the final design process because they “didn’t think of them” earlier. This often causes extra work due to the necessary redesigns. Include a statement similar to the following to reduce this occurrence:
- "No conduit, lighting, utility supports or sidewalks are to be included in the final plans for this bridge."
- If the district has already indicated that they want special items attached to the bridge, include the specifics on the Bridge Memorandum and modify the above note.
15. The design year AADT (annual average daily traffic) and AADTT (annual average daily truck traffic). Request this from the district if it is not shown on the plat sheet. On grade separations, get the AADT and AADTT for both roads.
16. For box culverts, always include the following notes:
- Channel bottom shall be graded within the right of way for transition of channel bed to culvert openings. Channel banks shall be tapered to match culvert openings. (Roadway Item)
- If any part of the barrel is exposed, the roadway fill shall be warped to provide 12 inches minimum cover. (Roadway Item) (See EPG 751.1.2.8.3.3, Box Culverts, Roadway Fill.)
17. Also for box culverts, state if guardrail (Roadway Item) is to be provided in lieu of meeting the clear zone requirements. If there will be guardrail over the box culvert and the fill height is less than indicated in EPG 750.7.4.5, Box Culverts, Guardrail Attachment, indicate that attachment of the guardrail to the top slab will be handled in the bridge plans, even though the guardrail itself is a roadway item. For additional information on when to use guardrail attachments, see EPG 751.1.2.8.3.2 Length, Box Culvert, Length.
18. For stream crossings (new structures, widened structures and rehabs where the waterway opening is reduced.) include a statement stating that a Floodplain Development Permit is required or that a Floodplain Development Permit is not required and that the Bridge Division will request such a permit if necessary. Also indicate the flood hazard zone (i.e., A, A1, B) and whether or not the bridge is in a Floodway.
19. On Rehabilitated and widened structures give the current and proposed load rating and load posting as well as the current condition ratings for the deck, superstructure, substructure and scour.
20. Identify the bridge approach slab class major or minor. If a design exception is required or approved, then note accordingly. Identify asphalt mix type (determined by district) when the asphalt bridge approach slab sub-class is an option.
21. Identify the bridge end drainage provisions as determined by district Design. For example, note when concrete aprons at each wing wall will be required (Rdwy. Item). Note when concrete approach pavement (Rdwy. Item) with or without drain basins (Rdwy. Item) will be required, or note when rock blanket will be required that extends up to full length of bridge approach slabs, or when drain flumes (Rdwy. Item) will be required.
22. For redecks or in other cases where the rock blanket elevations are not shown on the bridge plans and the top of the rock blanket is required to be flush to the existing ground line in accordance with the Memorandum of Agreement with SEMA, include the following note:
- The top of rock blanket shall be flush to the ground line as directed by the engineer. (Roadway Item.)
23. For retaining walls, indicate any aesthetic treatments such as concrete staining and form liner requirements. Be specific regarding names, types and colors of staining, and names and types of form liner.
24. Form liners are standard for MSE precast modular panel wall systems. Be specific regarding names, types and colors of staining, and names and types of form liner. See Bridge Standard Drawings → MSE Wall - MSEW.
25. For MSE wall supporting abutment fill: Identify gutter type, fencing, lower longitudinal and lateral drain pipe sizes (type and sizes to be determined by district Design division). (Lateral drain pipes are only required as determined by district Design division.)
26. OPTIONAL Seismic Information for new bridge or wall on Memo: Note “Preliminary Seismic Description: Site Class _, Seismic Design Category _, As = __, SD1 = _, _____”. The last blank should be filled with “non-seismic”, “seismic details”, “abutment seismic design”, “seismic details with abutment seismic design” or “complete seismic analysis”. The provided information is subject to change after Geotechnical Report is released. See Bridge Seismic Planning Flowchart. (This is similar to item no. 9 under EPG 751.1.2.31 Finishing Up Design Layout.)
27. For rehabs, redecks, widenings, recoatings and new replacement structures, see EPG 751.1.3.9 Environmental Considerations: Asbestos and Lead for notes to include.
751.1.2.18.3 Supporting Documents
Supporting documents may provide additional information to the district or request additional information from them. Other documents may need to be included, but at a minimum the following documents should be sent to the district with the Bridge Memorandum:
- Calculations used for the Preliminary Cost Estimate
- Constructability Questionnaire, modify to address project issues
- Layout for Soundings
751.1.2.18.4 Bridge Division Review
Once the Preliminary Designer has the Bridge Memo and supporting documents completed, they are submitted to the Structural Project Manager (SPM) for their review. The SPM will then request a Bridge Memo Conference with the Assistant State Bridge Engineer, the Structural Resource Manager and the Structural Prelim. & Review Engineer. After the review and conference, the Preliminary Designer will update the Bridge Memorandum and supporting documents. The Designer and SPM sign and date the memo by typing their names and the date in the locations provided.
751.1.2.18.5 Bridge/District Agreement Process
The following process will be used to establish agreement between the district and Bridge Division on Bridge Memorandums:
- 1) Bridge Memorandums and supporting documentation will be made available on SharePoint by Bridge Division.
- 2) The Bridge Division preliminary designer or Structural Project Manager (SPM) will email the Transportation Project Manager (TPM) and the District Bridge Engineer a link to the Bridge Memorandum in SharePoint when the memorandum is ready for review by the district. (A link to the Constructability Questionnaire, Cost Estimate, Layout for Soundings, and Request for Soil Properties may also be included.) As part of their review the TPM should forward the Bridge Memorandum to the appropriate Resident Engineer to solicit their input on the Memorandum.
- 3) Changes to the Bridge Memorandum should be made in revision mode or with bold blue text for additions and red strikethrough text for deletion of existing text. (Discussion of proposed changes with the Bridge Division preliminary designer and SPM is recommended before making changes.)
- 4) Once the district’s review of the Bridge Memorandum is complete the approving district personnel should type their names, titles and the date in the appropriate locations.
- 5) TPMs or their designees email the Bridge Division preliminary designer and SPM to inform them the district has reviewed and signed the Bridge Memorandum. A summary explaining any of the changes should be included in the email.
- 6) The Bridge Division preliminary designer or SPM will accept the changes or coordinate with TPMs or their designees to resolve any differences.
- 7) Once all differences are resolved the Bridge Division preliminary designer or the SPM will email the TPM or the TPM's designee indicating the agreement process is complete. Changes made to the Bridge Memorandum after the initial agreement may be handled by email or by the process described above.
751.1.2.18.6 Documentation
The Bridge Memorandum, supporting documents and related correspondence will be stored on the Bridge Division SharePoint page in the Projects -Inwork directory.
A copy of the agreed upon bridge memo is placed in the Layout folder. If changes are made after the initial agreement, a copy of the revised memo should be added to the layout folder and the original bridge memo marked as void with the date of revision noted.
751.1.2.19 Soundings (Borings)
Additional Information |
Request for Final Soundings for Structures Form |
Guidance for Request for Final Soundings for Structures Form |
751.1.2.19.1 Purpose
The borings define subsurface conditions at the project site and are used to determine type of foundation (driven piles, pile cap footing, spread footings, drilled shafts), preliminary estimate of pile lengths and engineering design properties.
Note that two types of soundings are typically provided by a soundings investigation.
- 1. Auger Borings - These are the most typical type of soundings provided due to availability of equipment and low cost. This type of boring is generally stopped immediately upon encountering "hard rock". All description of type of soil and rock encountered is determined in the field.
- 2. Core Samples - These are more time consuming and expensive. They are also subject to the availability of the specialized equipment and are therefore provided as sparingly as possible by the soundings crew. Once "hard rock" is encountered at a coring location, drilling is continued for an additional 10 ft. to ensure a consistent layer of actual hard rock (not a boulder). If a void layer is encountered in the additional drilling, the drilling is continued until another 10 ft. of consistent hard rock is encountered. In addition to field determination of soil layer type and performance of the Standard Penetration Test (SPT), samples are returned to the lab for additional tests such as determination of rock quality (% RQD).
751.1.2.19.2 Required Locations
Bridges – Borings should be requested at each bent. For bents on columns, estimate the number and location of the columns for each bent and request borings for these locations.
Box Culverts – Borings should only be requested for Box Culverts on Rock (no bottom slab). Borings should be requested every 10 ft. along the alignment of both exterior walls for single box culverts and along both the exterior and interior walls for multiple cell culverts.
MSE Walls – Borings should be requested at 25 ft. intervals along the baseline of the MSE Wall and at control points along the wall (such as bend lines). For a MSE Wall that wraps around an end bent, consideration should be given as to whether requesting additional borings in a grid pattern between the walls is necessary.
CIP Concrete Retaining Walls – Borings should be requested at 25 ft. intervals along the wall alignment.
751.1.2.19.3 Required Documents
Plan and Elevation/Profile Sheets. Using MicroStation, the proposed structure should be drawn on the bridge survey plan sheet(s). Boring symbols should be placed at all requested boring locations.
To find the Northing and Easting, the "Label Coordinates" tool in MicroStation can be used. The grid factor, projection factor, coordinate system, zone, horizontal datum and vertical datum will be required information necessary for completing the Request for Final Soundings for Structures Form, all of which should have been provided with the bridge survey report.
Plan and Elevation Sheet(s) of Existing Bridge. When applicable.
