Difference between revisions of "Recent Policy Changes in the EPG"

From Engineering_Policy_Guide
Jump to navigation Jump to search
m (EPG 108.1.4)
m
(94 intermediate revisions by the same user not shown)
Line 2: Line 2:
 
{| cellspacing="3"  
 
{| cellspacing="3"  
 
|valign="top" cellspacinepgg="0" cellpadding="5" style="border: 1px solid #74BAAC; background:#DCEDEA"|
 
|valign="top" cellspacinepgg="0" cellpadding="5" style="border: 1px solid #74BAAC; background:#DCEDEA"|
'''[[:Category:108 Prosecution and Progress#Professional Service Contract Labor|EPG 108.1.4, Professional Service Contract Labor]]'''
+
'''[[153.18 Multimodal#MO53|EPG 153.18 Multimodal]]'''
  
4/28/20: New guidance is now available for the relatively rare occurrence of professional service contract labor.
+
11/24/20: Information is now available for the new template, MO53 Preliminary Engineering Master Agreement.
  
'''[[237.8 Contract Time#Contract Administrative Costs|EPG 237.8.2 Liquidation Damages]]'''
+
'''[[LPA:136.11 Local Public Agency Construction#136.11.13 Documentation Requirements|EPG 136.11.13 Documentation Requirements]]
  
4/27/20:  The "Contract Administrative Costs" table has been updated.
+
11/23/20: MoDOT will no longer be approving specific software for use; the LPA must ensure the software chosen meets the outlined criteria. Guidance about what should be documented in the construction diaries was clarified in [[LPA:136.11 Local Public Agency Construction#136.11.13.1 Project Diaries|EPG 136.11.13.1 Project Diaries]]. 
  
'''New QRG'''
+
'''[[751.50 Standard Detailing Notes#I4. Fiber Reinforced Polymer (FRP) Wrap - Bent Cap Shear Strengthening|EPG 751.50, I4. Fiber Reinforced Polymer (FRP) Wrap - Bent Cap Shear Strengthening]]'''
  
11/14/19: The new [http://epg.modot.mo.gov/forms/CM/AWP_CO_DailyWorkReport_Deleting_Postings_and_Acceptance_Records.doc AWP CO Daily Work Report, Deleting DWR Postings and Acceptance Records QRG] is now available.  
+
11/20/20: New standard notes for Standard Drawing RHB08 to clarify note regarding design force.
  
'''[[236.17 Junkyards|EPG 236.17 Junkyards]]'''
+
'''[[147.3 Job Order Contracting (JOC)#147.3.6 Closing JOC Contracts|EPG 147.3.6 Closing JOC Contracts]]'''
  
4/22/20: Guidance has been clarified and updated.
+
11/12/20: Clarified that a Materials Summary is not needed for Job Order Contracts.
  
'''[[:Category:134 Engineering Professional Services|EPG 134 Engineering Professional Services]]'''
+
'''Wing Lengths and C Bars'''
  
4/17/20: The process for consultant agreements has been streamlined and other guidance has been clarified.
+
11/12/20: In [[751.1 Preliminary Design#751.1.2.2 Wing Lengths|EPG 751.1.2.2 Wing Lengths]], guidance was added to consider making short turned-back wings sufficiently long so that the Type D barrier end section does not require extensive. In [[751.12 Barriers, Railings, Curbs and Fences#751.12.1.2.1 Slip Forming|EPG 751.12.1.2.1 Slip Forming]], replaced guidance about determining C bars lengths with actual length of C bars.
  
'''Reinforcement of Concrete Pile Cap Intermediate Bents and Concrete Pile Cap Integral End Bents'''
+
'''[[media:616.8.10 interim.pdf|Fig. 616.8.10 - TMA Flagger - Lane Closure on Two-Lane Highways Using TMA Flaggers - DE/CM/MT]]'''
  
4/17/20: Guidance was clarified about additional flexure reinforcement requirements between piles for pile cap intermediate bents and integral end bents and skin reinforcement spacing requirements.  This guidance was updated primarily in [[751.32 Concrete Pile Cap Intermediate Bents#751.32.4.1 Typical Pile Cap Bent|EPG 751.32.4.1 Typical Pile Cap Bent and EPG 751.32.4.2 Encased Pile Cap Bent]] as well as [[751.35 Concrete Pile Cap Integral End Bents#751.35.4.1 Wide Flange Beams & Plate Girders|EPG 751.35.4.1 Wide Flange Beams & Plate Girders and EPG 751.35.4.2 Prestressed I-Girders, Bulb-Tee Girders and NU-Girders]].
+
11/10/20: Interim guidance for TMA flagger operations is now available in [[616.8 Typical Applications (MUTCD 6H)|EPG 616.8 Typical Applications]].
  
