- 12:43, 19 April 2022 diff hist +9,214 Category:805 Seeding Guidance for seeding, mulching, and temporary seeding reflects the new standard seed mixes, fertilizer, and lime rates (as shown in the new Standard Plan 805.00 Seeding) will promote a more effective vegetative establishment. New guidance for cool season and warm season grasses is available. A new seed species picture guide is available in EPG 805.2.4 Acceptance to assist with general inspection and acceptance of vegetative covers.
- 12:27, 19 April 2022 diff hist +1,642 Category:802 Mulching Per Env'l, guidance for mulching reflects the new standard seed mixes, fertilizer, and lime rates (as shown in the new Standard Plan 805.00 Seeding) will promote a more effective vegetative establishment. Mulching will not be required for final seeded areas where temporary seeding is planned for temporary stabilization of areas to receive warm season grasses. current
- 11:22, 19 April 2022 diff hist +424 Category:403 Asphaltic Concrete Pavement →403.1.19 Acceptance of Material (Sec 403.19): Per CM, the maximum number of contractor QC sublots that can be used for one lot of superpave asphalt pavement is 28. Regardless of lot size, QA testing will always be at a frequency of one per four sublots.
- 11:09, 19 April 2022 diff hist -306 903.3 Ground-Mounted Sign Supports Per TS, in EPG 903.3.4.3 Perforated Square Steel Tube Posts (PSST), guidance for PSST anchor installations has been updated and clarified.
- 10:37, 19 April 2022 diff hist -38 Category:1064 Temporary Concrete Traffic Barrier Per DE and TS, guidance now reflects that the use of non-MASH 2016 temporary traffic control devices barriers is being discontinued. All temporary traffic control devices on a project must be NCHRP 350 or MASH 2016 Test Level 3 compliant. current
- 10:36, 19 April 2022 diff hist +13 Category:1063 Temporary Traffic Control Devices Per DE and TS, guidance now reflects that the use of non-MASH 2016 temporary traffic control devices barriers is being discontinued. All temporary traffic control devices on a project must be NCHRP 350 or MASH 2016 Test Level 3 compliant. current
- 10:34, 19 April 2022 diff hist -1,503 617.2 Construction Inspection Guidelines for Sec 617 Per DE and TS, guidance now reflects that the use of non-MASH 2016 temporary traffic control devices barriers is being discontinued. All temporary traffic control devices on a project must be NCHRP 350 or MASH 2016 Test Level 3 compliant. The use of two-loop temporary Type F concrete traffic barrier shall not be allowed after January 1, 2023.
- 10:29, 19 April 2022 diff hist +36 617.1 Temporary Traffic Barriers Per DE and TS, guidance now reflects that the use of non-MASH 2016 temporary traffic control devices barriers is being discontinued. All temporary traffic control devices on a project must be NCHRP 350 or MASH 2016 Test Level 3 compliant.
- 10:17, 19 April 2022 diff hist -217 616.23 Traffic Control for Field Operations →616.23.2.5 Temporary Traffic Control Devices: Per DE and TS, guidance now reflects that the use of non-MASH 2016 temporary traffic control devices barriers is being discontinued. All temporary traffic control devices on a project must be NCHRP 350 or MASH 2016 Test Level 3 compliant.
- 10:15, 19 April 2022 diff hist -2 m 616.19 Quality Standards for Temporary Traffic Control Devices →616.19.2.15 Traffic Management
- 10:12, 19 April 2022 diff hist -208 616.19 Quality Standards for Temporary Traffic Control Devices →616.19.2.7 Changeable Message Sign/Flashing Arrow Panels/Traffic Signals: Per DE and TS, guidance now reflects that the use of non-MASH 2016 temporary traffic control devices barriers is being discontinued. All temporary traffic control devices on a project must be NCHRP 350 or MASH 2016 Test Level 3 compliant.
- 10:09, 19 April 2022 diff hist -125 616.18 Construction Inspection Guidelines for Sec 616 Per DE and TS, guidance now reflects that the use of non-MASH 2016 temporary traffic control devices barriers is being discontinued. All temporary traffic control devices on a project must be NCHRP 350 or MASH 2016 Test Level 3 compliant.
- 10:04, 19 April 2022 diff hist -632 616.6 Temporary Traffic Control Zone Devices (MUTCD 6F) Per DE and TS, guidance now reflects that the use of non-MASH 2016 temporary traffic control devices barriers is being discontinued. All temporary traffic control devices on a project must be NCHRP 350 or MASH 2016 Test Level 3 compliant.
- 09:56, 19 April 2022 diff hist -3 Category:612 Impact Attenuators Per DE and TS, guidance now reflects that the use of non-MASH 2016 temporary traffic control devices barriers is being discontinued. All temporary traffic control devices on a project must be NCHRP 350 or MASH 2016 Test Level 3 compliant.
- 14:31, 18 April 2022 diff hist +167 m Recent Policy Changes in the EPG EPG 236.7
- 14:26, 18 April 2022 diff hist +1,138 m 236.7 Negotiation Per RW, additional guidance for greater clarity about what is needed from property owners to close on the properties either with MoDOT or a title company.