Request for Final Soundings for Structures Form. The Guidance for Request for Final Soundings for Structures Form is available.
Instructions to Soundings Party included on the form should be similar to the following:
- Bridges – Provide cores at alternating locations with one core per bent. Where rock is not encountered at core sampling locations, make standard penetration tests at 5 ft. depth increments. If rock is encountered at these core locations, provide RQD determinations at 5 ft. depth increments. If a sounding location is not accessible, please provide an alternative sounding as close as possible to the requested location in order to get an accurate representation of soil conditions at the bent line.
- Box Culverts – Provide cores at each location to determine depth and quality of rock. Information will be used to determine structure type (concrete box on rock – without bottom slab) and excavation quantities. If rock is unsuitable for concrete box on rock, discontinue core and sound depth to rock. If sounding location is not accessible, provide an alternate sounding as close as possible to the requested location in order to get an accurate representation of soil conditions along proposed culvert wall.
- Retaining Walls - Request that soundings be taken every 25 ft. along the wall alignment. Soundings shall be made to rock or to a point which is 20 ft. below the bottom of the wall, whichever is higher.
Request for Soil Properties – The request for soil properties is located on a separate tab in the Request for Final Soundings for Structures form.
- Bridges – If there is a possibility that drilled shafts will be used, request borings based on using drilled shafts so the appropriate lab work can be done the first time.
- MSE Walls – The request for soundings for MSE walls should include requests for the angle of internal frictions (Ø) for both the foundation (improved and unimproved) and the retained material.
Due Date – Use the following guidelines when setting a due date:
Project Time Line | Foundation Report Due Date |
---|---|
< 10 Months | Contact Geotechnical Section1 |
≥ 10 Months | 13 Weeks from Submittal Date |
1 Preferred due date should be discussed at the memo conference and the Geotechnical Section contacted to establish a due date. |
751.1.2.19.4 Submittal
The completed Request for Final Soundings for Structures Form and the other supporting documents listed above should be stored in the project's corresponding eProjects folder. (Consultants should contact the Structural Liaison Engineer).
A request for soundings should be sent by email to the Construction and Materials Division. The email shall be addressed to the Geotechnical Engineer and copied to the Geotechnical Director and the Structural Project Manager (or the Structural Liaison Engineer). It should include at a minimum, a link to the SharePoint folder that contains the completed Request for Final Soundings for Structures Form and supporting documents. In addition to the link, any relevant information that may aid the Geotechnical Section in providing the requested borings should be included.
The request for soundings is typically done at the same time that the Bridge Memorandum is sent to the district.
751.1.2.19.4.1 Sounding Information for Seismic Category A, B, C and D
For all new or replacement bridges or walls or structure modification for widening submit Request for Final Soundings for Structures Form (Soil Properties Form A and AASHTO LRFD (SGS) Form B) for LRFD projects. Based on following procedure Geotechnical Section will determine SDC for structures located in SDC B, C and D on Preliminary Seismic Design Map. For all new or replacement box culverts on rock submit Request for Final Soundings for Structures Form (Soil Properties Form A).
- Geotechnical Section will determine SD1 = , AS = , and SDC = ____ using NSHMP Static Data Services (usgs.gov) website. The risk-targeted design spectra returned by this web service are derived from the USGS 2018 National Seismic Hazard Model for the conterminous United States. Designer should use same procedure to create response spectra for bridge seismic design or verifying SDC using Geotechnical section reported site class.
- For example see: Example 1_SDC_Response_Spectra
751.1.2.20 Substructure Type
Once the signed Bridge Memo and the Borings are received, the entire layout folder should be given to the Preliminary Detailer (requested by SPM, assigned by Structural Resource Manager). The Preliminary Detailer will copy the appropriate MicroStation drawings into their own directory. (Do not rename files) Consultants contact Structural Liaison Engineer. The Preliminary Detailer will then draw the proposed bridge on the plat and profile sheets. The bridge should also be drawn on the contracted profile for a perspective of the profile grade relative to the ground line for drainage considerations. The Preliminary Detailer will also generate a draft Design Layout Sheet and then return the layout folder to the Preliminary Designer for review.
The Preliminary Designer will then choose the substructure types for each of the bents. Pile cap bents without concrete encasement are less expensive than column bents but they should not be used at the following locations:
- Where drift has been identified as a problem
- Where the height of the unbraced piling is excessive and kl/r exceeds 120 (kl/r<120 is generally preferred) (take scour into account)
- Where the bent is adjacent to traffic (grade separations)
Encased pile cap bents may be considered if economical. Embed concrete encasement 2 ft. (minimum) below the top of the lowest finished groundline elevation, unless a greater embedment is required for bridge scour. Greater embedment up to 5 or 6 ft. may be considered in situations where anticipated ground line elevation can fluctuate more severely. (Be sure to account for excavation quantities for deeper embedment.) Provision for encasing piles may be considered at the following locations:
- Where drift is a concern and protection is required
- Where larger radius of gyration is necessary and therefore improved buckling resistance for locations where the exposed unbraced column length is large
- Not exclusively where the piles at the pile/wall interface may experience wet/dry cycles and/or excessive periods of ground moisture
For column bents, an economic analysis should be performed to compare drilled shafts to footings with cofferdams. When evaluating the drilled shaft option, keep in mind that if casing is used (see Geotechnical information) it should extend at least as high as the elevation that would be used for the seal course design. Also keep in mind that the permanent casing should be kept at least one foot below the ground line or low water elevation. Any casing above this elevation will be temporary.
End Bents are usually pile cap bents; however, if quality rock is abundant at or just below the bottom of beam elevation, a stub end bent on spread footings may be used. If you have any doubt about the suitability and uniformity of the rock, you can still use a pile cap end bent. Just include prebore to get a minimum of 10 ft. of piling. If you have concerns about temperature movements, you can require that the prebore holes be oversized to allow for this movement.
For any pile cap bents, where steel piles are to be placed near a fluctuating water line or near a ground line where aggressive soil conditions exist or anticipated to exist in the future, corrosion can result in substantial material loss in pile sections over time, either slowly or rapidly. Galvanized steel piling is required for all new pile cap bents to be used as a deterrent to both accelerated and incidental pile corrosion as commonly seen in the field. Further, conditions like known in corrosive soils, some stream crossings with known history of effects on steel piles and grounds subject to stray currents, these conditions should affect the decision of whether pile cap bents can be effectively utilized. The potential effects of corrosion and the potential deterioration from environmental conditions should always be considered in the determination and selection of the steel pile type and steel pile cross-section (size of HP pile or casing thickness), and in considering the long-term durability of the pile type in service.
Once the substructure type has been determined, re-examine your Preliminary Cost Estimate and notify the district if it needs to be adjusted.
Galvanized Steel Piles
Galvanizing shall be required for all steel piles. Utilizing galvanized steel piles and pile bracing members shall be in addition to the requirements of Standard Specifications Sec 702 except that protective coatings specified in Sec 702 will not be required for galvanized piles or galvanized bracing members.
Where galvanized steel piling is expected to be exposed to severe corrosive conditions, consideration can be given to increased steel pile thickness or consideration of a reduced loaded steel area for bearing, or conditions mitigated to prevent long term corrosivity risk . This equally applies to the potential corrosion and early deterioration of permanent steel casing used for drilled shafts though they are not required to be galvanized. For all cases, further consideration beyond normal practice should be given to investigating corrosion protection, rate of corrosion as it relates to steel thickness design and expected service life including galvanizing losses, corrosion mitigation or different substructure support in order to meet a 75 year or longer design life. For additional information refer to LRFD 10.7.5 and 10.8.1.5. Consult with the Structural Project Manager or Structural Liaison Engineer to determine options and strategy for implementation.
All Bridge and Retaining Wall Piles (For Example, abutment piles, wing wall piles, intermediate pile cap bent piles and pile cap footing piles)
All surfaces of piles shall be galvanized to a minimum galvanized penetration (elevation) or its full length based on the following guidance. The minimum galvanized penetration (elevation) shall be estimated in preliminary design and finalized in final design. The minimum galvanized penetration (elevation) or full length will be shown on the design layout.
Guidance for determining minimum galvanized penetration (elevation):
The designer shall establish the limits of galvanized structural steel pile (i.e., HP pile and CIP pile). All exposed pile plus any required length below ground shall be galvanized. Based on required galvanized pile length determine and show Minimum Galvanized Penetration (Elevation) or Full Length on the Design Layout and on the plans.
Required Pile Galvanizing For Nonscour |
Required Pile Galvanizing For Channel Scour |
Required Pile Galvanizing For Channel Migration | |
---|---|---|---|
Estimated Pile Length ≤ 50 feet | Full Length of Pile | Full Length of Pile | Full Length of Pile |
Estimated Pile Length > 50 feet | 20 feet (in ground)1 | 20 feet (in ground)1, but not less than 5 feet below max. scour depth. | 20 feet (in ground)1, but not less than 5 feet below stream bed elev. |
1 “In ground” is measured from finished ground line on intermediate bents, and bottom of beam cap for abutments. |
For retaining walls supported on piles, the minimum galvanized penetration (elevation) for piles shall be “Full Length of Pile” for estimated pile length up to 50 feet and 15 feet below bottom of wall for estimated pile length greater than 50 feet.
