Recent Policy Changes in the EPG

From Engineering Policy Guide
Jump to navigation Jump to search


March 1, 2025
  • Adding a new policy in EPG 119 Project Schedules to standardize and centralize the project schedules for every project in the STIP and provide guidelines for how schedules are modified, updated, and communicated throughout the department.
March 18, 2025
March 6, 2025
March 5, 2025
March 4, 2025
February 18, 2025
February 2, 2025
January 31, 2025
January 30, 2025
  • Add a note I1.62 stating that the contractor is responsible for asbestos abatement if they choose to remove the handrail to slip-form the blockout in EPG 751.50 - I1 General.
  • Updated EPG 747.2.3.4 Profile Sheets and 747.2.3.6.3 Additional Information for Railroad Crossings, field shots have been increased to 1,000 ft. each side of structure.
  • Revisions to EPG 136.3.10.1 adds language to allow special road districts to receive soft match credit, and further requires that any agency doing so must be a legally identified politial subdivision in good financial standing.
January 29, 2025
January 28, 2025
January 27, 2025
  • Updated Web Wall guidance in EPG 751.1.2.28 Web Walls to match current practice.
  • Increased minimum specified thickness for polyester polymer concrete from 3/4" to 1" minimum thickness to ensure not less than 3/4" applied in field in EPG 751.1.3.6 Deck Treatment.
January 24, 2025
  • Added EPG 233.5 Intersection Alternatives providing additional guidance about intersection types implemented throughout the state with more context for consideration and comparisons.
  • Added EPG 241.7 Roundabout Aesthetic Structure regarding new policy for determining what is allowed and the submittal/approval processes for roundabout structures on MoDOT right of way.
January 10, 2025
  • Update to EPG 110.1 Wage Rates to provide clarity to who is responsible for running the report.
January 9, 2025
January 3, 2025
  • Updated EPG 141.1 Cost Share Program to reflect the Commission policy change that increased the set aside portion for economic development from 10% to 20%.
  • EPG Fig. 136.4.18 is being revised to include supporting documentation requirements related to consultant travel expenses.
January 2, 2025
December 24, 2024
December 13, 2024
December 12, 2024
December 11, 2024
  • Removed TR17 Traffic Engineering Studies and TR18 Towing Services Agreement from EPG 153.21 Traffic, they are no longer used.
November 27, 2024
  • Added guidance to EPG 109.12.2 Change Order Approval to disallow the practice of contractors typing disclaimers on change orders when they sign.
  • Revised EPG 751.24.2.1 Design to allow wetcast modular wall blocks in splash zones for non-critical structural application.
  • Updated EPG 751.32.4.2 Encased Pile Cap Bent to allow #4 @ 12" (min.) stirrup bars for encased pile cap bents instead of #5 @ 12” (min.).
November 21, 2024
November 20, 2024
  • Updated EPG 108.16 Project Dates the internal process was rearranged so dates flow with life of project. Removed references to actual and projected dates, they are no longer used in AWP software.
October 11, 2024
October 10, 2024
October 9, 2024
September 16, 2024
July 22, 2024
July 18, 2024
July 11, 2024
  • Current armor detail is no longer in production. An optional armor detail is provided in bridge standard drawings. Added a standard note for those drawings to EPG 751.50.
July 3, 2024
July 2, 2024
  • EPG 941.9.8.4 Culvert Pipe updates the terminology of the plastic pipes and updates the guidance on use with driveways.
June 27, 2024
June 21, 2024
June 5, 2024
May 28, 2024
  • EPG 105.15.2 Final Acceptance was updated to clarify the DBE Final Payment Form now serves as the required DBE Participation List and Final Verification.
May 23, 2024
May 16, 2024
May 13, 2024
  • Updated the Missouri Uniform Crash Report Preparation Manual in EPG 907.4.
May 10, 2024
  • EPG 902.15.3.1 has been revised to allow core team to specify signal detection type to be documented with memo in eProjects instead of a design exception.
March 27, 2024
March 14, 2024
January 23, 2024