- 08:01, 18 April 2022 diff hist 0 N File:236.16.2 2022 map.jpg current
- 08:00, 18 April 2022 diff hist -16 m 236.16 Outdoor Advertising →236.16.2 Organization & Personnel: Per ODA, updated contact info and map
- 14:42, 14 April 2022 diff hist 0 m 236.6 Appraisal and Appraisal Review →236.6.3.3 Waiver Valuation: Per RW, increased the maximum threshold for waiver valuation reports from $10,000 to $25,000, per FHWA consent.
- 14:38, 14 April 2022 diff hist 0 m 236.6 Appraisal and Appraisal Review Per RW, increased the maximum threshold for waiver valuation reports from $10,000 to $25,000, per FHWA consent.
- 12:39, 14 April 2022 diff hist -19,511 m Category:113 Construction Inspection Guidance for Contractor's Claims Per CM, moved contents to EPG 105.16 current Tag: Replaced
- 11:23, 14 April 2022 diff hist +19,826 m Category:105 Control of Work →105.16 Controversies and Claims for Adjustment (Sec 105.16): Per CM, moved content of EPG 113 Construction Inspection Guidance for Contractor's Claims to EPG 105.16
- 10:29, 14 April 2022 diff hist -11 m 903.5 Regulatory Signs →903.5.20 DO NOT ENTER Sign (R5-1) (MUTCD Section 2B.37): minor correction
- 09:23, 13 April 2022 diff hist 0 N File:905.2.14.2.5.jpg current
- 09:22, 13 April 2022 diff hist -45 m 905.2 Traffic Studies Per TS, updated text to current verbiage by changing "accidents" to "crashes", "SWAR" changed to "SWCR" and "AR" to "CR". current
- 10:44, 12 April 2022 diff hist +1 m Category:403 Asphaltic Concrete Pavement →403.1.19 Acceptance of Material (Sec 403.19)
- 10:26, 12 April 2022 diff hist +8 m Category:126 Location Study and Alternatives Analysis Per Env'l, replaced CE2 Form with existing example version of CE3 Form. Also, updated archaic dot file to dotx
- 07:22, 12 April 2022 diff hist +27 m 751.22 Prestressed Concrete I Girders →751.22.2.5 Pretensioned Anchorage Zones: minor cosmetic revisions
- 14:45, 11 April 2022 diff hist -30 m Category:1011 Geotextile Per MT, updated link current
- 14:30, 11 April 2022 diff hist -246 m Recent Policy Changes in the EPG EPG 751.22
- 13:59, 11 April 2022 diff hist 0 N File:751.22.3.2.6 2022.jpg current
- 13:57, 11 April 2022 diff hist 0 N File:751.22.3.2.5 2022.jpg current
- 13:53, 11 April 2022 diff hist 0 N File:751.22.3.2.4 2022.jpg current
- 13:51, 11 April 2022 diff hist 0 N File:751.22.3.2.3 2022.jpg current
- 13:49, 11 April 2022 diff hist 0 N File:751.22.3.2.2 2022.jpg current
- 13:44, 11 April 2022 diff hist 0 N File:751.22.3.2.1 2022.jpg current
- 13:40, 11 April 2022 diff hist 0 N File:751.22.2.5 2022.jpg current
- 13:34, 11 April 2022 diff hist +1,487 m 751.22 Prestressed Concrete I Girders Per BR, revision allows a larger number of bonded strands for many of these girders, effectively increasing the span limits for these girders. Expanded guidance in EPG 751.22.3.2 to eliminate or reduce conflict between lowest middle two strands and the B bars.
- 10:31, 11 April 2022 diff hist 0 m 642.8 Sidewalk Design Criteria minor update to ADA Checklist links
- 10:30, 11 April 2022 diff hist -1 m Category:150 Quality Management minor update to ADA Checklist links
- 10:29, 11 April 2022 diff hist 0 m LPA:136.12 Figures, Glossary and Other Useful Links →136.12.1 Figures: minor update to ADA Checklist links
- 10:28, 11 April 2022 diff hist 0 m LPA:136.11 Local Public Agency Construction minor update to ADA Checklist links
- 10:27, 11 April 2022 diff hist 0 m LPA:136.9 Plans, Specs and Estimates (PSE) minor update to ADA Checklist links
- 10:25, 11 April 2022 diff hist 0 m Category:101 Standard Forms →Construction and Materials: minor update to ADA Checklist link
- 07:10, 11 April 2022 diff hist -157 m 171.4 Shoulders and Approaches →S&A(C2) Culvert Ends: updated broken std plan links
- 15:19, 6 April 2022 diff hist +2 m 153.20 Right of Way Per RW and CCO, minor updates to RW51 contract requirements. This agreement should include the approval as to form and attestation signature.
- 12:40, 6 April 2022 diff hist +6 m Category:101 Standard Forms →Bridge
- 12:39, 6 April 2022 diff hist +79 m Category:101 Standard Forms →Bridge: Per BR, updated link to Culvert Hydraulics Report
- 15:16, 5 April 2022 diff hist +24 m Recent Policy Changes in the EPG EPG 127.2.5
- 15:11, 5 April 2022 diff hist +386 m 127.2 Historic Preservation and Cultural Resources →127.2.5 Approximate Timelines for Section 106 Compliance: Per Env'l, Clarifying the timelines for completing the Section 106 of the National Historic Preservation Act review process