For bridge end bents on piles with embankments supported by MSE walls, the minimum galvanized penetration (elevation) for piles shall be “Full Length of Pile” for estimated pile length up to 50 feet and 15 feet below top of leveling pad for estimated pile length greater than 50 feet.
Temporary Bridge Piles
Protective coatings are not required in accordance with Sec 718. Galvanized pile is not required. All HP piles driven to rock shall require pile point reinforcement.
751.1.2.21 Type of Footings
Once it has been determined that a bent will have columns on footings, the next decision is whether the footings should be pile or spread (on shale or rock). If it is a stream crossing, the bottom of footing elevation should be based on the scour calculations found in EPG 750.3 Bridges, an article dealing with hydraulic design. The borings should then be studied to see if a minimum of 10 ft. of piling can be placed below the footings. If this is doubtful because of the presence of shale or rock, spread footings or drilled shafts should be used. In instances where it appears that a spread footing can be used but there are pinnacles in the area, you may want to use a pile footing and just require prebore to ensure that you get the minimum embedment of 10 feet. For spread footings on grade separations, include a “not above” elevation to ensure a footing cover of at least 3 feet.
751.1.2.22 Types of Piling
The two types of piling commonly used are structural steel HP pile and close-ended steel pipe pile (cast-in-place, CIP). Open ended steel pipe pile (cast-in-place, CIP) can also be used. HP piles are commonly used as end bearing piles when shale or rock will be encountered at an elevation that will limit the pile lengths to about 100 ft. or less. CIP piles are commonly used as friction pile for which a minimum tip elevation must be determined (see EPG 751.36.2 Steel Pile for criteria). All HP piles driven to rock shall require pile point reinforcement. For end bearing pile tipped in shale, sandstone, or rock of uncertain strength at any loading where the likelihood of pile damage is increased, Geotechnical Section should indicate either “PDA recommended” or “PDA not recommended” in Foundation Investigation Geotechnical Report (FIGR). See EPG 751.36.5.3 Geotechnical Resistance Factor (ϕstat) and Driving Resistance Factor (ϕdyn) for more information about pile driving verification methods.For CIP pile, Geotechnical Section indicates either "No Pile Point Needed" or "Pile Point Needed" and recommends pile point type on boring log. “Cruciform” or “Conical” pile point reinforcement is allowed for closed ended CIP pile. “Manufactured open ended cutting shoe (inside flange)” pile point reinforcement is allowed for open ended CIP. Generally, pile point reinforcement is needed for CIP pile if boulders, cobbles, or dense gravel are anticipated. For all piles, prebore if necessary to achieve minimum embedment.
Here are some guidelines for minimum embedment:
Pile Type Minimum Embedment Structural Steel HP-Pile 10' into natural ground(5)
15’ into natural ground at integral end bents(1)(2)
10’ below bottom of MSE wall leveling pad
15'-20' below scour depth(4)CIP Steel Pipe Pile 10' into natural ground
10’ below bottom of MSE wall leveling pad
15’ into natural ground at integral end bents(1)(3)
15'-20' below scour depth(4)(1) 10’ is allowed if piles are designed using a rigorous design procedure.
(2) When precore into rock is necessary to provide the minimum 15’ embedment, a minimum precore of 5’ is required. (i.e., 12’ of soil over rock will require a 17’ pile embedment).
(3) When prebore is required, pile shall be embedded at least 15’ below prebore hole.
(4) 15’ if the material is hard cohesive or dense granular; 20’ if the material is soft cohesive or loose granular. When precore into rock is necessary to provide the minimum embedment, the embedment into rock shall be determined by design (include rock depth in soil-structure analysis) but minimum precore shall not be less than 5’ into hard rock and 10’ into weak rock regardless of overburden condition.
(5) When precore into rock is necessary to provide the minimum 10’ embedment by design, a minimum precore of 5’ is required. (i.e., 7’ of soil over rock will require a 12’ pile embedment).
See EPG 751.24.2.1 Design for further guidance on pile embedment behind MSE Walls.
751.1.2.23 Estimating the Lengths of Piles
All designers doing preliminary design should use the bearing graph provided in the foundation investigation Geotechnical report to estimate the lengths for piling. If a bearing graph is not provided the designer should perform a static analysis.
One way to check the validity of your static analysis results is to look at the piling information for existing bridges in the vicinity. Please also be on the lookout for any borings that contain "glacial till" (gravelly clay). This material is notorious for stopping pile.
This procedure is not a substitute for experience and engineering judgment. It is simply an attempt to have a more uniform method for estimating pile lengths.
All soil data must be obtained as well as elevation information pertaining to intermediate and end bents. The soil borings and core information are then observed. The unit weights of the different soil layers are determined by correlating information from the core data with information found in reference tables. The resulting unit weights are written on the soil boring page. If the soil is cohesive, the undrained shear strength should be determined by dividing the results of the pocket penetrometer test by two. If there was no pocket penetrometer test performed, then a correlation between the SPT blow counts and the undrained shear strength can be determined from reference tables. The water table must be identified or estimated and labeled on each of the borings and cores. The water table is usually distinguishable by the presence of gray colored soil. Note that more accurate data is obtained from cores than is obtained from borings because borings are performed using an auger type apparatus that mixes and remolds the soil.
751.1.2.24 Drilled Shafts
Drilled shafts are to be used when their cost is comparable to that of large cofferdams and footings. Other examples include when there are subsurface items to avoid (culverts, utilities, etc.) or when there are extremely high soil pressures due to slope failures.
The Foundation Investigation request should include a request for opinion regarding the necessity of permanent casing when drilled shafts are investigated.
Cost estimate savings and supporting subsurface information shall be discussed with Construction and Materials before permanent casing is omitted on a project.
The Foundation Investigation Geotechnical Report (or soundings report) for drilled shafts should supply you with the nominal end bearing (tip resistance) and side friction (side resistance) as well as the elevations for which the nominal rock values are applicable.
The Design Layout Sheet should include the following information:
- Top of Drilled Shaft Elevation
- Top of Permanent Casing Elevation
- Anticipated Tip of Casing Elevation
- Anticipated Top of Sound Rock Elevation
Bent Elevation Side Friction (tsf) End Bearing (tsf)
751.1.2.25 Excavation Datum
An Excavation Datum should be placed on the Layout Sheet when water is expected to be encountered during the excavation for footings. The elevation used is usually the Low Water Elevation plus 1 foot (rounded up to the next even foot) but may be made slightly higher on bigger streams and rivers. Everything above this datum is Class 1 Excavation while everything below it is Class 2 Excavation.
751.1.2.26 Seal Courses
On structures over water with pile footings, a determination should be made as to whether or not to include seal courses. Seal courses are used in conjunction with cofferdams when a contractor may have trouble dewatering the footing excavation. They are usually necessary when you have sandy or gravelly soils and footing elevations below the stream bed. You will need to include a water surface elevation on the Design Layout Sheet for which the Seal Courses should be designed for. Typically the elevation used is the average of the Low Water Elevation and the Design High Water Elevation; however, a site visit may be required to determine how reasonable this is. In no case should this elevation be higher than the 10 year high water elevation or the overbank elevation.
751.1.2.27 Cofferdams
Cofferdams should be included if the depth of the hole for the footing exceeds 8 feet and/or the bottom of footing elevation is below the Ordinary High Water (OHW) elevation. Any bent that requires a seal course will also require a cofferdam. These are bid lump sum per bent. Consult with the Assistant State Bridge Engineer about this. All piling in pile footings should be straight (not battered) when a cofferdam is expected.
751.1.2.28 Webs
On structures over water where medium to heavy drift has been indicated on the Bridge Survey, consider using web walls between the columns on the column bents near or in the stream. The bottom elevation for the web is typically 1' higher than the overbank elevation.
751.1.2.29 Protection of Spill Slopes and Side Slopes
The district shall be consulted for type of slope protection. Either Concrete Slope Protection or Rock Blanket can be used for grade separations and are Roadway Pay Items. On stream crossings, Rock Blanket is usually placed. The type and thickness of Rock Blanket is to be determined by the district based on the flow velocity from the Scour design flood frequency. This flow velocity is determined by the person doing the hydraulic calculations and should be placed on the Bridge Memorandum. Permanent erosion control geotextile is always required to be placed under rock blanket.
When Rock Blanket is used, an elevation for the upper limit of this protection needs to be calculated. First, calculate the following two elevations:
- 100 year High Water Elevation plus 2 feet
- 500 year High Water Elevation plus 1 foot
Take the higher of these two elevations and compare it to the Low Girder Elevation minus 1.2 feet. Use the lowest of these two elevations for the upper limit of your Rock Blanket. This elevation should be placed on the profile sheets.
If the toe of the abutment slope falls on the overbank, the rock blanket apron should extend from the toe toward the channel a distance equal to twice the 100 year flow depth on the overbank, but need not exceed 25 feet.
Note: District Design has the option of extending rock blanket up to and for the full length of the bridge approach slab or otherwise using drain flumes for bridge end drainage. See EPG 503 Bridge Approach Slabs, EPG 611 Embankment Protection and Standard Plan 609.40.
751.1.2.30 Design Exceptions
Anytime MoDOT standards are not followed, a Design Exception is necessary. These are usually initiated by the Transportation Project Manager in the district; however, if the item is related to the bridge, the Bridge Division will initiate the Design Exception.