'''[[616.6 Temporary Traffic Control Zone Devices (MUTCD 6F)#Fig. 616.6.87.1 Rumble Strip Placement in Flagging Operations|EPG 616.6.87 Temporary Rumble Strips]]'''
+
'''[[751.5 Structural Detailing Guidelines|EPG 751.5 Structural Detailing Guidelines]]'''
  
4/14/20: In Figures 616.6.87.1 and 616.6.87.2, the short-term Rumble Strip Placement spacing was updated. For speed limits from 50-55 mph, the spacing is now 20 feet. For speed limits from 60-70 mph, the spacing is now 30 feet.
+
11/9/20: Guidance has been added ([[751.5 Structural Detailing Guidelines#751.5.9.2.1.1 Reinforcing Callouts|EPG 751.5.9.2.1.1 Reinforcing Callouts]], for example) to standardize the format for reinforcing callouts.
  
'''Bluebeam Revu'''
+
'''[[121.3 The Statewide Transportation Improvement Program (STIP)|EPG 121.3 The Statewide Transportation Improvement Program (STIP)]]'''
  
4/10/20: In [[:Category:239 Construction Inspection Guidelines for Final Plans|EPG 239 Construction Inspection Guidelines for Final Plans]], district construction staff can now easily access vital Bluebeam Revu resources to prepare final as-built plans. These resources include [[media:239 Creating Digital IDs in Bluebeam Revu.pdf|Creating Digital IDs in Bluebeam Revu]], [[media:239 Preparing As-Built Plans.pdf|Preparing As-Built (Final) Plans in Construction Using Bluebeam Revu]], [[media:239 Revu 2015 Training Manual.pdf|Bluebeam Revu Training Manual (2015)]] and [[media:239 Where to Save Stamps.pdf|Where to Save Stamps]].
+
11/5/20: STIP information and the annual process to update the STIP were updated to current practice.
  
'''Fracture Critical Member (FCM) Notes'''
+
'''[[751.50 Standard Detailing Notes#(A2.9)|Updated Standard Detailing Note]]'''
  
4/720: Fracture Critical Member (FCM) notes have been revised and moved from [https://epg.modot.org/index.php/751.5_Structural_Detailing_Guidelines#751.5.9.3.3_Fracture_Control_Plan_.28FCP.29 EPG 751.5.9.3.3] to [https://epg.modot.org/index.php/751.50_Standard_Detailing_Notes#A5._Miscellaneous EPG 751.50 A5.1] and [[751.50 Standard Detailing Notes#(H1.23)|EPG 751.50 H1.23]].
+
11/2/20: Verbiage in A2.9 was updated to match new Standard Plan wording.
  
'''[[127.29 Storm Water#127.29.8 MCM 6: Pollution Prevention/Good Housekeeping|EPG 127.29.8 MCM 6: Pollution Prevention/Good Housekeeping]]'''
+
'''[[:Category:129 Public Involvement|EPG 129 Public Involvement]] and [[127.14 National Environmental Policy Act (NEPA) Classification and Documents#127.14.3.1 Categorical Exclusion|EPG 127.14.3.1 Categorical Exclusion]]'''
  
4/7/20: The guidance for the Facility Runoff Control Plan form has been expanded.
+
10/30/20: Updated Programmatic Categorical Exclusion (PCE) and “virtual” public involvement requirements to bring policy into compliance with the federal NEPA regulations. EPG 129 Public Involvement was generally re-written.
  
'''[[236.16 Outdoor Advertising|EPG 236.16 Outdoor Advertising]]'''
+
'''[[751.1 Preliminary Design#751.1.2.22 Types of Piling|EPG 751.1.2.22 Types of Piling]] and [[751.24 LFD Retaining Walls#MSE Wall Construction:|EPG 751.24.2.1 Design, MSE Wall Construction: Pipe Pile Spacers Guidance]]'''
  
4/6/20: Guidance was clarified and updated to current practice. Vegetation policies were updated to match traffic policies for work on right of way.
+
10/30/20: Guidance clarified pile spacer embedment requirements when rock is anticipated within a 5 - 10 ft. zone below the MSE wall leveling pad.
  