The Design Exception Information should be filled out by the preliminary designer and then reviewed by the Structural Project Manager (SPM). A complete explanation of the basis for the design variance must be provided, including cost justification and details on how the variance will affect adjacent properties. The SPM should then submit the Design Exception to the Assistant State Bridge Engineer for review. After this review, the Design Exception should be submitted to the State Bridge Engineer for the Sate Bridge Engineer's signature. This submission should include written comments from the SPM on why the Design Exception should be approved. Once the Design Exception has been signed by the State Bridge Engineer, the SPM should mail the Design Exception Information Form and cover letter to the Transportation Project Manager in the district. The TPM will sign it and then send it to the General Headquarters Design Division for final approval. The Design Division will supply copies of the signed Design Exception to both the district and the Bridge Division.
Some examples of Design Exceptions initiated by the Bridge Division are:
Hydraulic Standards
These include not meeting the standards for freeboard, design frequency, etc.
Vertical Clearance
If the vertical clearance under a new or widened bridge does not meet the standard, a Design Exception is required. If the reduction in vertical clearance is due solely to the overlay of the road under the bridge, the Bridge Division would not initiate the Design Exception.
Roadway/Shoulder Width Less Than Standard (New Structures)
On new structures, if the roadway and/or shoulder widths on the bridge match the approach roadway, the Design Exception would be initiated by the district. If the roadway and/or shoulder widths on a new bridge are less than the approach roadway, the Design Exception would be initiated by the Bridge Division.
Roadway/Shoulder Width Less Than Standard (Existing Structures)
On Non-Interstate Rehab (3R) jobs, an exception for width is required any time we don’t meet the new design standards. The approach lanes being referred to in the rural design standards note (8) are the new lanes. The last note should be modified to read “Bridges programmed for replacement within 5 years may be allowed to remain in place as is and should be looked at on a case by case basis.”
On Interstate Rehab (4R) jobs, an exception for width is required any time we don’t meet the new design standards. If an existing bridge is over 200 feet long, FHWA has said that they will routinely approve the width if both shoulders are at least 3.5’ wide, but we should still request the Design Exception. FHWA will want to see any approved Design Exceptions before they approve the preliminary design.
Bridge Approach Slabs (New Bridges)
On new bridges, the interchangeability of bridge approach slab classes will require a design exception. For example, if a Bridge Approach Slab (Major) is to be substituted for a Bridge Approach Slab (Minor), a design exception will be required and initiated by the Bridge Division based on project core team consensus.
751.1.2.31 Finishing Up Design Layout
Design Layouts shall be generated for new bridges, retaining walls and when foundation work is required for bridge widenings. Otherwise, Design Layouts are not utilized for conveyance of information related to rehabilitation projects, or work on existing bridges or, more generally, on structures.
Once the Preliminary Detailer has created the Design Layout Sheet and added the borings and details of the proposed bridge to the plat and profile sheets, they should be checked by the Preliminary Designer. These sheets are the end product of the Preliminary Design process and will be used to perform the structural calculations for the Final Design phase of the bridge, which results in the production of the contract plans. Here is a list of items to include.
1.) | General Information | |
a. | Route and structure classifications | |
b. | Live load designation | |
c. | Traffic counts for the design year (AADT and AADTT). | |
d. | Tie station (if applicable). | |
e. | Beginning station. | |
f. | Horizontal curve data. | |
g. | Profile grade information (including offset from CL of roadway or median). | |
h. | Excavation datum. | |
2.) | Superstructure | |
a. | Type and span lengths. | |
b. | Roadway widths and type of barrier or railing. | |
3.) | Substructure | |
a. | Skew(s) of all bents. | |
b. | Types of all bents. | |
c. | Type and locations of sway bracing for concrete pile cap intermediate bent with HP pile. | |
d. | Locations and top of wall elevations for collision walls. | |
e. | Embedment of encasement for encased pile cap bent. | |
f. | Location of tie beam. | |
g. | Bottom elevations of web beam. | |
4.) | End Bents (Abutments) | |
a. | Type of end fill and maximum slope. Include earth plugs for piling in rock fill. | |
b. | Berm elevations. | |
c. | Type and extent of spill and side slope protection (permanent erosion control geotextile fabric is required). | |
d. | Bridge end drainage provisions per district (drain basins1, rock blanket, drain flumes) (Rdwy. Item) | |
e. | Angle of internal friction to be used for deadman anchors. | |
5.) | Foundations | |
a. | Type and lengths of all piling. | |
b. | Minimum galvanized penetration (elevation) | |
c. | Minimum tip elevations for all piles. | |
d. | Location and elevation for any preboring. | |
e. | Pile point reinforcement (shoes) required for all structural steel HP piles. When Geotechnical Section indicates pile point reinforcement needed and show pile point type on boring log for CIP pile, then recommended pile point reinforcement type shall be shown on Design Layout. | |
f. | For end bearing pile when Geotechnical Section recommends dynamic pile testing (PDA) for pile driving verification method then reflect that on Design Layout. | |
g. | Types of footings, their elevations and allowable bearing (if applicable). | |
h. | Location of any cofferdams and/or seal courses. | |
i. | End bearing and side bearing capacity for any drilled shafts. | |
j. | Top of Rock Socket elevations and their minimum lengths. | |
k. | Estimated Maximum Scour Depth (Elev.)2 | |
l. | Minimum pile cleanout penetration (Elev.)3 | |
6.) | Traffic Handling | |
a. | How will traffic be handled (bypass, road closure, staging, other) | |
b. | Include a sketch of any staging. | |
7.) | Disposition of Existing Structure | |
a. | Bridge No(s). of structures slated for removal. | |
b. | Estimate cost of removal and indicate that this cost is included in the total. | |
8.) | Hydraulic Information | |
a. | Drainage area and terrain description. | |
b. | Design frequency. | |
c. | Design discharge. | |
d. | Design high water elevation. | |
e. | Estimated backwater. | |
f. | Overtopping frequency and discharge if less than 500 yr. | |
9.) | Seismic Information (New or Replacement Bridge, substructure widening or Wall) (Applies to both seismic and nonseismic designs): | |
a. | Provide Site Class, Seismic Design Category, As and SD1 for SDC B, C and D bridge/wall, and Liquefaction Potential information for SDC C and D (All available information from Geotechnical report). When As is greater than 0.75 then show As = 0.75. For SDC A area bridge/wall indicate SDC A, SD1 < 0.15 and As = N/A. Use N/A if not reported in Geotech report. | |
b. | Indicate either “Nonseismic”, "Seismic Details", “Abutment Seismic Design”, “Seismic Details plus Abutment Seismic Design” or “Complete Seismic Analysis” for a bridge structure based on Geotechnical Section provided SDC and Bridge Seismic Design Flowchart (EPG 751.9.1 Seismic Analysis and Design Specifications).
| |
c. | For a wall structure in SDC B, or C seismic analysis provisions shall not be ignored for walls that support another structure (i.e. abutment fill or building) in accordance with LRFD 11.5.4.2. Based on wall supporting information and Geotech report indicate “seismic analysis not required” or “seismic analysis required”. SDC D retaining walls shall be designed for seismic load. | |
d. | All new or replacement bridge/wall designs, either nonseismic (meaning a regular static design) or seismic design or detail, must meet Seismic Design Category (SDC) A requirements in accordance with SGS (Seismic Zone 1 of LRFD). Additionally, bridge/wall seismic designs/details must meet requirements of the Seismic Design Category B, C, or D where applicable. See EPG 751.1.2.13 Seismic (Earthquake) Design Category A, B, C and D Considerations. | |
10.) | Miscellaneous | |
a. | Locations of Bridge Approach Slabs. | |
b. | Call out slab drain requirements if other than the standard procedure. | |
c. | The location of the stationing reference line (CL roadway, CL median, other). | |
d. | Station equations. | |
e. | Minimum final and construction clearances (vertical and horizontal). | |
f. | Use of weathering steel or color of paint (steel girders). | |
g. | Name and phone number of district contact. | |
h. | Preliminary Cost Estimate. | |
i. | Details of any utilities to be attached to the bridge. | |
j. | Details of any conduit, light supports or any other unusual attachments. | |
k. | Channel change requirements. | |
l. | Temporary shoring requirements and whether it is a Bridge or Roadway Item. | |
m. | Temporary MSE wall systems. (If determined during layout process for staged bridge construction). | |
n. | Location of Maint. facility contractor is to use for delivery of MoDOT retained items. | |
o. | All DGN files should be stored in the project folder (Preliminary subfolder). |
1 | Drain basins can be included with concrete approach pavement per district. (Rdwy. Item) | ||
2 | Show maximum of total scour depths estimated for multiple return periods in years from Preliminary design which should be given on the Design Layout. Show the controlling return period (e.g. 100, 200, 500) in Foundation Data. If return periods are different for different bents, add a new line in Foundation Data. On the plans report note EPG 751.50 E2.22 for CIP pile. | ||
3 | Show for open ended CIP piles. For scour condition, minimum cleanout elevation shall be at least 3 feet below maximum estimated scour depth. For non scour condition, minimum cleanout elevation shall be at least 10 feet below natural ground line. |
Once the Preliminary Detailer and Designer are in agreement on these items, the entire layout folder should be submitted to the SPM for their review. The SPM will then request a Design Layout Conference with the Assistant State Bridge Engineer and the Structural Resource Manager.
Following this conference, the Preliminary Detailer and Designer will make any requested changes and complete the assembly of the Layout Folder by including the approved Design Layout Sheet and one set of half sized plat and profile sheets. The Layout Folder should then be delivered to the SPM along with one set of half-sized plat and profile sheets and a copy of the Design Layout Sheet.
The SPM should then use a cover letter to send the one set of half-sized plat and profile sheets, as well as the copy of the Design Layout Sheet, to the Transportation Project Manager in the district. Include in this cover letter any changes in the Preliminary Cost Estimate and the current Plans Completion Date. An example can be found on the next page.
The Preliminary Detailer should provide a copy of the Design Layout Sheet to the Bridge Survey Processor. The Bridge Survey Processor should then perform the following tasks:
- Enter the Date to Final Design in the Bridge Survey Book and the Survey Rcv. Database
- Supply a copy of the Design Layout Sheet to Development and Review.
- Copy all of the MicroStation files in house to
- pwname:\\MoDOT\Documents\Central Office\Bridge\A_Prelim_design\district\job no.
- (Consultants contact Structural Liaison Engineer).
The SPM should then enter the following information into Bloodhound:
- Span layout information
- Preliminary Cost Estimate
- Date of Layout Conference
- Preliminary Plans to District
All other fields in Bloodhound should be updated at this time by the SPM.
The SPM will then send a request for a Final Designer to the Structural Resource Manager.
751.1.2.32 FHWA Submittal
Federal involvement is determined in accordance with EPG 123.1.1 FHWA Oversight – National Highway System. Projects which are delegated for federal involvement for preliminary design on the PODI matrix must be submitted to FHWA for approval.
The submittal should include the following:
- Cover letter
- One set of half-sized plat and profile sheets
- One copy of Design Layout Sheet
- One copy of completed Bridge Survey Report
- One copy of the Borings report including Cover Letter from Materials
- One copy of each approved Design Exception (if applicable)
- One copy of the Bridge Deck Condition Survey Summary (if applicable)
- One copy of the Bridge Rehab Checklist (if applicable)
- One copy of the Bridge Inspection Report for the existing bridge (if applicable)
- One copy of half-sized existing bridge plans (if applicable)
- One copy of anything else referred to on the Design Layout Sheet (an example would be top of pavement elevations if these are to be used in Final Design)
That is the end of the Preliminary Design phase of bridge design at MoDOT.
751.1.2.33 Aesthetic Enhancements
Aesthetic enhancements can include everything from form liners and different colored paints to actual brick or stonework on the bridge. The district is required to inform the Bridge Division if aesthetic enhancements will be required on a bridge. Aesthetic enhancements should be discussed by the core team during the scoping process.
Note: Galvanized slab drains are to remain unpainted unless otherwise requested by the district. The required special provision is available if the district wishes to paint the galvanized slab drains.
Specifying Form Liners
Form liners are typically supplied in 4 ft. wide sections. Consideration should be given to specifying concrete work in 2 ft. increments to avoid waste of form liner. Use of 1 ft. increments may be possible. Avoid specifying work requiring less than 1 ft. increments of form liner without approval of the Structural Project Manager or Structural Liaison Engineer. Specifying work requiring form liner using other than 4 ft. increments may affect cost and should be reviewed.
751.1.2.34 Blast Loading Considerations
Consideration should be given to the blast loading provisions given in AASHTO LRFD Bridge Design Specifications and AASHTO Bridge Security Guidelines for major bridges only and with the approval of the State Bridge Engineer.
Requirements for provision of blast loading protection and for structural design should be documented on the Bridge Memorandum and Design Layout.
All documentation associated with consideration of and requirements for blast loading protection and/or structural design including structural design computations should be detached or separated from other publicly available documents and marked “Not for Public Consumption.”
751.1.2.35 Bridge Approach Slabs
See EPG 503 Bridge Approach Slabs.
751.1.2.36 Bridge End Drainage
See EPG 503 Bridge Approach Slabs.
751.1.3 Wearing Surfaces/Rehabs/Redecks/Widenings
751.1.3.1 Overview
Modifying existing bridges is quite different from laying out new bridges. Bridge wearing surfaces (overlays), rehabs, redecks and only widenings when the substructure is not being widened require the preparation and approval of a Bridge Memo as the only official written document requiring signatory approval (see EPG 751.1.2.19 Bridge Memorandums) as a matter of procedure. A Design Layout is not required in these instances. However, bridge widenings when substructure and foundation work are required will require procedurally both a Bridge Memo and a Design Layout for signatory approval since soundings for exploring subsurface conditions will be required for the foundations.
These types of projects can be broken into four general categories:
- Adding a wearing surface to an existing bridge as part of a roadway overlay project.
- Rehabilitating and/or redecking an existing bridge as a stand alone programmed project.
- Widening an existing bridge to meet minimum shoulder width requirements as part of a roadway overlay project.
- Widening an existing bridge to add lanes as part of a roadway project.
751.1.3.2 Documentation
A structural rehabilitation checklist shall be required for determining the current condition and documenting all needed improvements regardless of budget restraints. It is critical to control future growth in project scope or cost overruns during construction that is checklist captures all needed repairs using accurate quantities corresponding to contract bid items. Staff responsible for filling out checklist should contact the Bridge Division if assistance is needing in correlating deterioration with appropriate contract bid items.
A deck test is not required but may be useful in determining the most appropriate wearing surface for bridges with deck ratings of 5 or 6.
A pull off test is not required but may be useful in determining the viability of polymer wearing surface.
Both deck tests and pull off tests are performed by the Preliminary and Review Section.
A Bridge Memorandum shall be required for documenting proposed construction work and estimated construction costs for district concurrence.
A Design Layout shall be required only for widening projects where there is proposed foundation construction.
751.1.3.3 Bridges on Resurfacing Projects
This is probably the most common type of project. The first step is to determine the limits of the project. This can be done by looking at the description and log miles of the project in the Program Book. The district contact should also be consulted to make sure the project limits have not changed. The second step is using the Bridge Maps produced by the Maintenance Division to locate any and all bridges within the limits of the project.
Once the Bridge Nos. for these structures are known, obtain a copy of the Bridge Maintenance report for each structure. These reports contain the log mile for each structure. Compare this to the log mile limits of the project. If the log mile on the report indicates the bridge is outside of the project limits, check with the district contact again to see if the bridge is to be included in the project.
If a bridge falls within the project limits, it must be evaluated to see if it meets the current safety criteria for such items as shoulder width and curb type/height. If the job will be built with federal funds, any substandard safety item must be remedied or handled with a design exception. If the job will be built with 100% state funds, the bridge can be left alone (no safety improvements).
751.1.3.4 Barrier or Railing Type, Height and Guidelines for Curb Blockouts
AASHTO LRFD uses the term “railing” to refer to all types of bridge traffic barrier systems used on bridges. MoDOT uses the term “barrier” for solid concrete bridge railing (single-faced on the edge of roadway and dual-faced medians) and the term “railing” for barrier systems consisting of a rail(s) and supports. Several types of barrier and railing are acceptable for use on bridges in Missouri (see Common Bridge Barrier and Railing); thrie beam railing, Type A, B, C, D, G and H barrier; curb and parapet barrier, two tube rail; or FHWA MASH or NCHRP 350 approved crash tested barrier or railing meeting TL-4 rating as given on the FHWA Bridge Railings website.
While meeting MASH TL-4 requirements is preferred, existing barrier or railing may be used in place if meeting NCHRP 350 TL-3 or TL-4 requirements, or existing barrier or railing may be retrofitted to meet same requirements. See Common Bridge Barrier and Railing (for Rehabilitations) for further guidance.
New bridge barrier or railing on existing bridges shall meet MASH TL-4 requirements on major routes with design speeds greater than 45 mph. Similarly, MASH TL-4 barrier or railing is required on minor and low volume routes with design speeds greater than 55 mph or AADT ≥ 1700. New bridge barrier or railing on existing bridges for all other major, minor, and low volume routes may instead meet MASH TL-3, NCHRP 350 TL-4 or NCHRP 350 TL-3 requirements where circumstances restrict the use of a MASH TL-4 barrier or railing. In any case, the new barrier or railing shall not be rated lower than the existing barrier or railing. The hierarchy for crash test ratings in descending order is listed below with qualified barriers and railings in Missouri:
- MASH (2016) TL-4 (Type C and D barrier, 38-inch two tube railing)
- MASH TL-3 (Type H barrier, Type A and B barrier, culvert guardrail)
- NCHRP 350 TL-4 (32-inch two tube railing)
- NCHRP 350 TL-3 (12” x 29” vertical barrier, thrie beam railing).
Type C and D barrier shall be used on all redecks, rehabs and widenings where the full length of barrier is being replaced with exceptions for the following:
- sight distance concerns. Type H barrier or two tube rail is recommended.
- rating concerns where the weight of the barrier prohibits its use or causes impractical restrictions or costs for the project. Type H barrier or two tube rail is recommended.
- roadway width restrictions. 32-inch two tube rail or thrie beam rail is recommended.
The approach railing does not need to match the test level of the bridge barrier or railing. MoDOT standard approach rails typically do not rate higher than TL-3.