'''[[:Category:113 Construction Inspection Guidance for Contractor's Claims|EPG 113 Construction Inspection Guidance for Contractor's Claims]]'''
+
'''Sand Barrel Impact Attenuator Arrays'''
  
4/2/20: The procedures for handling contractor claims has been updated.
+
10/29/20: Guidance in [[:Category:612 Impact Attenuators#612.2 Sand-Filled Impact Attenuators (Sand Barrels)|EPG 612.2 Sand-Filled Impact Attenuators (Sand Barrels)]] and [[:Category:612 Impact Attenuators#Sand-Filled Impact Attenuator Array|EPG 612.3 Construction Inspection Guidelines]] was updated to clarify how the sand barrel impact attenuator arrays are paid for and used in work zones.
  
'''[[903.9 General Information Signs#903.9.9 City/County Limit Signs (I4, I5, I6 Series)|EPG 903.9.9 City/County Limit Signs (I4, I5, I6 Series)]]'''
+
'''[[:Category:134 Engineering Professional Services#134.2.4 Consultant Solicitation and Selection Process – Standard Solicitation Method for On-Call Cost Plus Fixed Fee Contracts|EPG 134.2.4 Consultant Solicitation and Selection Process – Standard Solicitation Method for On-Call Cost Plus Fixed Fee Contracts]]'''
  
4/1/20: Guidance was clarified for where inadequate space exists to install a city limits sign at the standard location.
+
10/28/20: On-call consultant guidance has been updated.
  
'''[[153.8 Design#DE62|Design Division eAgreement Contracts]]'''
+
'''[[237.8 Contract Time#237.8.2 Liquidated Damages|EPG 237.8.2 Liquidated Damages]]'''
  
3/31/20: New guidance is available for DE62 Stream Wetland Credit Purchase Agreement and DE66 TCF Bat Habitat Credit Purchase Agreement.
+
10/26/20: Guidance was clarified to provide justification for higher liquidated damages.
  
'''[[:Category:402 Bituminous Surface Leveling|Contract Leveling Course (CLC)]] and [[:Category:409 Seal Coat|Seal Coat]]'''  
+
'''[[:Category:1048 Pavement Marking Material#1048.2.7.3 Acceptance|EPG 1048.2.7.3 Acceptance]]'''
  
3/25/20: The Contract Leveling Course and Seal Coat guidelines, as well as their pdf files, were updated.  
+
10/22/20: Guidance has been updated to reflect the current process for how acrylic waterborne and high build acrylic waterborne traffic marking are accepted.
  
'''[[147.4 Fixed Price Variable Scope (FPVS) Contracting|EPG 147.4 Fixed Price Variable Scope Contracting]]'''
+
'''Minimum Wall Thickness for CIP Piles and Limited Nominal Axial Resistance of CIP Piles Embedded and Tipped in Cohesionless Soils'''
  
3/25/20: This new article provides guidance for the new contracting method, FPVS Contracting.
+
10/19/20: Guidance in [[751.36 Driven Piles|EPG 751.36 Driven Piles]] (particularly in [[751.36 Driven Piles#751.36.2.2.2 Cast-In-Place (CIP) Pile|EPG 751.36.2.2.2 Cast-In-Place (CIP) Pile]], [[751.36 Driven Piles#751.36.5.7.1 Design Values for Individual HP Pile|EPG 751.36.5.7.1 Design Values for Individual HP Pile]], and [[751.36 Driven Piles#751.36.5.10 Pile Nominal Axial Compressive Resistance|EPG 751.36.5.10 Pile Nominal Axial Compressive Resistance]]) was updated to implement maximum axial loads in sands and clarified minimum nominal wall thickness requirements for CIP pile. Numerous standard detailing notes in [[751.50 Standard Detailing Notes#G. Substructure Notes|EPG 751.50, G. Substructure Notes]] for hooks of vertical bar requirements for column and CIP piles were also clarified.
  
'''[[153.19 Right of Way|EPG 153.19 Right of Way]]'''
+
'''[[236.7 Negotiation#236.7.4.4 Agreement for Purchase of Real Estate|EPG 236.7.4.4 Agreement for Purchase of Real Estate, When Agreement for Purchase of Real Estate is Used]]'''
  
3/24/20: New eAgreements, RW55 - RW60, has been added to the listings.
+
10/9/20: To reflect legal requirements, Tax Lien guidance was added.  
  
'''[[:Category:642 Pedestrian Facilities|EPG 642 Pedestrian Facilities]]'''
+
'''[[:Category:108 Prosecution and Progress#108.16 Project Dates|EPG 108.16 Project Dates]]'''
  
3/20/20: Please closely read this article since most of the article has been re-written.  EPG 642.1 through EPG 642.5 have been slightly revised and renumbered as EPG 642.8 through EPG 642.12.
+
9/30/20: EPG 108.16 has been rewritten to reflect the move to AWP.
  