When using a concrete barrier, a five-hole bolt pattern shall be used for connecting the approach railing to the bridge barrier.
Bridge barrier or railing on single lane bridges may be used in place if for no other reason than the grade is not being raised. Thin wearing surfaces measuring no more than 3/8 inch will not be considered as raising the grade.
Thrie Beam Railing (Bridge Guardrail)
If the deck is less than 8½ inches thick, the attachment must bolt through the deck with a plate on the bottom side of the deck. In the past, MoDOT used details where a bent stud was formed within the deck. This is no longer acceptable because of observed failure in thin decks where the edge can break off and the bottom of slab can pop out during a collision.
The center of the thrie beam shall be a minimum of 21 inches to the top of the finished driving surface.
Thrie beam railing shall not be installed on new or replacement bridges or widenings. Thrie beam shall not be used for grade crossings or other areas where drainage over the side of the deck is a concern.
W-beam Railing (Culvert Guardrail)
The MASH TL-3 standard for guardrail attachment is covered in EPG 751.12.6 Culvert Guardrail (Top Mounted). Existing guardrail or thrie beam attachments likely do not have an adequate base plate design, railing height or headwall clearance to be considered MASH TL-3 compliant. Existing attachments most closely fit NCHRP 350 TL-3 or MASH TL-2. Existing guardrail attachments shall be treated in the same manner as free-standing guardrail when determining if the system can be used in place (see EPG 606.1.3.1 Guardrail Selection and Placement). If Midwest Guardrail System (MGS) is required and space is available for headwall clearance, 2’-10” minimum between headwall and roadway face of guardrail, the MASH TL-3 standard for guardrail attachment shall be used.
If there is less than 2’-10” of space between headwall and roadway face of guardrail, a thrie beam shall be used and it is preferrable to top mount the headwall instead of pushing the slab mount closer to headwall. The condition of the headwall should be considered before choosing the headwall mount option.
If the top slab is less than 10 inches a bolt-thru attachment is required. For thicker slabs a resin-anchor system is available with a minimum 8-inch embedment. There are advantages to both systems. A bolt-thru attachment provides a stouter connection which may reduce the damage to the culvert slab after impact. On the other hand, repairing a bolt-thru system requires access inside the culvert while a resin-anchor system requires access to top of culvert only. Resin-anchor systems may also be preferred if culvert walls interfere with post placement.
Type A, B, C, D, G and H Barriers
If installed at the same time as the driving surface, the top of the barrier shall not be less than 32 inches above the driving surface.
If a wearing surface is installed after the barrier is in place, the wearing surface thickness shall not be made greater than that whereby the barrier height is made less than 30 inches , i.e. the final grade with wearing surface installed shall not increase more than 2 inches.
If an existing wearing surface is replaced next to Type A or B barrier, the new wearing surface thickness shall not be made less than that where by the height above the driving surface of the break between the upper and lower slope of the barrier is made greater than 13 inches.
Curb and Parapet Barrier
The concrete portions of the curb and parapet are the only components used in determining the height of the barrier for establishing if the system meets current standards or is substandard. The handrails are not crashworthy and therefore are not considered as part of the height of the barrier.
Curb and parapet were typically constructed 27 inches measured from the driving surface to top of parapet.
Sections of curb and parapet may be replaced without consideration of upgrading.
When a wearing surface is to be applied, the height of the existing curb and parapet system shall be determined from the existing driving surface and if necessary shall be heightened to 32 inches or 36 inches above the proposed driving surface based on Guidelines for Curb Blockout, immediately below. Increasing the height of an existing curb and parapet is generally done by adding a blockout to the curb and parapet (i.e., curb blockout).
Guidelines for Curb Blockout
Background and Application
Guidelines were developed considering Practical Design concepts (refer to EPG 143 Practical Design).
Guidelines apply to bridges to be resurfaced and/or rehabilitated that have concrete curb and parapet barrier. They do not apply to bridges on Contract Leveling Course projects that are in accordance with EPG 402.1 Design of Leveling Course Projects.
When resurfacing and rehabilitating a bridge, consideration shall be given to upgrading the curb and parapet barrier by increasing the overall height if the barrier does not meet criteria given in these guidelines. The guidelines are based upon reviewing conditions that require satisfying height and horizontal parapet offset requirements using the minimum height of 27 inches in accordance with 2002 AASHTO 17th Edition and earlier editions and a maximum horizontal parapet offset of 6 inches from curb face to parapet face which is a MoDOT requirement (EPG 128 Conceptual Studies, 3R-Rural Design Criteria recommends a 6-inch brush curb). Upgrades to curb and parapet should be made by constructing a curb blockout. The following guidelines describe circumstances where it is, or is not, necessary to upgrade curb and parapet that were either originally built substandard or made substandard due to an earlier wearing surface or will be made substandard due to a proposed wearing surface.
Guidelines
Look at the 5-year history of accidents on the bridge (beginning log mile to ending log mile).
If there were any accidents in this time period that involved a vehicle striking the curb, then curb and parapet not meeting current standards should be upgraded to meet the current (2016) MASH TL-4 requirement which is to increase the height to 36 inches. A 32” blockout height will be allowed, upon approval of the SPM or SLE, when either sight distance or weight restrictions are a concern.
If there were NOT any accidents in the 5-year history AND if the grade is not being raised then it shall not be necessary to upgrade the curb and parapet.
If the accident history or grade criteria are not met, then it shall be necessary to upgrade the curb and parapet. The district may submit a design exception to eliminate a curb blockout for bridges not on major routes and with AADT < 1700 when there is no history of accidents on the bridge and the grade is being raised no more than 2 inches from the 27-inch minimum height requirement.
Limiting Wearing Surface Thickness To Meet Guidelines
The wearing surface thickness can be limited to that which would not cause the curb and parapet height to become substandard. An exception to this is a 1/4 to 3/8-inch height tolerance to allow for the possibility of placing a thin wearing surface on a bridge with an existing standard 27-inch high curb and parapet as measured from the original driving surface to the top of the parapet. Adding a thin wearing surface will not by itself make a satisfactory curb and parapet railing height substandard as reviewed and approved by MoDOT and FHWA. For overlay projects, where a curb blockout is already in place, the final blockout height shall not be less than 30 inches.
Note: In all cases, the allowable wearing surface thickness would also be dependent on a structural review to confirm that the weight of the wearing surface would not lead to overstresses or an unacceptable posting.
Details
The horizontal offset (or ledge) from the curb face to the parapet face is recommended to be between zero and 3 inches but shall not exceed 6 inches. If a curb blockout is used, the ledge shall not exceed 3 inches.
End posts are not always the same width as the parapets. If the end posts are wider and if they extend towards the driving lanes, it shall be necessary to remove the end posts completely in order to construct the curb blockouts. If end posts extend towards the outside of the bridge, it may not be necessary to remove the end posts.
The end treatment for the 36-inch blockout will require a maximum 6:1 slope to transition down to a maximum 32-inch end height near the guardrail attachment. A 32-inch blockout does not require a reduced height for the end treatment. The preferred end treatment will include a gradual width transition that approximates a 10:1 slope. A block inset for the guardrail attachment should be avoided.
Common Bridge Barrier and Railing (for Rehabilitations)
Type | Section (Test Level) |
Allowed Wearing Surface | Required Retrofit | Notes |
---|---|---|---|---|
Curb and Parapet (Brush Curb ≤ 6”) |
(N/A) |
3/8” Thin Wearing Surface | Use in place with curb blockout for wearing surfaces greater than 3/8” from original deck surface | (1) |
Curb and Parapet ( Brush Curb > 6”) |
(N/A) |
None without retrofit | Use in place with curb blockout (preferred) or thrie beam railing. | (1) Horizontal step must be 6” or less to be UIP. |
Brush Curb with Steel Rail |
(N/A) |
None without retrofit | Use in place with added curb blockout (preferred) or thrie beam railing. | (1) A variety of steel railing systems were employed on brush curbs. None are acceptable without retrofit. |
Thrie Beam |
(NCHRP 350 TL-3) |
21” (Min.) from centerline of thrie beam to top of wearing surface | Use in place if minimum height to centerline of thrie beam is acceptable. | (2) and (4) May be embedded or bolted thru. W6x15 blockout is included for all new construction. Non-blocked railing may be used-in-place when no approach guardrail is provided. |
Type A Barrier (Photo not available) |
(MASH TL-3) |
Up to 2” | Use in place. | (1) |
Type B Barrier |
(MASH TL-3) |
Up to 2” | Use in place. | (1) |
Type C Barrier (Photo not available) |
(MASH 2016 TL-4) |
Up to 6” | Use in place. | (3) Wearing surfaces greater than 3” require a bridge rating analysis |
Type D Barrier |
(MASH 2016 TL-4) |
Up to 6” | Use in place. | (3) Wearing surfaces greater than 3” require a bridge rating analysis |
Type G Barrier (Photo not available) |
(MASH 2016 TL-3) |
Up to 2” | Use in place. | (3) Use if Type C is considered impractical. |
Type H Barrier | (MASH 2016 TL-3) |
Up to 2” | Use in place. | (3) Use if Type D is considered impractical. |
32-inch Two Tube Rail |
(NCHRP 350 TL-4) |
Up to 2” | Use in place. | (3) and (4) |
38-inch Two Tube Rail (Photo not available) |
(MASH 2016 TL-4) |
Up to 2” | Use in place. | (3) Not for use with turned-back abutment wings less than 18” thick. |
12” x 29” Vertical Barrier |
(NCHRP 350 TL-3) |
Up to 2” | End of barrier modification for new guardrail attachment. | (1) |
Culvert Guardrail | (NCHRP 350 TL-3 Thrie Beam or W-Beam) |
See EPG 606.1.3.1 Guardrail Selection and Placement | Use in place. | If MGS is required for the approach, the MASH TL-3 standard shall be installed if space allows. |
(1) Shall not be used for redecks, widenings, and railing or cantilever full length replacements. (2) Typically specified for redecks, and railing or cantilever full length replacements. Shall not be used for widenings. (3) Typically specified for redecks, widenings, and railing or cantilever full length replacements. (4) Shall not be used on major routes with design speeds greater than 45 mph or on minor and low volume routes with design speeds greater than 55 mph or AADT ≥ 1700. May be used for all other major, minor, and low volume routes. |
Aluminum handrail is not crashworthy and does not contribute to barrier height. Use only the concrete portion.
Many other, less common, barrier and railing systems have been constructed. Most are not crashworthy for rural highway speeds. Generally, the replacement of the existing barrier or railing is the only means to upgrade.
For additional information on curb blockouts, see Guidelines for Curb Blockouts.
A curb blockout is utilized along full length of the curb. Bridge Division provides plans for curb blockouts.
751.1.3.5 Deck Repairs
The project scope is developed from a thoroughly developed structural rehabilitation checklist which includes the typical repairs covered in Sec 704.
Typical Repair
Cleaning and epoxy coating of the bottom and edges of the superstructure is preferred over slab edge repair and unformed superstructure repair because of the relative short life of these repair especially when over traffic. However, consult with Structural Project Manager or the Structural Liaison Engineer for urban regions where repairing the overhang may be preferred. If requested by the core team for aesthetics with extensive patchwork of repairs visible to public, specify on the Bridge Memorandum to apply tinted sealer to slab edge repair and unformed superstructure repair to blend repair to existing concrete.
Non-Typical Repair
Modified deck repair is specified instead of half-sole deck repair on existing poor bridge decks to obtain a little more service life until it is practical to replace the bridge deck, superstructure or entire bridge.
On rare occasions shallow deck repair is used in combination with half-sole deck repair as a cost savings measure on major bridges. Consult with the structural project manager or the structural liaison engineer prior to specifying shallow deck repair.
751.1.3.6 Deck Treatment
The Bridge Wearing Surface Flowchart has been developed to aid in the selection of the appropriate deck treatment.
When possible, multiple types of wearing surfaces should be allowed by specifying on the Bridge Memorandum the appropriate optional wearing surface. It shall also be specified if any of the wearing surfaces of the optional wearing surfaces are not allowed. The specific wearing surface shall be specified on the Bridge Memorandum when only one wearing surface option is allowed.
Concrete Crack Filler
Concrete crack filler in accordance with Sec 704 is typically used for bridges with deck ratings of 7, 8 or 9 with cracks 1/128 inch or less. May also be an option for bridges with deck ratings of 7, 8 or 9 with cracks greater than 1/128 inch and the deck fails a required pull off test.
Concrete Wearing Surface
A concrete wearing surface in accordance with Sec 505 is the preferred deck treatment for bridges with deck ratings of 5 or 6 so long as the barrier height does not become substandard and the bridge remains not posted (or if already posted not be reduced).
Typically, the wearing surface thickness that has the least impact on existing grade is specified on the Bridge Memorandum as the minimum required thickness. When this thickness equals the minimum allowable thickness, as shown below, consider adding 1/2 inch to the minimum required thickness specified on the Bridge Memorandum for hydro demolition projects to provide coverage over existing aggregate protruding into the new wearing surface. For bridges with special repair zones where two different minimum hydro demolitions depths are specified, then two corresponding minimum required thicknesses shall be specified on the Bridge Memorandum.
Wearing Surface Type | Allowable Thickness |
---|---|
Latex Modified | 1¾″ to 3″ |
Silica Fume | 1¾″ to 3″ |
Latex Modified Very Early Strength | 1¾″ to 3″ |
CSA Cement Very Early Strength | 1¾″ to 3″ |
Steel Fiber Reinforced | 3″ to 4″ |
Low Slump | 2¼″ to 3″ |
Polyester Polymer | ¾″ to 3″ |
For a deck without an existing wearing surface, scarification of the deck producing a very rough texture in accordance with Sec 216.20 is required to produce a bondable surface for the new concrete wearing surface. Typically, 1/2 inch of scarification is specified on the Bridge Memorandum. Scarification equipment may not engage the deck when less than 1/2 inch of scarification is specified.
For a deck with an existing wearing surface, removing the existing wearing surface plus an additional amount of existing deck in accordance with Sec 216.30 is required to produce a very rough bondable surface for the new concrete wearing surface. Typically, 1/2 inch of additional existing deck is specified on the Bridge Memorandum. Removal equipment may not remove the entire existing wearing surface when less than 1/2 inch of additional deck is specified.
When the estimated deck repair is more than 30 percent of the deck, one inch shall be specified for scarification or for the additional amount of existing deck with the removal of an existing wearing surface. Verify there will be a minimum of 1/2 inch of concrete above the top bars after scarification or after the removal of the existing wearing surface and if necessary, reduce one-inch depth accordingly.
Total surface hydro demolition in accordance with Sec 216.110 performed after scarification or after the removal of the existing wearing surface is preferred for the establishment of a highly rough and bondable surface. For typical bridges, a minimum 1/2 inch of hydro demolition is specified on the Bridge Memorandum. For bridges with special repair zones, typically a 1/4-inch minimum is specified inside special repair zones to avoid deeper penetration into newly repaired areas and a 1/2-inch minimum is specified outside the special repair zones.
Removal of existing deck repair in accordance with Sec 216.110 is required prior to hydro demolition. The estimated quantities for these removals shall include all previous conventional deck repairs, regardless of condition except that for bridges with special repair zones, the removal of all sound and unsound existing deck repairs inside special repair zones shall be included in the estimated quantities for half-sole repair.
Polymer Wearing Surface
A polymer wearing surface in accordance with Sec 623 may only be used if the deck passes a required pull off test. Polymer is typically used for bridges with deck ratings of 7, 8 or 9 with cracks greater than 1/128 inch.The polymer may also be an option for bridges with deck ratings of 5 or 6 that have load rating issues.
Polymer Options |
---|
1/4″ Epoxy Polymer |
3/8″ MMA Polymer Slurry |
If requested by the core team, a black beauty type aggregate shall be specified on the Bridge Memorandum for MMA polymer slurry wearing surface.
If requested by the core team, a high friction (HFST) aggregate shall be specified on the Bridge Memorandum for MMA polymer slurry wearing surface pending a safety benefit/cost ratio analysis performed by district traffic staff. See Roadway non-standard special provision NJSP1513 to reference aggregate requirements and surface friction test.
If requested by the core team, preparation of reflective deck cracks shall be specified on the Bridge Memorandum if during the scoping process there is concern of primer loss with reflective deck crack size at the precast panel joints.
Asphalt Wearing Surface or Seal Coat
Asphalt wearing surfaces in accordance with Sec 403, ultrathin asphalt wearing surfaces in accordance with Sec 413 and seal coats in accordance with Sec 409 are typically used on existing poor bridge decks to obtain a little more service life until it is practical to replace the bridge deck, superstructure or entire bridge.
Grade B1 seal coat aggregate shall be used whenever a bridge deck is to receive an asphalt wearing surface.
Grade A1 seal coat aggregate shall be used whenever the seal coat is to be the final riding surface. Grade C seal coats are no longer used for bridge applications because of dust issues.
751.1.3.7 Bridge Approach Slabs
Follow guidance for new bridges and see EPG 503 Bridge Approach Slabs.
751.1.3.8 Bridge End Drainage
Follow guidance for new bridges and see EPG 503 Bridge Approach Slabs.
751.1.3.9 Environmental Considerations: Asbestos and Lead
Check TMS1 to see if an asbestos and lead inspection has been performed for a structure and include the applicable note shown immediately below on the Bridge Memorandum under the Special Notes Section. The report in TMS will be located in the Images link under the Media tab for the structure. If there is not a report in TMS, please see the SPM/SLE or contact the Chemical Lab Director with a request. Include the applicable note of the two shown immediately below on the Bridge Memorandum depending on whether an inspection has not been performed or if the inspection report indicates that asbestos or lead, or both are present or not present. (These notes are also applicable for new replacement structures that involve removal of any part of an existing structure.)
- “Asbestos and lead inspections have not been performed on this structure (Bridge/Culvert # XXXXX). The Bridge Division will request these inspections and will include the report in the electronic deliverables folder when submitting contract documents to the Design Division for the Letting (Bridge Item).”
- “Asbestos and lead inspections have been performed on this structure (Bridge/Culvert # XXXXX). Results indicate that asbestos is present lead is present both are present both are not present. The Bridge Division will include the inspection report in the electronic deliverables folder when submitting contract documents to the Design Division for the Letting (Bridge Item).”
1Available only to MoDOT employees. All others: contact the Bridge Division or the Structural Liaison Engineer directly for information related to EPG 751.1.3.9 Environmental Considerations: Asbestos and Lead.