'''[[127.27 Guidelines for Obtaining Environmental Clearance for Off-Site Activities|EPG 127.27 Guidelines for Obtaining Environmental Clearance for Off-Site Activities]]'''
+
'''[[751.50 Standard Detailing Notes#(J1.21a)|Updated Standard Detailing Note]]'''
  
3/16/20: Borrow practices have been clarified and new permit information has been provided.
+
9/28/20: Dowel requirements for inverted U-shape precast coping for large block (panel) MSE walls in Standard Note J1.21a were clarified.  
  
'''[http://epg.modot.mo.gov/forms/CM/DBE_and_non_DBE_Subcontractor_Reporting_Form.pdf DBE and Non-DBE Subcontractor Reporting Form]'''
+
'''[[751.50 Standard Detailing Notes#(H7.8.2) Use note|New Standard Detailing Note]]'''
  
3/16/20: Guidance for this form is now available in [[:Category:108 Prosecution and Progress#108.1.3 Disadvantaged Business Enterprises (DBE) Subcontracting|EPG 108.1.3 Disadvantaged Business Enterprises (DBE) Subcontracting]].
+
9/23/20: New Note H7.8.2 is available when requiring epoxy-mastic primer coating on galvanized drain support brackets that come in contact with weathering steel beams/girders.
  
'''[[127.12 Air Quality|EPG 127.12 Air Quality]]'''
+
'''[[237.5 Special Provisions|EPG 237.5 Special Provisions]]'''
  
3/13/20:  Guidance was clarified.
+
9/22/20:  Guidance has been clarified and updated to current practice.
  
'''[[147.3 Job Order Contracting (JOC)#147.3.10 Guardrail and Guard Cable Repair|EPG 147.3.10 Guardrail and Guard Cable Repair]]'''
+
'''[[127.27 Guidelines for Obtaining Environmental Clearance for Off-Site Activities|EPG 127.27 Guidelines for Obtaining Environmental Clearance for Off-Site Activities]]'''
  
3/13/20: This new guidance assists JOC administrators to identify high priority repairs for guardrail and guard cable.
+
9/16/20: Guidance has been updated to reflect current practice.
  
'''Preliminary Structure Guidance'''
+
'''[[751.36 Driven Piles#751.36.5.8 Additional Provisions for Pile Cap Footings|EPG 751.36.5.8 Additional Provisions for Pile Cap Footings]]'''
  
3/9/20: Superstructure selection guidance has been updated throughout [[751.1 Preliminary Design#751.1.2.7 Structure Type Selection|EPG 751.1.2.7 Structure Type Selection to EPG 751.1.2.17 Preliminary Cost Estimate]].  Pricing and bridge replacement information was updated.
+
9/16/20: Guidance has been updated to clarify pile uplift design requirements for pile cap footing and to implement DSB-16-02 requirements.
  
'''[[127.26 Environmental Classification|EPG 127.26 Environmental Classification]]'''
+
'''[[:Category:203 Roadway and Drainage Excavation, Embankment and Compaction#203.2.3.1.2 Embankment in Place (Contractor-Furnished Borrow)|EPG 203.2.3.1.2 Embankment in Place (Contractor-Furnished Borrow)]]'''
  
3/4/20: The definitions of Categorical Exclusion, Environmental Assessment and Environmental Impact Statement were updated.
+
9/16/20: Contractor-furnished borrow guidance has been updated to current practice.
  
'''[[LPA:136.4 Consultant Selection and Consultant Contract Management#Environmental.|EPG 136.4.2.4.3 Using the LPA On-Call Consultant List]]'''
+
'''[[127.2 Historic Preservation and Cultural Resources|EPG 127.2 Historic Preservation and Cultural Resources]]'''
  
2/27/20: Two new categories (Environmental and Historic Preservation) have been added to the LPA on-call consultant guidance.
+
9/11/20: Guidance has been updated to reflect changes in the Section 106 processes that have incrementally occurred over the last few years.

Revision as of 15:29, 24 November 2020

EPG 153.18 Multimodal

11/24/20: Information is now available for the new template, MO53 Preliminary Engineering Master Agreement.

EPG 136.11.13 Documentation Requirements

11/23/20: MoDOT will no longer be approving specific software for use; the LPA must ensure the software chosen meets the outlined criteria. Guidance about what should be documented in the construction diaries was clarified in EPG 136.11.13.1 Project Diaries.

EPG 751.50, I4. Fiber Reinforced Polymer (FRP) Wrap - Bent Cap Shear Strengthening

11/20/20: New standard notes for Standard Drawing RHB08 to clarify note regarding design force.

EPG 147.3.6 Closing JOC Contracts

11/12/20: Clarified that a Materials Summary is not needed for Job Order Contracts.