751.1.4 Retaining Walls
751.1.4.1 Overview
This article is intended to help with the issues unique to retaining walls. Many portions of EPG 751.1.2 Bridges/Boxes will still need to be used when working on retaining walls.
Retaining walls are very much like bridges in that they require the many of the same items, such as:
- Bridge Survey
- Bridge Number
- Bridge Memorandum
- Soundings
- Design Layout Sheet
751.1.4.2 Types of Walls
There are two general types of retaining walls used by MoDOT; cast-in-place (CIP) concrete walls and mechanically stabilized earth (MSE) walls. MSE walls are the preferred type due to their lower cost; however, there are several times when MSE walls cannot be used. These include:
- When barrier or railing must be attached to the top of the wall.
- When the underlying soil cannot support the weight of the fill and wall (must use CIP on piling).
- When you don’t have adequate room behind the wall for the reinforcing straps.
In general a minimum reinforcement length of 8.0 ft., regardless of wall height, has been recommended based on historical practice, primarily due to size limitations of conventional spreading and compaction equipment. Shorter minimum reinforcement lengths, on the order of 6.0 ft., but no less than 70 percent of the wall height, can be considered if smaller compaction equipment is used, facing panel alignment can be maintained, and minimum requirements for wall external stability are met.
The requirement for uniform reinforcement length equal to 70 percent of the structure height has no theoretical justification, but has been the basis of many successful designs to-date. Parametric studies considering minimum acceptable soil strengths have shown that structure dimensions satisfying all of the requirements of Article 11.10.5 require length to height ratios varying from 0.8H for low structures, i.e. 10.0 ft., to 0.63 H for high structures, i.e. 40.0 ft.
Significant shortening of the reinforcement elements below the minimum recommended ratio of 0.7H may only be considered when accurate, site specific determinations of the strength of the unreinforced fill and the foundation soil have been made. Christopher et al. (1990) presents results which strongly suggest that shorter reinforcing length to height ratios, i.e. 0.5 H to 0.6 H, substantially increase horizontal deformations.
- The reinforcement length shall be uniform throughout the entire height of the wall, unless substantiating evidence is presented to indicate that variation in length is satisfactory.
- A nonuniform reinforcement length may be considered under the following circumstances:
- Lengthening of uppermost reinforcement layers to beyond 0.7H to meet pullout requirements or to address seismic or impact loads.
- Lengthening of the lowermost reinforcement layers beyond 0.7H to meet overall (global) stability requirements based on the results of a detailed global stability analysis.
- Shortening of bottom reinforcement layers to less than 0.7H to minimize excavation requirements, provided the wall is bearing on rock or very competent foundation soil.
For walls on rock or very competent foundation soil, e.i., SPT > 50, the Bottom reinforcements may be shortened to a greater of 0.4H or 5 ft with the Upper reinforcements lengthened to compensate for external stability issues in lieu of removing rock or competent soil for construction. Design Guidelines for this case are provided in FHWA Publications No. FHWA-NHI-10-024.
For conditions of marginal stability, consideration must be given to ground improvement techniques to improve foundation stability, or to lengthening of reinforcement.
MSE walls are pre-qualified and listed on the internet in three categories:
- Drycast modular block wall (DMBW-MSE) systems
- Wetcast modular block wall (WMBW-MSE) systems
- Precast modular panel wall (PMPW-MSE) systems
Drycast modular block wall systems are battered walls with a maximum height of 10 feet. Drycast modular block wall systems have five major components: Dry cast modular blocks, pre-approved geogrid soil reinforcements, select granular backfill, unit fill and nonreinforced concrete leveling pad.
Wetcast modular block wall systems are battered walls with a maximum height of 15 feet. Wetcast modular block wall systems have five major components: Wetcast modular blocks, pre-approved geogrid soil reinforcements, select granular backfill, unit fill and nonreinforced concrete leveling pad.
Precast modular panel wall systems are vertical walls with heights that may exceed 10 feet. Precast modular panel wall systems have five major components: Precast modular panels, pre-approved soil reinforcements, anchorage devices, select granular backfill, and nonreinforced concrete leveling pad.
Aesthetic enhancements may be used for either CIP or MSE walls. If EPG 751.1.2.33 Aesthetic Enhancements are required by the district, form liners and concrete stains are encouraged rather than actual brickwork and stonework since form liners and concrete stains typically need less maintenance, less loading, less detailing, less detailing, no extra support ledge and produce no risk of delamination or falling work. However, for MSE precast modular panel wall systems only, form liners are required for all panels. For additional information, see EPG 751.24.2 Mechanically Stabilized Earth (MSE) Walls.
Any deviation from the criteria listed shall be discussed with Structural Project Manager.
751.1.4.3 MSE Walls
Generally, both the horizontal alignment and the top of wall elevations are supplied by the district in the Bridge Survey. You do need to check the top of wall elevations to make sure the district accounted for any concrete gutters placed behind the top of the wall (Gutters are necessary if the slope of the fill can direct water towards the top of the wall, i.e., positive sloping and flat backfills). The district should decide whether to use Type A or Type B gutters (Standard Plan 609.00), or Modified Type A or Modified Type B gutters (Standard Plan 607.11) if fencing is required, and where they should drain (to be shown on roadway plans). For general guidelines, see EPG 751.24.2 Mechanically Stabilized Earth (MSE) Walls.
You will also need to set the elevations for the top of the leveling pad. The minimum embedment depth of MSEW, which is the distance between the finished ground line and the top of the leveling pad, is based on this table: (FHWA-NHI-10-024, Table 2-1 and LRFD 11.10.2.2)
Slope in Front of Wall | Minimum Embedment Depth to Top of Leveling Pad |
All Geometries | 2 ft minimum |
Horizontal (walls) | H/20 |
Horizontal (abutments) | H/10 |
3H:1V | H/10 |
2H:1V | H/7 |
1.5H:1V | H/5 |
Where,
H:V = Horizontal to vertical slope in the front of the wall
H = Height of the wall as measured from the top of the leveling pad to the top of the wall
The absolute minimum embedment is 2 ft except when rock is found near surface. When the soundings are returned from the Geotechnical Director, they will include a minimum embedment depth to the top of leveling pad, minimum soil reinforcement length necessary for global stability, bearing resistance and settlement requirements. If rock is encountered during excavation then the contractor shall immediately cease excavating and notify the engineer and contact Geotechnical Section to perform global stability and suggest a required minimum embedment depth to the top of leveling pad and required minimum soil reinforcement length.
Preliminary cost estimating MSE walls is based on the unit price bid history and on the square footage of the area of the face of the wall. The unit price per square foot of wall includes wall elements, leveling pad and backfill. Excavation and retained fill are not included.
If soundings indicate weak material exist, then the designer should investigate that sufficient right of way limits exist to address the required length for the soil reinforcement.
For design requirements of permanent and temporary MSE wall systems, see EPG 720 Mechanically Stabilized Earth Wall Systems.
For additional information, see EPG 751.24.2 Mechanically Stabilized Earth (MSE) Walls.
751.1.4.4 CIP Concrete Walls
Once you determine that you must use a CIP wall, there is very little to do as far as the layout of the structure. Both the horizontal alignment and the top of wall elevations are supplied by the district in the Bridge Survey. You do need to check the top of wall elevations to make sure the district accounted for any concrete gutters placed behind the top of the wall. These are necessary if the slope of the fill will direct water towards the top of the wall. The district should decide whether to use Type A or Type B gutters (Standard Plan 609.00), or Modified Type A or Modified Type B gutters (Standard Plan 607.11) if fencing is required, and where they should drain to.
You will also need to set the elevations for the top of the footing, which should be a minimum of 2 feet below the finished ground line for walls south of Interstate 70 and 3 feet below the finished ground line for walls north of Interstate 70. In tight roadway situations where a barrier or railing is to be placed on top of the wall, make sure that a stem thickness of 16 inches will fit.
Check with the district contact to determine if they want any coping on the exposed face of the wall.
French drains will be used to relieve water pressure behind the CIP wall as a default. If you expect to encounter springs or swampy conditions, then check with the district contact on calling for an underdrain. If the decision is made to use an underdrain, the porous backfill and pipes are Roadway Items and this must be noted on the Bridge Memorandum and Design Layout.
For details on requesting soundings, see EPG 751.1.2.19 Soundings (Borings).
If you have indications that the foundation material is very poor in quality (less than 1 ton per sq. ft. allowable bearing), consider piling and include in the Preliminary Cost Estimate. Preliminary cost estimating should follow EPG 751.1.2.17 Preliminary Cost Estimate and be based upon unit price bid history. More refined cost estimating should follow cost-basing estimating.
751.1.4.5 Obstructions
Any time the retaining wall will encounter obstructions, provisions must be made on the final plans. Therefore, if you are aware of any obstructions, they should be called out on the Bridge Memorandum and Design Layout Sheet. Here are some examples of types of obstructions and how to describe them on the layout:
Type of Obstruction Description Lighting Foundation Std. 45’ Light Pole, Sta. 167+48.50, 16 ft. left Sign Truss Foundation Truss T-72, Sta. 172+41.80, 31 ft. right Drop Inlet 2’ x 2’ Type D Drop Inlet, Sta. 163+12.45, 14 ft. left