Wing Lengths and C Bars

11/12/20: In EPG 751.1.2.2 Wing Lengths, guidance was added to consider making short turned-back wings sufficiently long so that the Type D barrier end section does not require extensive. In EPG 751.12.1.2.1 Slip Forming, replaced guidance about determining C bars lengths with actual length of C bars.

Fig. 616.8.10 - TMA Flagger - Lane Closure on Two-Lane Highways Using TMA Flaggers - DE/CM/MT

11/10/20: Interim guidance for TMA flagger operations is now available in EPG 616.8 Typical Applications.

EPG 751.5 Structural Detailing Guidelines

11/9/20: Guidance has been added (EPG 751.5.9.2.1.1 Reinforcing Callouts, for example) to standardize the format for reinforcing callouts.

EPG 121.3 The Statewide Transportation Improvement Program (STIP)

11/5/20: STIP information and the annual process to update the STIP were updated to current practice.

Updated Standard Detailing Note

11/2/20: Verbiage in A2.9 was updated to match new Standard Plan wording.

EPG 129 Public Involvement and EPG 127.14.3.1 Categorical Exclusion

10/30/20: Updated Programmatic Categorical Exclusion (PCE) and “virtual” public involvement requirements to bring policy into compliance with the federal NEPA regulations. EPG 129 Public Involvement was generally re-written.

EPG 751.1.2.22 Types of Piling and EPG 751.24.2.1 Design, MSE Wall Construction: Pipe Pile Spacers Guidance

10/30/20: Guidance clarified pile spacer embedment requirements when rock is anticipated within a 5 - 10 ft. zone below the MSE wall leveling pad.

Sand Barrel Impact Attenuator Arrays

10/29/20: Guidance in EPG 612.2 Sand-Filled Impact Attenuators (Sand Barrels) and EPG 612.3 Construction Inspection Guidelines was updated to clarify how the sand barrel impact attenuator arrays are paid for and used in work zones.

EPG 134.2.4 Consultant Solicitation and Selection Process – Standard Solicitation Method for On-Call Cost Plus Fixed Fee Contracts

10/28/20: On-call consultant guidance has been updated.

EPG 237.8.2 Liquidated Damages

10/26/20: Guidance was clarified to provide justification for higher liquidated damages.

EPG 1048.2.7.3 Acceptance

10/22/20: Guidance has been updated to reflect the current process for how acrylic waterborne and high build acrylic waterborne traffic marking are accepted.

Minimum Wall Thickness for CIP Piles and Limited Nominal Axial Resistance of CIP Piles Embedded and Tipped in Cohesionless Soils

10/19/20: Guidance in EPG 751.36 Driven Piles (particularly in EPG 751.36.2.2.2 Cast-In-Place (CIP) Pile, EPG 751.36.5.7.1 Design Values for Individual HP Pile, and EPG 751.36.5.10 Pile Nominal Axial Compressive Resistance) was updated to implement maximum axial loads in sands and clarified minimum nominal wall thickness requirements for CIP pile. Numerous standard detailing notes in EPG 751.50, G. Substructure Notes for hooks of vertical bar requirements for column and CIP piles were also clarified.

EPG 236.7.4.4 Agreement for Purchase of Real Estate, When Agreement for Purchase of Real Estate is Used

10/9/20: To reflect legal requirements, Tax Lien guidance was added.

EPG 108.16 Project Dates

9/30/20: EPG 108.16 has been rewritten to reflect the move to AWP.

Updated Standard Detailing Note

9/28/20: Dowel requirements for inverted U-shape precast coping for large block (panel) MSE walls in Standard Note J1.21a were clarified.

New Standard Detailing Note

9/23/20: New Note H7.8.2 is available when requiring epoxy-mastic primer coating on galvanized drain support brackets that come in contact with weathering steel beams/girders.

EPG 237.5 Special Provisions

9/22/20: Guidance has been clarified and updated to current practice.

EPG 127.27 Guidelines for Obtaining Environmental Clearance for Off-Site Activities

9/16/20: Guidance has been updated to reflect current practice.

EPG 751.36.5.8 Additional Provisions for Pile Cap Footings

9/16/20: Guidance has been updated to clarify pile uplift design requirements for pile cap footing and to implement DSB-16-02 requirements.

EPG 203.2.3.1.2 Embankment in Place (Contractor-Furnished Borrow)

9/16/20: Contractor-furnished borrow guidance has been updated to current practice.

EPG 127.2 Historic Preservation and Cultural Resources

9/11/20: Guidance has been updated to reflect changes in the Section 106 processes that have incrementally occurred over the last few years.